Settlement-free foundations on pile mattresses
Text Roel van Gils Beeld Bonneveld

As part of the large-scale reconstruction of De Nieuwe Meer interchange, Bonneveld and its partner Joosten Concepts are responsible for a challenging part of the work: constructing pile mattresses and reinforced soil structures. Work is under way on both sides of the road over a length of approximately 2 kilometres, from Amstelveenseweg to beyond the interchange itself, to create a settlement-free foundation that will enable future widening.
The soil on site has a low load-bearing capacity. “There is too little space and time to use preloading, so the decision was made to relieve the underlying soil. This is done by means of a pile mattress, allowing the permanent road to be built in a single phase without any settlement,” says Peter Koelewijn, work planner at Bonneveld Gewapende Grondconstructies. The company was brought in by construction consortium TriAX during the tender stage to explore the options. “After the contract was awarded, we joined the further design of the foundations, and we have been carrying out the work on site since October 2024.”

Pile mattress
Bonneveld Gewapende Grondconstructies is carefully building the pile mattress. “We first place what are known as pile caps on the driven and raking piles installed by construction consortium TriAX,” explains Hans van Beek, site supervisor at Bonneveld Gewapende Grondconstructies. “There are around 4,000 precast concrete pile caps in total. We fill the spaces between them with sand. We then roll out geotextiles supplied by Joosten Concepts, place and compact a layer of mixed aggregate approximately 80 centimetres thick on top, and fold the geotextiles over. This creates a self-supporting structure that serves as the foundation for the new road. If the soil body beneath it were to settle, the foundation would still be strong enough to support the road above.”
Reinforced soil
In some locations, the pile mattress also forms part of the foundation for the abutments of the new bridges. “The abutments then rest partly on raking piles and partly on our pile mattress structure, as well as on the reinforced soil structure above it,” says Koelewijn. In the middle of De Nieuwe Meer interchange, Bonneveld is working on a special structure comprising 26 layers of reinforced soil, each 60 centimetres thick, and a combi-wall of 27 steel tubular piles with a diameter of 1.5 metres to prevent the reinforced soil from sliding. A combi-wall has been installed in front of this structure to prevent sliding. “Using our specially developed in-house high-pressure pump, we first emptied these tubes, pressure-washed them clean and then filled them with concrete to support the reinforced soil structure that we are currently building against them.”

Innovative working methods
Bonneveld is working at ten different locations on the project simultaneously, which Van Beek says is characterised by very limited space. “Sometimes there is only 1 metre of working space between the excavation and the adjacent buildings, which calls for adapted working methods. For example, where we would normally need 3.5 metres to brace walls, here we use special internal support structures.” Koelewijn adds: “Precast concrete walls weighing 15.5 tonnes each are delivered to site and installed by us on the concrete levelling beam, which in turn rests on the pile mattress. These are active walls that serve as formwork during construction and later as the permanent exposed wall alongside the road.”
Building the pile mattress and reinforced soil structures at De Nieuwe Meer interchange is a technical and logistical feat. Site conditions also play a part: nearby schools, cycle traffic and limited access and delivery routes require careful coordination every day. Thanks to early collaboration, smart structural solutions and tailored construction methods, a solid foundation is being laid for the future expansion of this important interchange. It is a fine example of how Bonneveld is helping to provide a solid foundation for connectivity in Amsterdam and the Randstad.
Een zakelijke vraag aan Bonneveld BV? Get in touch
Wie aan Knooppunt De Nieuwe Meer werkte
- geotextielJoosten ConceptsIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectDe Nieuwe Meer interchange
- SubjectFoundations
- CompanyJoosten Concepts
- CompanyBonneveld BV
- CompanyJoosten Groep