BouwMat

Demolition with military precision

Text Roel van Gils Images Saes International

Vlasman Sloopwerken draait al een tijdje mee op de A16 Rotterdam.
Vlasman Sloopwerken draait al een tijdje mee op de A16 Rotterdam.

On the A16 Rotterdam, structure KW58 was found to be in such poor condition that a support structure was urgently installed beneath it in 2022. The idea of replacing the entire structure was soon put forward. To make this possible, two temporary bridges were brought into position around King's Day and during the Ascension weekend. To enable the latter, Vlasman Sloopwerken had to demolish part of the existing structure with military precision, and in a very short timeframe. Vlasman's high-quality Epiroc demolition hammers, supplied by Saes International, proved invaluable.

Vlasman Sloopwerken has been working on the A16 Rotterdam for some time. When it came to light in 2022 that the structure no longer met requirements and had to be replaced, construction consortium De Groene Boog brought in Vlasman. Rijkswaterstaat and the construction consortium carried out various option studies to find the most efficient solution for replacing the structure while causing as little disruption to traffic flow as possible. At that stage, we were asked to provide our expertise in safely demolishing the structure just a stone's throw from traffic speeding past on the busiest stretch of road in the Netherlands.

Vlasman used various types of demolition hammers for the breaking work, supplied by Saes International.

Demolition

De Groene Boog ultimately opted for a solution that temporarily diverted traffic over KW58 via two temporary bridges. The temporary bridge for southbound traffic was assembled away from the traffic flows and opened over the King's Day weekend. Installing the temporary bridge for northbound traffic required first demolishing part of the existing structure. We carried out this operation with De Groene Boog during the 4-day road closure over the Ascension weekend. With so much work needing to be done at the same time, we had just 24 hours to demolish the eastern part of the structure. And we could only work from one side.

It was quite a challenge, and took some organising, to demolish so much in 24 hours.

Demolition hammers

For the ‘24-hour job’, Vlasman Sloopwerken deployed an impressive range of equipment: a 160-tonne crane, a 70-tonne crane, a 60-tonne crane, three 50-tonners, two 30-tonners, a 25-tonner, a 20-tonne mobile crane and two 8-tonners. Five dumpers were also used to remove the rubble. Various types of demolition hammers were deployed for the breaking work. Two 7-tonne Epiroc HB 7000 hammers handled the heavy work, and a third HB 7000 was hired from Saes International as a back-up. Production could not be allowed to stop under any circumstances. We also had two 4-tonne demolition hammers from the HB 4100 series and a few smaller attachments at our disposal. We purchased some of the attachments from Saes, our trusted partner for many years. The company has an extensive network and its own service and maintenance department. The latter is particularly valuable to us.

Vlasman's high-quality Epiroc demolition hammers, supplied by Saes International, are proving invaluable on the A16 Rotterdam.

Working in sequence 

Vlasman began work on the project on the night of Thursday 9 May. A few weeks before work was due to start, De Groene Boog discovered that the asphalt was up to 1 metre thick. After consultation, it was therefore decided to start a little earlier, so that we could begin demolishing the deck at 8 am as planned. We had exactly 24 hours for this, as a piling crew with two rigs was due to start installing the tubular piles for the temporary bridge immediately after us. Civiele technieken de Boer had already prefabricated the bridge in the angle of the exit slip road. The temporary bridge itself then had to be moved into position on Saturday 11 May, as planned. The entire weekend was scheduled almost down to the minute.

The concrete rubble was left on site, where it is being crushed and used as foundation material in the surrounding road network.

Chrome-6 remediation

Ahead of the Ascension weekend, Vlasman was also called in to remediate various components of KW58 containing chrome-6. We abrasive-blasted around ten bridge edges because of a chromium VI compound in the blue and grey coating. Then, immediately after the Ascension weekend, on Monday 13 May, we demolished the western deck of KW58 between the two temporary bridges. The time pressure was less intense here, so we only needed to work during the day. Even so, we still had a deadline to meet, as the following week Hoofdweg, which runs beneath the temporary bridges, had to reopen. We got that done too, of course.

Saes International has been a trusted partner of Vlasman for many years.

Intensive project

Vlasman will return to the project in December this year to demolish the remaining foundations of KW58. As the temporary bridge runs over them, we cannot access them for now. By then, we will have demolished more than 5,000 m3 of deck in total. The concrete rubble was left on site, where it is being crushed and used as foundation material in the surrounding road network. Vlasman looks back on an interesting and, above all, intensive project. It was quite a challenge, and took some organising, to demolish so much in 24 hours. Two weeks before the Ascension weekend, we also gave a presentation to all the staff involved to leave nothing to chance. And that paid off.     

Een zakelijke vraag aan Saes International BV? Get in touch

Who worked on A16 Rotterdam

  1. civil engineering componentsMobilisMentioned in A special launching method on the new A16 Rotterdam
  2. all installationsCroonwolter&drosMentioned in A special launching method on the new A16 Rotterdam
  3. clientRijkswaterstaatMentioned in An innovative launching method for the new A16 Rotterdam
  4. consortiumDe Groene BoogMentioned in Project A16 Rotterdam to become the first energy-neutral motorway, including a 2.2 km-long tunnel
  5. lifting and transport frameSarensMentioned in Reinforced underwater concrete floor for Rottemerentunnel
  6. supplier of reinforcing steelBCSMentioned in Reinforced underwater concrete floor for Rottemerentunnel
  7. diving teamsDISAMentioned in Working underwater is 100% teamwork
  8. construction consortiumBesixMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  9. construction consortiumVan OordMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  10. construction consortiumDura VermeerMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  11. construction consortiumTBIMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  12. construction consortiumRebelMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  13. construction consortiumJohn LaingMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  14. temporary bridgesRetro BridgeMentioned in ‘Safely to the other side’ on the A16 Rotterdam project
  15. reinforced earth structuresVoets Gewapende GrondconstructiesMentioned in Sure footing with geogrids
  16. geogridsHUESKER SyntheticMentioned in Sure footing with geogrids
  17. construction consortiumDe Groene Boog construction consortiumMentioned in GPS-guided precision excavation in the wet cofferdam
  18. excavation workAannemingsbedrijf Verboon Maasland BVMentioned in GPS-guided precision excavation in the wet cofferdam
  19. foundation contractor consortiumVoorbij FunderingstechniekMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  20. foundation contractor consortiumFranki GrondtechniekenMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  21. UO calculationsM.U.C.Mentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  22. UO calculationsHektecMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  23. subcontractorKandtMentioned in ‘A brilliant home fixture’
  24. subcontractorFreyssinetMentioned in Building a viaduct over a live motorway?
  25. reinforcementDiepstraten WapeningstaalMentioned in Specialist reinforcement solutions for 33 structures
  26. culvertsDISA InternationalMentioned in Structured diving operations on the A16 Rotterdam project
  27. ready-mixed concreteDyckerhoff BasalMentioned in Specially formulated mixes significantly reduce carbon footprint
  28. waterproofingBrabotechMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
  29. construction consortiumDe Groene Boog construction consortiumMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
  30. concrete pumpRvR Betonpomp VerhuurMentioned in Piles for traffic gantries drilled ‘remotely’
  31. prefabricatedCiviele technieken deBoerMentioned in A leading name in heavy lifting and specialist transport
  32. formwork specialistDokaMentioned in One-stop shop for shoring and formwork systems
  33. sheet pile profilesArcelorMittalMentioned in Circular sheet piles on the A16 Rotterdam
  34. printing pressDiesekoMentioned in Circular sheet piles on the A16 Rotterdam
  35. Bonneveld Gewapende GrondconstructiesBonneveldMentioned in One of the largest EPS structures ever built
  36. demolition hammersSaes InternationalIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectA16 Rotterdam
  • SubjectBouwMat
  • CompanySaes International BV
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.