Road construction

From milestone to milestone, with the local community in mind

Text Roel van Gils Beeld Sjaak Boot Photograpy, TopView Luchtfotografie

Construction of the new A16 Rotterdam has entered its final phase. (Image: TopView Luchtfotografie)
Construction of the new A16 Rotterdam has entered its final phase. (Image: TopView Luchtfotografie)

Construction of the new A16 Rotterdam has entered its final phase. The De Groene Boog construction consortium is ticking off milestone after milestone. One milestone has barely been reached before the next comes into view. The importance of stakeholder management on a major project such as the A16 Rotterdam is beyond question. And De Groene Boog has it down to a fine art. Zero complaints from the local community after the ‘open-heart surgery’ over the extended Ascension weekend is quite an achievement. 

Commissioned by Rijkswaterstaat, Dura Vermeer, Mobilis, Croonwolter&dros, BESIX NL, Van Oord, Rebel and John Laing are jointly responsible for the design, construction, financing and 20-year maintenance of the A16 Rotterdam. “The work carried out over the past Ascension weekend was initially on a much smaller scale,” says Jeroen Toet, project manager for Mobilis at De Groene Boog. “We were ‘only’ going to move the new structure into place on the new slip road leading to the A16 (KW52B). In the end, the viaduct over the Hoofdweg was added to the programme (KW58). An inspection had established that the structure was at the end of its service life and that it would be irresponsible to keep using it. It therefore had to be replaced, which meant a considerable increase in scope at that point. As it is located in the middle of the A16, it is essential to replace the structure with as little disruption as possible. The first steps towards this were taken over the King’s Day weekend and later over the Ascension weekend.”

The number of activities taking place over the Ascension weekend was enormous. (Image: Sjaak Boot Photography)

A mammoth task 

KW58 is located at one of the most important and busiest junctions on the national road network. “It is impossible to close the A16 for an extended period. So, together with Rijkswaterstaat, we devised a plan to divert traffic over temporary bridges, allowing us to build the new viaduct in between them. The temporary bridge for southbound traffic was built away from the traffic flows and opened over the King’s Day weekend. The bridge on the eastern side was moved into place over the Ascension weekend, when part of the existing viaduct was also demolished. It was a mammoth task with a major impact on the local community and through traffic, as the A16 northbound was closed for 4 days.”

The De Groene Boog construction consortium is ticking off milestone after milestone. (Image: Sjaak Boot Photography)

Construction disruption

Work continued 24 hours a day for four days over the Ascension weekend. “That meant demolishing in the middle of the night with seven machines, vibrating sheet piles into the ground, installing piles, and so on,” explains Paul Eijking, stakeholder manager for Mobilis at De Groene Boog. “Given the nature of the work, we made thorough preparations with the immediate neighbourhood for the construction disruption that might arise. We also offered around 50 households the option of staying in a hotel for several nights, based on the noise levels. In the end, seven households took us up on the offer.” 

The work over the Ascension weekend had been prepared almost like a military operation. (Image: Sjaak Boot Photography)

Slip road closed for 18 months

The opening of the temporary bridges also means that an important slip road onto the A16 will be closed for 18 months. “We have been working since March 2023 with Rijkswaterstaat, the municipality of Rotterdam and Zuid-Holland Bereikbaar to alert local people and regular visitors to nearby businesses,” says Paul. “And that has definitely paid off.” There was also extensive communication about the 4-day closure over the Ascension weekend. “It even made the national media,” says Jeroen. “The impact of this kind of intervention is enormous. The signage plan for the temporary diversion routes over that weekend alone showed as much, extending almost as far as Amsterdam. And when there are no complaints from the local community during an operation like this, it means we have all done a good job.”

Military operation 

The work over the Ascension weekend had therefore been prepared almost like a military operation, says Jeroen. “The number of activities taking place that weekend was enormous: it was like an anthill. An organised anthill, that is. You can only pull that off if the collaboration within the construction consortium and with all the subcontractors is first-rate. That also enables you to deal with any setbacks together. And when the road then opens half an hour ahead of schedule, all we can say is that it went well.”

The next milestone is already in sight. “The first newly built section of KW58 will open at the end of this year, after which we will build the eastern section at speed, with completion due in September 2025. So we are moving at a rapid pace from one milestone to the next, gradually bringing the project closer to the condition in which it will be handed over. And all the while, we will keep the local community informed.” Paul concludes: “People in the area know what is going to happen, who they can contact and what impact the work will have during each phase. We will keep doing that right through to the finish.”     

Have a business enquiry for Mobilis? Get in touch

Who worked on A16 Rotterdam

  1. civil engineering componentsMobilisMentioned in A special launching method on the new A16 Rotterdam
  2. all installationsCroonwolter&drosMentioned in A special launching method on the new A16 Rotterdam
  3. clientRijkswaterstaatMentioned in An innovative launching method for the new A16 Rotterdam
  4. consortiumDe Groene BoogMentioned in Project A16 Rotterdam to become the first energy-neutral motorway, including a 2.2 km-long tunnel
  5. lifting and transport frameSarensMentioned in Reinforced underwater concrete floor for Rottemerentunnel
  6. supplier of reinforcing steelBCSMentioned in Reinforced underwater concrete floor for Rottemerentunnel
  7. diving teamsDISAMentioned in Working underwater is 100% teamwork
  8. construction consortiumBesixMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  9. construction consortiumVan OordMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  10. construction consortiumDura VermeerMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  11. construction consortiumTBIMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  12. construction consortiumRebelMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  13. construction consortiumJohn LaingMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  14. temporary bridgesRetro BridgeMentioned in ‘Safely to the other side’ on the A16 Rotterdam project
  15. reinforced earth structuresVoets Gewapende GrondconstructiesMentioned in Sure footing with geogrids
  16. geogridsHUESKER SyntheticMentioned in Sure footing with geogrids
  17. construction consortiumDe Groene Boog construction consortiumMentioned in GPS-guided precision excavation in the wet cofferdam
  18. excavation workAannemingsbedrijf Verboon Maasland BVMentioned in GPS-guided precision excavation in the wet cofferdam
  19. foundation contractor consortiumVoorbij FunderingstechniekMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  20. foundation contractor consortiumFranki GrondtechniekenMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  21. UO calculationsM.U.C.Mentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  22. UO calculationsHektecMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  23. subcontractorKandtMentioned in ‘A brilliant home fixture’
  24. subcontractorFreyssinetMentioned in Building a viaduct over a live motorway?
  25. reinforcementDiepstraten WapeningstaalMentioned in Specialist reinforcement solutions for 33 structures
  26. culvertsDISA InternationalMentioned in Structured diving operations on the A16 Rotterdam project
  27. ready-mixed concreteDyckerhoff BasalMentioned in Specially formulated mixes significantly reduce carbon footprint
  28. waterproofingBrabotechMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
  29. construction consortiumDe Groene Boog construction consortiumMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
  30. concrete pumpRvR Betonpomp VerhuurMentioned in Piles for traffic gantries drilled ‘remotely’
  31. prefabricatedCiviele technieken deBoerMentioned in A leading name in heavy lifting and specialist transport
  32. formwork specialistDokaMentioned in One-stop shop for shoring and formwork systems
  33. sheet pile profilesArcelorMittalMentioned in Circular sheet piles on the A16 Rotterdam
  34. printing pressDiesekoMentioned in Circular sheet piles on the A16 Rotterdam
  35. Bonneveld Gewapende GrondconstructiesBonneveldMentioned in One of the largest EPS structures ever built
  36. demolition hammersSaes InternationalMentioned in Demolition with military precision

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectA16 Rotterdam
  • SubjectRoad construction
  • CompanyMobilis
  • CompanyCroonwolter&dros
  • CompanyBESIX Nederland BV
  • CompanyVan Oord
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.