Modular TK58 temporary bridge is a spectacular project
Text Roel van Gils Image Retro Bridge

Around twelve modular bridges supplied by Retro Bridge have proved their worth over the past few years on and around the A16 Rotterdam. Most were dismantled between the middle of last year and the start of this year. However, some of the elements have recently been reused to enable the final stage of the operation, replacing the viaduct carrying the A16 over Hoofdweg (KW58). For Retro Bridge, this is a spectacular project: the temporary bridge (TK58) is exceptionally large in area and must keep traffic flowing at one of the busiest interchanges in the Netherlands.
Under an earlier agreement with the De Groene Boog construction consortium, Retro Bridge supplied the temporary bridges needed to build the Rottemerentunnel and the adjoining road section, among other works. “We supplied a wide variety of temporary bridges for a range of purposes. Some were used only by (heavy) construction traffic, while others carried through motor traffic or served as cycle and pedestrian bridges,” says Han Kastermans of Retro Bridge. “All those temporary bridges, apart from one pedestrian bridge, were dismantled between the 2023 summer holiday and January 2024. Separately from that contract, De Groene Boog approached us a year ago to provide the temporary bridge structure TK58 for the replacement of KW58. They asked us to build it using the recovered Retro Heavy Bridge elements already on site.”

102 by 25 metres
A few years ago, structure KW58 was identified as a high-risk viaduct. As a precaution, it was fitted with a support structure so that it could continue to serve its purpose safely. The extensive replacement operation is now under way. To make this possible, traffic in both directions is being diverted over a temporary bridge structure. Since 29 April, northbound-to-southbound traffic has been diverted over Retro Bridge’s TK58. “Our temporary bridge is on the A16 near the Prins Alexander exit,” Han explains. “The deck is 102 metres long and 25 metres wide, exceptionally large by Dutch standards. That is because the four lanes are laid out in a curve across the deck.”

1,500 tonnes
Retro Bridge’s TK58 is made up of 120 elements and weighs 1,500 tonnes in total. “The bridge consists of three spans, two of 40.5 metres and one of 21 metres, all from our Retro Heavy Bridge range,” Han explains. “We carried out detailed calculations and carefully selected the elements. The most recent elements are in the traffic lanes, while the somewhat ‘older’ sections are in the runs supporting the crash barrier and barriers. Logistically, it was quite a puzzle to select the right elements from all those recovered from the project. In the end, the elements were taken to the assembly site in mid-January, on the other side of the motorway, where we assembled the three sections.”

Tight deadline
TK58 rests on demountable supports installed by De Groene Boog. “At the beginning of March, we installed the first 40.5-by-25-metre span. We moved the deck into position using launching beams, then lowered it onto the supports with large cranes,” Han says, describing the installation. “A few weeks later, we installed the other two sections in the same way, enabling De Groene Boog to open the temporary structure (TK58) to traffic on schedule, on 29 April,” Han says. Retro Bridge’s TK58 is scheduled to remain in use for 76 weeks. “By then, the new viaduct will be ready. We’ll dismantle our bridge and will no doubt be able to put the elements to use somewhere else.”
Een zakelijke vraag aan Retro Bridge Nederland? Get in touch
Who worked on A16 Rotterdam
- consortiumDe Groene BoogMentioned in Project A16 Rotterdam to become the first energy-neutral motorway, including a 2.2 km-long tunnel
- lifting and transport frame
SarensMentioned in Reinforced underwater concrete floor for Rottemerentunnel - supplier of reinforcing steelBCSMentioned in Reinforced underwater concrete floor for Rottemerentunnel
- construction consortium
Van OordMentioned in De Groene Boog aims for maximum reduction in CO2 emissions - construction consortiumDura VermeerMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumJohn LaingMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumDe Groene Boog construction consortiumMentioned in GPS-guided precision excavation in the wet cofferdam
- excavation workAannemingsbedrijf Verboon Maasland BVMentioned in GPS-guided precision excavation in the wet cofferdam
- foundation contractor consortium
Voorbij FunderingstechniekMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’ - foundation contractor consortiumFranki GrondtechniekenMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsM.U.C.Mentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsHektecMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- reinforcementDiepstraten WapeningstaalMentioned in Specialist reinforcement solutions for 33 structures
- ready-mixed concreteDyckerhoff BasalMentioned in Specially formulated mixes significantly reduce carbon footprint
- waterproofingBrabotechMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- construction consortiumDe Groene Boog construction consortiumMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- prefabricatedCiviele technieken deBoerMentioned in A leading name in heavy lifting and specialist transport
- Bonneveld Gewapende Grondconstructies
BonneveldMentioned in One of the largest EPS structures ever built
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA16 Rotterdam
- ThemeExtending the life of roads and civil engineering structures
- SubjectRoad construction
- CompanyRetro Bridge Nederland



























