GPS-guided precision excavation in the wet cofferdam

As part of the A16 Rotterdam project, construction consortium De Groene Boog is building the Rottemerentunnel ‘in the wet’. The excavation work was therefore highly specialised, making it a job ideally suited to Aannemingsbedrijf Verboon Maasland BV. Ruud van Wijk, managing director of the Verboon Maasland Groep, outlines the situation.
Large cranes in wet cofferdams
“It’s an impressive sight, seeing our large cranes at work in the wet cofferdams,” he begins. “We have to excavate between the piles fitted with GEWI anchors by the foundation crews. Excavation is carried out in two passes. The first pass was completed to a level well above the anchors; the second is being carried out between the anchors, down to the excavation level. This is precision work, carried out by our skilled operators using GPS-guided cranes. The silt is then removed using a ‘deep underwater pump’, or DOP for short. The bottom needs to be as free of silt as possible. Since it is technically impossible to make it 100% silt-free, a layer of gravel is placed over the remaining silt, and the underwater concrete is poured on top.”

Wire-rope cranes with grabs
Excavating down to the required level is particularly specialist work. “This work is done using wire-rope cranes with grabs and DOP pumps. Much of the first pass was carried out with hydraulic excavators, in collaboration with Van Oord, which is part of construction consortium De Groene Boog. The sheet-pile recesses are also cleaned out and the gravel placed using hydraulic and wire-rope cranes,” explains Van Wijk. Verboon Maasland began preparations for the project a year and a half ago. “In recent years, we’ve already completed several similar projects, including the Rijnlandroute, the Blankenburgverbinding and the car park on Lammermarkt in Leiden. So we have plenty of relevant experience to draw on.”
At the time of writing, De Groene Boog’s excavation work has reached the crossing with the Rotte. “The tunnel crosses the Rotte here. This section of the excavation is being carried out in two phases so as not to disrupt boat traffic,” Van Wijk concludes. “We’d be happy to report back on it next year.”
Have a business enquiry for Van Oord? Get in touch
Who worked on A16 Rotterdam
- consortiumDe Groene BoogMentioned in Project A16 Rotterdam to become the first energy-neutral motorway, including a 2.2 km-long tunnel
- lifting and transport frame
SarensMentioned in Reinforced underwater concrete floor for Rottemerentunnel - supplier of reinforcing steelBCSMentioned in Reinforced underwater concrete floor for Rottemerentunnel
- construction consortium
Van OordMentioned in De Groene Boog aims for maximum reduction in CO2 emissions - construction consortiumDura VermeerMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumJohn LaingMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumDe Groene Boog construction consortiumIn this story
- excavation workAannemingsbedrijf Verboon Maasland BVIn this story
- foundation contractor consortium
Voorbij FunderingstechniekMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’ - foundation contractor consortiumFranki GrondtechniekenMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsM.U.C.Mentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsHektecMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- reinforcementDiepstraten WapeningstaalMentioned in Specialist reinforcement solutions for 33 structures
- ready-mixed concreteDyckerhoff BasalMentioned in Specially formulated mixes significantly reduce carbon footprint
- waterproofingBrabotechMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- construction consortiumDe Groene Boog construction consortiumMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- prefabricatedCiviele technieken deBoerMentioned in A leading name in heavy lifting and specialist transport
- Bonneveld Gewapende Grondconstructies
BonneveldMentioned in One of the largest EPS structures ever built
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA16 Rotterdam
- ThemeUnderground construction
- SubjectWater infrastructure
- CompanyDe Groene Boog construction consortium
- CompanyAannemingsbedrijf Verboon Maasland BV
- CompanyVan Oord