Ultra-slim reinforced-soil noise barrier for Park Vijfsluizen
Text Roel van GilsImage Heijmans

Heijmans is transforming Shell’s former sports ground in the municipality of Vlaardingen into a new residential area of around 400 homes: Park Vijfsluizen. To restore its green character and keep out traffic noise, an ultra-slim reinforced-soil noise barrier has been built alongside the A4 motorway. According to Gino Jongmans, business manager at Voets Gewapende Grondconstructies, the structure is so slim that it is unique by Dutch standards.
Several Heijmans specialisms are involved in the development of Park Vijfsluizen. “The Property division is developing the site, Housing is building the homes and Infrastructure is preparing the site for construction and occupation,” explains Mark van Hees, project manager in the Infrastructure division. The noise barrier was put out to European tender, with the intention of proceeding with the winning bidder as a construction team in the first phase. This construction-team phase is followed by a delivery phase. Heijmans (Infrastructure and Foundation Techniques) and Voets Gewapende Grondconstructies jointly worked through the tender in autumn 2021 to arrive at the best plan. “On 21 January 2022, we were found to be the best bidder and awarded phase 1, the construction-team phase.”

Buildability
In the first phase, the three parties worked up the design in more detail as a construction team, together with the municipality of Vlaardingen and Heijmans Vastgoed as the client. “At this stage, we brought together the client’s requirements, the landscape architect’s input, buildability and all the disciplines and stakeholders at record speed. It confirmed that the client was right to set up a construction team for the project,” says Jongmans. “Price was also a key consideration. As a construction team, we were challenged to optimise the project further from a preliminary design, in consultation with consultancy Crux, which was already working with the client.” According to Jongmans, buildability was a real issue, in this case because of the slenderness of the reinforced-soil structure. “Drawing on everyone’s expertise, we ultimately arrived at a buildable design within a budget acceptable to the client. This led to a works contract for the delivery phase (phase 2) under UAV-GC, signed on 25 July 2022. We started work soon afterwards.”

45,000 tonnes of mixed granulate
The noise barrier is 520 metres long, tapers towards the top and varies in width. At its narrowest point, the ‘screen’ is just 2.5 metres wide at the top and 4.5 metres wide at the base, with a height ranging from 12 to 14 metres. “The structure rests on a pile mattress made up of 1,432 driven piles, topped with pile caps and a layer of mixed granulate wrapped in foil (the mattress),” explains Van Hees. “The intention is for the entire barrier to be supported by those piles. The reinforced-soil structure has been built on the pile mattress. At its core, the noise barrier consists of mixed granulate, supplemented with graded sand and site-won soil in the wider sections. At the top of the barrier is a gabion made of granulate and bioblocks, finished with Corten steel. The bioblocks also help to dampen traffic noise from the A4.” Van Hees says that more than 45,000 tonnes of mixed granulate were used in the noise barrier. “In the interests of sustainability, most of the granulate came from the demolition of the old lock in Terneuzen. All in all, managing the transport was also a considerable logistical challenge, given that the residential area was being built at the same time.”

The noise barrier is currently still predominantly black, a characteristic of reinforced-soil structures. Van Hees explains: “Climbing plants will be planted in the autumn, eventually turning it into a green oasis. To encourage their growth, the soil has been improved and the wall fitted with steel wires and climbing mesh. In front of the barrier, a maintenance path with tree-pit aggregate has been laid, along with a swale to ensure drainage from the A4.” The noise barrier was formally handed over to the client on 14 June 2023. “It was a very special project for us, and far from routine,” says Jongmans, reflecting on the work. He concludes: “Above all because we were involved from day one, which gave us the opportunity to ensure the design was buildable from the outset.”
Een zakelijke vraag aan Voets Gewapende Grondconstructies B.V.? Get in touch
Who worked on it
Park Vijfsluizen in Vlaardingen, transformation
- Reinforced earth structure
Voets Gewapende Grondconstructies - clientHeijmans Vastgoed
- construction teamHeijmans (Infra en Funderingstechnieken)
- consultancyCrux
Keep following this
Get an email when a new story is published. No account needed.
- ProjectPark Vijfsluizen
- SubjectRoad construction
- CompanyVoets Gewapende Grondconstructies B.V.
- CompanyHeijmans Vastgoed
- CompanyHeijmans (Infra en Funderingstechnieken)
- CompanyCrux