From milestone to milestone, with the local community in mind
Text Roel van Gils Beeld Sjaak Boot Photograpy, TopView Luchtfotografie

Construction of the new A16 Rotterdam has entered its final phase. The De Groene Boog construction consortium is ticking off milestone after milestone. One milestone has barely been reached before the next comes into view. The importance of stakeholder management on a major project such as the A16 Rotterdam is beyond question. And De Groene Boog has it down to a fine art. Zero complaints from the local community after the ‘open-heart surgery’ over the extended Ascension weekend is quite an achievement.
Commissioned by Rijkswaterstaat, Dura Vermeer, Mobilis, Croonwolter&dros, BESIX NL, Van Oord, Rebel and John Laing are jointly responsible for the design, construction, financing and 20-year maintenance of the A16 Rotterdam. “The work carried out over the past Ascension weekend was initially on a much smaller scale,” says Jeroen Toet, project manager for Mobilis at De Groene Boog. “We were ‘only’ going to move the new structure into place on the new slip road leading to the A16 (KW52B). In the end, the viaduct over the Hoofdweg was added to the programme (KW58). An inspection had established that the structure was at the end of its service life and that it would be irresponsible to keep using it. It therefore had to be replaced, which meant a considerable increase in scope at that point. As it is located in the middle of the A16, it is essential to replace the structure with as little disruption as possible. The first steps towards this were taken over the King’s Day weekend and later over the Ascension weekend.”

A mammoth task
KW58 is located at one of the most important and busiest junctions on the national road network. “It is impossible to close the A16 for an extended period. So, together with Rijkswaterstaat, we devised a plan to divert traffic over temporary bridges, allowing us to build the new viaduct in between them. The temporary bridge for southbound traffic was built away from the traffic flows and opened over the King’s Day weekend. The bridge on the eastern side was moved into place over the Ascension weekend, when part of the existing viaduct was also demolished. It was a mammoth task with a major impact on the local community and through traffic, as the A16 northbound was closed for 4 days.”

Construction disruption
Work continued 24 hours a day for four days over the Ascension weekend. “That meant demolishing in the middle of the night with seven machines, vibrating sheet piles into the ground, installing piles, and so on,” explains Paul Eijking, stakeholder manager for Mobilis at De Groene Boog. “Given the nature of the work, we made thorough preparations with the immediate neighbourhood for the construction disruption that might arise. We also offered around 50 households the option of staying in a hotel for several nights, based on the noise levels. In the end, seven households took us up on the offer.”

Slip road closed for 18 months
The opening of the temporary bridges also means that an important slip road onto the A16 will be closed for 18 months. “We have been working since March 2023 with Rijkswaterstaat, the municipality of Rotterdam and Zuid-Holland Bereikbaar to alert local people and regular visitors to nearby businesses,” says Paul. “And that has definitely paid off.” There was also extensive communication about the 4-day closure over the Ascension weekend. “It even made the national media,” says Jeroen. “The impact of this kind of intervention is enormous. The signage plan for the temporary diversion routes over that weekend alone showed as much, extending almost as far as Amsterdam. And when there are no complaints from the local community during an operation like this, it means we have all done a good job.”
Military operation
The work over the Ascension weekend had therefore been prepared almost like a military operation, says Jeroen. “The number of activities taking place that weekend was enormous: it was like an anthill. An organised anthill, that is. You can only pull that off if the collaboration within the construction consortium and with all the subcontractors is first-rate. That also enables you to deal with any setbacks together. And when the road then opens half an hour ahead of schedule, all we can say is that it went well.”
The next milestone is already in sight. “The first newly built section of KW58 will open at the end of this year, after which we will build the eastern section at speed, with completion due in September 2025. So we are moving at a rapid pace from one milestone to the next, gradually bringing the project closer to the condition in which it will be handed over. And all the while, we will keep the local community informed.” Paul concludes: “People in the area know what is going to happen, who they can contact and what impact the work will have during each phase. We will keep doing that right through to the finish.”
Have a business enquiry for Mobilis? Get in touch
Who worked on A16 Rotterdam
- consortiumDe Groene BoogMentioned in Project A16 Rotterdam to become the first energy-neutral motorway, including a 2.2 km-long tunnel
- lifting and transport frame
SarensMentioned in Reinforced underwater concrete floor for Rottemerentunnel - supplier of reinforcing steelBCSMentioned in Reinforced underwater concrete floor for Rottemerentunnel
- construction consortium
Van OordMentioned in De Groene Boog aims for maximum reduction in CO2 emissions - construction consortiumDura VermeerMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumJohn LaingMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumDe Groene Boog construction consortiumMentioned in GPS-guided precision excavation in the wet cofferdam
- excavation workAannemingsbedrijf Verboon Maasland BVMentioned in GPS-guided precision excavation in the wet cofferdam
- foundation contractor consortium
Voorbij FunderingstechniekMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’ - foundation contractor consortiumFranki GrondtechniekenMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsM.U.C.Mentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsHektecMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- reinforcementDiepstraten WapeningstaalMentioned in Specialist reinforcement solutions for 33 structures
- ready-mixed concreteDyckerhoff BasalMentioned in Specially formulated mixes significantly reduce carbon footprint
- waterproofingBrabotechMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- construction consortiumDe Groene Boog construction consortiumMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- prefabricatedCiviele technieken deBoerMentioned in A leading name in heavy lifting and specialist transport
- Bonneveld Gewapende Grondconstructies
BonneveldMentioned in One of the largest EPS structures ever built
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA16 Rotterdam
- SubjectRoad construction
- CompanyMobilis
- CompanyCroonwolter&dros
- CompanyBESIX Nederland BV
- CompanyVan Oord