Reinforced underwater concrete floor for Rottemerentunnel

Clever design built entirely underwater
Consortium De Groene Boog, comprising Besix, Dura Vermeer, Van Oord, TBI (Mobilis, Croonwolter&dros), Rebel and John Laing, is delivering the A16 Rotterdam project on behalf of Rijkswaterstaat. The new A16 Rotterdam will be an 11-kilometre national road between the A16/A20 at Terbregseplein and the A13 at Rotterdam The Hague Airport.
The 11-kilometre route includes the new Rottemerentunnel, which will be 2.2 km long (3.0 km including the entrance and exit ramps). It is an unusual project, as the decision was made to carry out the work underwater. Underwater concrete is being used, placed by diving teams. GWW Magazine visited the construction site and spoke to Kenneth Wyns, tunnel design manager, Wim Guis, tunnel project manager, and Sander Tetteroo, head of civil engineering construction for the tunnel.

Do more with less material
“Reinforced underwater concrete is used increasingly often, but this is the first time it has been used on this scale, in this case over 2.2 km,” says Guis. “The advantage is that less concrete is needed, resulting in a lower MKI score. The downside is that all the work has to be carried out underwater: excavation, cleaning the pile heads, all 7,700 of them, installing the expansion joint beams, each weighing 90 tonnes, placing the reinforcement and pouring the concrete itself. On peak days, 35 to 40 diving teams are working on site.” The Rottemerentunnel is therefore an unusual project in every respect. It runs right through the Lage Bergse Bos near Rotterdam and is divided into 34 construction pits ranging in length from 50 to 200 metres.

Tunnel design originated during the tender
Wyns explains how the design was developed: “We wanted to achieve the most suitable MKI score in DuboCalc while maintaining quality. The key question was: what can we do with less material? What would be the most sustainable design? The calculations showed that there was a ‘vertical balance’. During the temporary phase, the upward force on the floor was of the same order of magnitude as the downward soil pressure in the permanent phase, so we could use piles of a single length. Economically, that was ideal. By opting for reinforced underwater concrete, we could use fewer piles. If we had chosen unreinforced concrete in this case, we would have needed a pile grid with piles roughly every 3.5 m. Now, in the tunnel cross-section, it is sufficient to have 2 piles beneath the outer walls and 2 beneath the central tunnel duct. So the cross-section shows just 6 piles. This not only means a substantial reduction in materials, but also less work. These are important factors affecting the MKI score.”
The design took shape during the tender phase. Wyns says: “Along the 2.2 km route, the tunnel’s geotechnical profile ranges from ground level to -6 metres NAP and down to -15/-20 metres NAP, through layers of clay and peat. The composition varies along that 2.2 km. The sand layer lies about 2 to 3 metres below the concrete floor. The thickness of the soft layer varies by 4 to 5 metres. From a design perspective, the best approach was to calculate a cross-section every 25 metres, based on the established soil profile. This allowed us to determine the required reinforcement and calculate the number of piles for each section. Parametric calculations enabled us to arrive at 5 different reinforcement configurations for the floor. The advantage of parametric design is that if something changes in one location, the change can also be applied elsewhere. That saves a great many engineering hours.” Tetteroo adds: “The design really had to be ‘idiot-proof’, taking account of both the design requirements and the needs of the construction team. This involved extensive consultation between the design department and the construction team.”

Design given plenty of tolerance
“One characteristic of an underwater concrete floor is that there are wide tolerances for flatness,” Guis explains. “The wall formwork had to be adapted accordingly. The custom-made formwork has hydraulically adjustable panels, allowing the wall to connect properly to the floor. A mock-up of the tunnel’s reinforced underwater concrete floor was built so that the method could be practised in dry conditions. A great deal of time and effort went into analysing tolerances, and the design geometry was given plenty of leeway. That presents a challenge: how do you connect everything within those tolerances?”
Tetteroo adds: “BCS, the reinforcement steel supplier, was also closely involved in the design process. Working together, they drew the entire reinforcement structure in 3D. A great deal of attention was paid to the details from the outset, because we cannot afford to make mistakes when working underwater.” Wyns says: “The design underwent three reviews. The municipality, Rijkswaterstaat and SecoNed all reviewed it during the design phase.”
Underwater works at a glance
After excavation, placing the gravel and installing the relief pipes, the piles are cleaned. Guis says: “Next, horizontal driven piles are laid on the gravel. They keep the reinforcement from touching the gravel and ensure sufficient concrete cover beneath the structure. The first and second layers of reinforcement are then laid. This reinforcement is supplied prefabricated. Next, the anchor plates are installed, with nuts, to take the tensile force in the floor and transfer it to the concrete piles. Reinforcement cages are placed over the piles, designed to allow for the tolerances in pile installation. The cage can then be fitted over the pile without grinding or modifying the reinforcement. By adjusting the layers, we can install the suspension reinforcement properly. This is followed by two more layers of top reinforcement mesh, after which the concrete pour can begin.” Tetteroo adds: “Another special feature is a tool developed with HYTORC that allows us to extend the GEWI bar underwater and tighten it to the required torque.”
At the time of writing, 6 of the 34 construction pits have been poured and dewatered. Guis says: “We work in sequence, like a train. We expect to have poured another 3 pits before Christmas.”
Special expansion joint beam
Normally, an expansion joint profile would be installed between the tunnel sections in dry conditions. Tetteroo says: “During the tender, it was decided to make precast expansion joint beams beside the construction pit and position them underwater. Underwater concrete is then poured against each side, alternately in 20 cm increments, to prevent the beam from tipping over. The fabrication, transport and lifting have all been fine-tuned, and the process is truly special. An expansion joint beam weighs 76 tonnes on its own, and the beam and lifting frame together weigh 90 tonnes. Each beam is therefore lifted into place using 3 cranes. The lifting and transport frame was developed in collaboration with Sarens. They provided excellent input at the start of the process. You cannot do this kind of project without the right partners.” Wyns emphasises: “Companies such as Sarens, BCS and Dyckerhoff Basal (concrete) are important during the design phase. We get the right information from them and can use them as a sounding board.”

Cleverly accommodating concrete tolerances
Tetteroo says of the formwork: “The formwork was specifically designed for this tunnel, with extensive consultation between Kenneth’s design team, Hendriks Precon and BCS. All the reinforcement had to be possible to assemble in advance, so that as little as possible would need to be adjusted on site. The design team and BCS reviewed all the reinforcement options and drew up a shortlist. A final choice was then made. To accommodate the tolerances in the uneven top surface of the underwater concrete, we designed a system with Hendriks to quickly seal the gaps between the underside of the formwork and the top of the concrete floor. The solution is a system of 1.5-metre panels with self-adjusting hydraulics. At the touch of a button, it can accommodate a height difference of 15 cm.”
A valuable learning experience
Like the other two areas of De Groene Boog, area 2, the tunnel, has been a valuable learning experience. Wyns says: “We continue to strive for innovative designs using as little material as possible. This project has taught us a great deal. Rijkswaterstaat required that the groundwater level must not be affected, which led to the decision to use a closed construction pit with a reinforced underwater concrete floor. That presented challenges, which we have successfully overcome. This is the kind of project that sets a benchmark for sustainable designs in the future.”
Have a business enquiry for BESIX Nederland BV? Get in touch
Who worked on A16 Rotterdam
- consortiumDe Groene BoogMentioned in Project A16 Rotterdam to become the first energy-neutral motorway, including a 2.2 km-long tunnel
- supplier of reinforcing steelBCSIn this story
- construction consortium
Van OordMentioned in De Groene Boog aims for maximum reduction in CO2 emissions - construction consortiumDura VermeerMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumJohn LaingMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumDe Groene Boog construction consortiumMentioned in GPS-guided precision excavation in the wet cofferdam
- excavation workAannemingsbedrijf Verboon Maasland BVMentioned in GPS-guided precision excavation in the wet cofferdam
- foundation contractor consortium
Voorbij FunderingstechniekMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’ - foundation contractor consortiumFranki GrondtechniekenMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsM.U.C.Mentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsHektecMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- reinforcementDiepstraten WapeningstaalMentioned in Specialist reinforcement solutions for 33 structures
- ready-mixed concreteDyckerhoff BasalMentioned in Specially formulated mixes significantly reduce carbon footprint
- waterproofingBrabotechMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- construction consortiumDe Groene Boog construction consortiumMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- prefabricatedCiviele technieken deBoerMentioned in A leading name in heavy lifting and specialist transport
- Bonneveld Gewapende Grondconstructies
BonneveldMentioned in One of the largest EPS structures ever built
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA16 Rotterdam
- SubjectWater infrastructure
- CompanySarens
- CompanyBCS
- CompanyBESIX Nederland BV
- CompanyVan Oord
- CompanyMobilis




























