35 metres beneath Vienna: Doka supplies bespoke tunnel formwork for metro network expansion

Vienna is expanding its public transport network with a major underground project designed to increase capacity and support more sustainable urban mobility. Doka is contributing to several construction phases with bespoke tunnel formwork solutions for complex geometries, demanding construction sequences and challenging logistics.
Deep beneath Vienna’s city centre, the U2xU5 project is creating new tunnel and station structures in a densely built-up urban environment. The project involves extending metro line U2 and building U5, Vienna’s first fully automated metro line. Where tunnel tubes, shafts, cross-passages and escalator tunnels meet at different angles, systems must be precisely tailored to the geometry, construction sequence and logistics. Doka is contributing its engineering and construction expertise, from 3D planning and pre-assembled formwork elements to on-site assembly.

Multiple stations, one underground challenge
Doka is involved in several construction phases of the U2xU5 project in Vienna. Since 2021, it has supported the ARGE U2 17-21 consortium, led by STRABAG and PORR, first at Matzleinsdorfer Platz station and now also at Reinprechtsdorfer Straße, Pilgramgasse and Neubaugasse. The challenge lies not in a single site, but in multiple underground stations and tunnel sections in a densely built-up urban environment, each with its own geometry, logistics and construction sequence.
“The complex structures along the U2 extension call for bespoke solutions and close collaboration between all project partners. Doka provides the technical expertise and tailored formwork solutions needed to meet these challenges. Our long-standing partnership plays a key role in the successful delivery of this major infrastructure project,” says Markus Kravutske, site manager at ARGE U2 17-21.
The project will also improve everyday mobility in Vienna: around 50,000 people are expected to benefit from the new connection to the urban railway at Matzleinsdorfer Platz. To make this link possible, a technically demanding underground tunnel and station structure is taking shape below ground. This highlights what is essential when building a metro in a city centre: precise planning, tightly coordinated logistics and a construction sequence in which preparation and execution must dovetail seamlessly. Doka supplied formwork travellers and bespoke solutions for the tunnel structures in the station areas.
Bespoke solutions using sliding formwork will also be used for the junction structure at Matzleinsdorfer Platz, including in the widening sections where the two tunnel tubes merge into a single structure.
Precision in confined spaces
The project’s complexity is particularly evident at Neubaugasse station. While everyday city life continues above ground, a major interchange with the existing U3 line is being built 35 metres below street level. Station tubes, cross-passages, escalator and ventilation tunnels, and intersecting structures converge at different angles in an extremely confined space. To manage these transitions, Doka developed 3D-planned formwork solutions precisely tailored to each geometry. The systems used include the heavy-duty SL-1 support system and the proven Top 50 large-area formwork system.


Tunnel expertise in practice
Doka is bringing decades of tunnel construction expertise to Vienna’s public transport expansion, drawing on international major infrastructure projects such as the Sydney Metro in Australia, the Stockholm metro extension and metro projects in Madrid. Early involvement in planning and construction preparation is a key success factor. This allows the systems to be tailored to project requirements from the outset.
“Every detail matters in tunnel construction. Movable modules are pre-assembled at our Doka factory near our headquarters, then precisely assembled on site. This significantly reduces assembly work on site and saves valuable construction time,” says Harald Zulehner, Managing Director of Doka Austria. Doka also uses modular systems, enabling many components to be reused across different construction phases. This helps keep progress deep underground reliably predictable.
Contributing to the mobility of tomorrow
The expansion of Vienna’s U2 and U5 is much more than a tunnel construction project. According to the client, Wiener Linien, the new cross-city connection will create capacity for an additional 300 million passengers a year and save around 550 million car kilometres annually. The project is therefore a powerful example of future urban mobility. With bespoke solutions for complex tunnel and station sections, Doka is making a tangible contribution to its delivery.
At a glance:
• Project: Vienna metro expansion U2xU5
• Location: Vienna
• Structure type: Metro station and tunnel construction
• Client: Wiener Linien
• Main contractor: Joint Venture STRABAG-PORR (“ARGE U2 17-21”)
• Completion: first phase scheduled for 2030
• Systems used: heavy-duty SL-1 support system, Top 50 large-area formwork, Staxo 100 supporting tower, etc.
• Key services: 3D planning, pre-assembly service, on-site assembly serviceImages
Have a business enquiry for Doka Nederland B.V.? Get in touch
Who worked on it
U2xU5-project in Wenen
- tunnelbekisting
Doka - clientWiener Linien
- main contractorSTRABAG
- main contractorPORR
Keep following this
Get an email when a new story is published. No account needed.
- ProjectU2xU5-project
- ThemeUnderground construction
- SubjectTunnel construction
- CompanyDoka Nederland B.V.
- CompanyWiener Linien
- CompanySTRABAG
- CompanyPORR