Connecting ramp and viaduct link the A13 and A16

The new A16 Rotterdam will be an 11-kilometre national road between the A16/A20 at Terbregseplein and the A13 near Rotterdam The Hague Airport. The project is being delivered on behalf of Rijkswaterstaat by the De Groene Boog consortium, comprising BESIX, Dura Vermeer, Van Oord, TBI (Mobilis, Croonwolter&dros), Rebel and John Laing. The project includes the connection between the A13 and A16 via a ‘connecting ramp’: a strikingly designed route featuring a viaduct over the A13. GWW Magazine visited the site office to talk to De Groene Boog project manager Martijn Schrover and integrated design manager Willem Peter Huijssoon.
Structure 10 is a remarkable feat
“Structure 10, the viaduct over the A13, forms part of the connecting ramp linking the A16 to the A13. It consists of two separate decks side by side,” Schrover begins. “The viaduct is unique for several reasons. First, because of the angle at which it crosses the road.” Huijssoon adds: “Because it curves, it is wider. The curve has been designed to give drivers enough forward visibility to see what is happening ahead. The concrete deck is also twisted, meaning that as well as following a curve, it is slightly inclined. This is necessary to rise and fall. That presents a major civil engineering challenge, and the 103-metre span also meant that the deck had to be cast in situ.”
Casting it in situ was a remarkable feat. Schrover explains: “Several factors need to be monitored when casting the deck. First, the concrete must have exactly the right viscosity and setting time, so that it does not ‘wander’ towards the lowest point. The rate of pouring and the volume poured in each phase are also crucial.” Huijssoon adds: “We followed a specific casting sequence and allowed the concrete to stiffen sufficiently before moving on safely to the next phase. It is a thick deck, around one and a half metres. It was a massive pour, taking 24 hours for each direction of travel. It could not have been built using precast elements either.”

‘Building on thick pudding’
The soft ground on which the structure is being built has been a major challenge. “It really is like building on thick pudding,” says Huijssoon. “The whole design presents not only a structural challenge, but a geotechnical one too. This includes raising sand and soil embankments 10 to 12 metres high, installing vertical drainage and creating wide ‘footprints’ during construction to keep the slopes stable. Settlement of 2 to 3 metres occurred on both sides. On top of that, we had to keep the waterways navigable. This part of the Netherlands where we are building is unique.” To illustrate the scale of the geotechnical challenge, Huijssoon shares an anecdote: “When a local farmer saw what we were doing, he took off his cap and scratched his head. Then he uttered these memorable words: ‘I don’t know what you’re doing, but I’ve been trying to build a little dam here for 50 years, without success…’ That gives you an idea of how complex the situation is.”
Pile-supported embankments for added safety
Pile-supported embankments were chosen on both sides of the viaduct because there was not enough time for consolidation. In total, 2,600 piles are being installed on either side of Structure 10. Schrover explains why: “The structure itself rests on piles. If we did not install the pile-supported embankments on either side, even minor settlement could affect the transition from the soft ground to the hard structure. In other words, settlement could make the ride onto and off the viaduct less smooth. For this reason, we designed the pile layout perpendicular to the direction of travel, in line with the geometry of the A16 Rotterdam. This provides a safe, robust road surface on the connecting ramp.”
Rebuilding while keeping the road open
“We are rebuilding while keeping the road open, which is a challenge in itself. Traffic continues to race along the A13. It is still in its original position, but there will be a phase when the A13’s left-hand carriageway runs beneath our structure, giving us room for the next construction phase,” says Huijssoon. Schrover adds: “Structure 10 is a key part of the project, enabling us to switch traffic over.” To connect the A16 in the middle of the A13, the A13 is being shifted outwards. “Making that connection also brought a number of geotechnical challenges,” Huijssoon notes. “We have to raise the road quite quickly to connect it to the viaduct. We are also using EPS as lightweight fill beneath the road surface where the A13 connects. It is all about road safety and driving comfort!”
Consideration is also being given to meadow birds
The phasing of the project takes account of the breeding season of the meadow birds that inhabit the area. “It’s good that this is being taken into account,” says Schrover. “For us, it simply means careful planning and phasing. Pile foundation works and demolition in particular have a significant impact on wildlife, so we can only carry out that work during a limited period. And speaking of birds… one memorable sight was a female avocet nesting in the pools that formed when the ground was preloaded.”
Finally, we ask what the A16 Rotterdam means to each of them personally. Huijssoon says: “I’m immensely proud to be working on such a major infrastructure project here in Rotterdam. It’s rewarding to be part of a project that contributes to mobility in the Netherlands.” Schrover concludes: “I love projects like this, with all their complexity, and want to build something I can look back on with my children. And if people enjoy experiencing this project as much as I do, that makes me very happy.”
Have a business enquiry for BESIX Nederland BV? Get in touch
Who worked on A16 Rotterdam
- consortiumDe Groene BoogMentioned in Project A16 Rotterdam to become the first energy-neutral motorway, including a 2.2 km-long tunnel
- lifting and transport frame
SarensMentioned in Reinforced underwater concrete floor for Rottemerentunnel - supplier of reinforcing steelBCSMentioned in Reinforced underwater concrete floor for Rottemerentunnel
- construction consortium
Van OordMentioned in De Groene Boog aims for maximum reduction in CO2 emissions - construction consortiumDura VermeerMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumJohn LaingMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumDe Groene Boog construction consortiumMentioned in GPS-guided precision excavation in the wet cofferdam
- excavation workAannemingsbedrijf Verboon Maasland BVMentioned in GPS-guided precision excavation in the wet cofferdam
- foundation contractor consortium
Voorbij FunderingstechniekMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’ - foundation contractor consortiumFranki GrondtechniekenMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsM.U.C.Mentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsHektecMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- reinforcementDiepstraten WapeningstaalMentioned in Specialist reinforcement solutions for 33 structures
- ready-mixed concreteDyckerhoff BasalMentioned in Specially formulated mixes significantly reduce carbon footprint
- waterproofingBrabotechMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- construction consortiumDe Groene Boog construction consortiumMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- prefabricatedCiviele technieken deBoerMentioned in A leading name in heavy lifting and specialist transport
- Bonneveld Gewapende Grondconstructies
BonneveldMentioned in One of the largest EPS structures ever built
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA16 Rotterdam
- ThemeExtending the life of roads and civil engineering structures
- SubjectRoad construction
- CompanyBESIX Nederland BV
- CompanyVan Oord
- CompanyMobilis
- CompanyCroonwolter&dros



























