One-stop shop for shoring and formwork systems
Text Roel van Gils Image Doka

Countless construction and infrastructure projects around the world have been built using Doka solutions. The De Groene Boog consortium also called on the formwork specialist’s expertise for the A16 Rotterdam, supplying the systems required for almost every structure. The highlight was the formwork for the innovative Incremental Launching Method, used for the viaduct over Terbregseplein, but the curved concrete trough girder for the structure installed over the long Ascension Day weekend (KW52B) was also built using Doka systems.
Doka systems are ideally suited to infrastructure projects. The Dutch division of the global company has amply demonstrated this on the A16 Rotterdam. At an earlier stage, Doka supplied the formwork and slab support for the construction of the viaduct sections at Terbregseplein. To keep traffic moving during construction, a technique unique by Dutch standards was used: the Incremental Launching Method (ILM), in which the sections were pushed out over the A20 from one side.

Top 50 girder formwork
Doka supplied Top 50 girder formwork for the ILM at the assembly area. “The viaduct was built in sections from one side and launched over the piers. Each section was cast in our formwork,” says Harry van Rijswijk of Doka Nederland. “The formwork system was designed to lower hydraulically, allowing the section to be moved forward, after which the formwork was raised again to produce the next section. This cycle was repeated seventeen times until the viaduct reached the other side. The process was then repeated for a second deck comprising seventeen sections. The great advantage of our Top 50 girder formwork is that the shape, size, tie pattern and form face of the panels can all be adapted to suit any requirement. Depending on the anticipated load, the spacing of the Doka H20 beams and walings is configured, allowing the position of the form face to be chosen freely.”

From tunnel to viaduct
Doka Nederland is the only company in the Netherlands with the expertise to use the innovative ILM technique, a proven method for constructing structures in mountainous terrain. “This quickly puts you in the running to supply shoring and formwork systems for other parts of the project too,” says Denick van Gemert of Doka Nederland. “We also supplied wall and shoring systems for the construction of the Rottemerentunnel and various other structures, including the curved trough girder for KW52B. Our Top 50 girder formwork was used for this as well. The system made it relatively straightforward to form around the tie connections and, just as importantly, to create the curved shape. We prepared complete formwork panels in our workshop in Oss, so that on site they simply had to be clipped together. We also carried out a final check of the system on site to make sure it had been assembled as shown in the drawings.”
And so Doka has contributed to almost every structure on the A16 Rotterdam. “Our solutions are known in the market as quality products. We also understand the challenges our customers face and know what it takes to make a project succeed. The best performance on site starts with the right quantity of formwork and scaffolding, in the right place and at the right time.”
Have a business enquiry for Doka Nederland B.V.? Get in touch
Who worked on A16 Rotterdam
- consortiumDe Groene BoogMentioned in Project A16 Rotterdam to become the first energy-neutral motorway, including a 2.2 km-long tunnel
- lifting and transport frame
SarensMentioned in Reinforced underwater concrete floor for Rottemerentunnel - supplier of reinforcing steelBCSMentioned in Reinforced underwater concrete floor for Rottemerentunnel
- construction consortium
Van OordMentioned in De Groene Boog aims for maximum reduction in CO2 emissions - construction consortiumDura VermeerMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumJohn LaingMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumDe Groene Boog construction consortiumMentioned in GPS-guided precision excavation in the wet cofferdam
- excavation workAannemingsbedrijf Verboon Maasland BVMentioned in GPS-guided precision excavation in the wet cofferdam
- foundation contractor consortium
Voorbij FunderingstechniekMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’ - foundation contractor consortiumFranki GrondtechniekenMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsM.U.C.Mentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsHektecMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- reinforcementDiepstraten WapeningstaalMentioned in Specialist reinforcement solutions for 33 structures
- ready-mixed concreteDyckerhoff BasalMentioned in Specially formulated mixes significantly reduce carbon footprint
- waterproofingBrabotechMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- construction consortiumDe Groene Boog construction consortiumMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- prefabricatedCiviele technieken deBoerMentioned in A leading name in heavy lifting and specialist transport
- Bonneveld Gewapende Grondconstructies
BonneveldMentioned in One of the largest EPS structures ever built
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA16 Rotterdam
- ThemeMaterials and techniques for infrastructure
- SubjectRoad construction
- CompanyDoka Nederland B.V.