Structured diving operations on the A16 Rotterdam project

With earth bunds, a partly sunken tunnel through Lage Bergse Bos, noise barriers and noise-reducing asphalt, the energy-neutral A16 Rotterdam is set to become one of the best-integrated national roads in the Netherlands. It is also an exceptionally tightly choreographed project. For the construction of the 2.2-kilometre Rottemerentunnel, for example, work is currently under way in eleven cofferdams at the same time. With more than 100 (!) divers, DISA International is making a major contribution. Despite this, there is a sense of calm both below and above the water.

To prevent the groundwater level in the surrounding area from falling, the partly sunken Rottemerentunnel is being built underwater. In other words, after the sheet piles were installed, the various cofferdams were excavated underwater. DISA International’s divers then construct the tunnel floor underwater, after which the cofferdams are pumped dry and the De Groene Boog consortium builds the outer walls and roof in the dry. “This is an enormous project for us, and its schedule also overlapped with the Blankenburgverbinding, which was no small project either,” says Didier De Graaff, Managing Director of DISA International.

Cleaning 6,000 piles with high-pressure water
After the cofferdams had been excavated to around 11 metres below ground level, DISA International’s divers began cleaning the sheet-pile enclosures and levelling the ground between the GEWI piles. “Together with De Groene Boog’s engineers, we came up with a concept during the preparatory phase in which the GEWI bar is greased, wrapped in a PVC pipe and secured with a nut. Our divers then only have to unscrew the nut underwater and remove the pipe, exposing the steel bar,” explains Marc Dröge, General Manager at DISA International. In practice, however, things proved more challenging, as John Penson, Operational Manager at DISA International, discovered first-hand. “The grout used to drill the GEWI piles had been placed too high, so the PVC pipe was also completely encased in grout. We therefore had to clean almost all 6,000 piles using water at 2,500 bar and carefully break away the grout. This exposes the top 7 centimetres of the bar, allowing the underwater concrete floor we install to meet the pile flush.”

Concrete pour stop-end
A unique concept, never used before, was devised to allow the reinforcement to continue from one cofferdam to the next. “In each cofferdam, the ground has been lowered by up to 2.5 metres on either side of the dividing screen. We pour a ‘starter layer’ of concrete in this recessed area. We then position a pour stop-end in the form of a frame, with starter bars projecting towards the dividing screen,” explains Dröge. Penson adds: “Apart from the starter layer, no underwater concrete floor is poured here. That only happens later, once the cofferdam has been pumped dry. The dividing screen is then burned away, additional reinforcement is installed and the ‘section’ measuring 5 metres across the full width of the cofferdam is poured. It is an innovative solution that avoids the contractor having to drill and saw later to install additional reinforcement.”
Safety awareness
After the GEWI piles have been cleaned, a layer of gravel is placed in the cofferdam. DISA International’s divers then install the bearing beams, expansion beams and reinforcement meshes, which are secured to the GEWI piles with plates. “Each cofferdam has 26 rows of 100-metre ‘units’. That means 2.6 kilometres of bearing beams per cofferdam alone,” Penson calculates. A total of 130,000 m3 of underwater concrete will eventually be poured. “Even though we have more than a hundred divers working on the A16, there is no stress. Everyone knows what they have to do,” says De Graaff. “As well as our structured diving operations, the De Groene Boog consortium also commends our proactive approach to safe working. As an organisation, we are proud of that, quite apart from the impressive work our divers deliver every day.”
Have a business enquiry for DISA International? Get in touch
Who worked on A16 Rotterdam
- consortiumDe Groene BoogMentioned in Project A16 Rotterdam to become the first energy-neutral motorway, including a 2.2 km-long tunnel
- lifting and transport frame
SarensMentioned in Reinforced underwater concrete floor for Rottemerentunnel - supplier of reinforcing steelBCSMentioned in Reinforced underwater concrete floor for Rottemerentunnel
- construction consortium
Van OordMentioned in De Groene Boog aims for maximum reduction in CO2 emissions - construction consortiumDura VermeerMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumJohn LaingMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumDe Groene Boog construction consortiumMentioned in GPS-guided precision excavation in the wet cofferdam
- excavation workAannemingsbedrijf Verboon Maasland BVMentioned in GPS-guided precision excavation in the wet cofferdam
- foundation contractor consortium
Voorbij FunderingstechniekMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’ - foundation contractor consortiumFranki GrondtechniekenMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsM.U.C.Mentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsHektecMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- reinforcementDiepstraten WapeningstaalMentioned in Specialist reinforcement solutions for 33 structures
- ready-mixed concreteDyckerhoff BasalMentioned in Specially formulated mixes significantly reduce carbon footprint
- waterproofingBrabotechMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- construction consortiumDe Groene Boog construction consortiumMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- prefabricatedCiviele technieken deBoerMentioned in A leading name in heavy lifting and specialist transport
- Bonneveld Gewapende Grondconstructies
BonneveldMentioned in One of the largest EPS structures ever built
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA16 Rotterdam
- ThemeUnderground construction
- SubjectConcrete
- CompanyDISA International