Concrete

Structured diving operations on the A16 Rotterdam project

In totaal wordt er straks voor 130.000 m3 aan onderwaterbeton gestort.
In totaal wordt er straks voor 130.000 m3 aan onderwaterbeton gestort.

With earth bunds, a partly sunken tunnel through Lage Bergse Bos, noise barriers and noise-reducing asphalt, the energy-neutral A16 Rotterdam is set to become one of the best-integrated national roads in the Netherlands. It is also an exceptionally tightly choreographed project. For the construction of the 2.2-kilometre Rottemerentunnel, for example, work is currently under way in eleven cofferdams at the same time. With more than 100 (!) divers, DISA International is making a major contribution. Despite this, there is a sense of calm both below and above the water.

With more than 100 (!) divers, DISA International is making a major contribution to De Groene Boog.

To prevent the groundwater level in the surrounding area from falling, the partly sunken Rottemerentunnel is being built underwater. In other words, after the sheet piles were installed, the various cofferdams were excavated underwater. DISA International’s divers then construct the tunnel floor underwater, after which the cofferdams are pumped dry and the De Groene Boog consortium builds the outer walls and roof in the dry. “This is an enormous project for us, and its schedule also overlapped with the Blankenburgverbinding, which was no small project either,” says Didier De Graaff, Managing Director of DISA International. 

Work is currently under way in eleven cofferdams at the same time for the construction of the 2.2-kilometre Rottemerentunnel.

Cleaning 6,000 piles with high-pressure water

After the cofferdams had been excavated to around 11 metres below ground level, DISA International’s divers began cleaning the sheet-pile enclosures and levelling the ground between the GEWI piles. “Together with De Groene Boog’s engineers, we came up with a concept during the preparatory phase in which the GEWI bar is greased, wrapped in a PVC pipe and secured with a nut. Our divers then only have to unscrew the nut underwater and remove the pipe, exposing the steel bar,” explains Marc Dröge, General Manager at DISA International. In practice, however, things proved more challenging, as John Penson, Operational Manager at DISA International, discovered first-hand. “The grout used to drill the GEWI piles had been placed too high, so the PVC pipe was also completely encased in grout. We therefore had to clean almost all 6,000 piles using water at 2,500 bar and carefully break away the grout. This exposes the top 7 centimetres of the bar, allowing the underwater concrete floor we install to meet the pile flush.”

To prevent the groundwater level in the surrounding area from falling, the partly sunken Rottemerentunnel is being built underwater.

Concrete pour stop-end

A unique concept, never used before, was devised to allow the reinforcement to continue from one cofferdam to the next. “In each cofferdam, the ground has been lowered by up to 2.5 metres on either side of the dividing screen. We pour a ‘starter layer’ of concrete in this recessed area. We then position a pour stop-end in the form of a frame, with starter bars projecting towards the dividing screen,” explains Dröge. Penson adds: “Apart from the starter layer, no underwater concrete floor is poured here. That only happens later, once the cofferdam has been pumped dry. The dividing screen is then burned away, additional reinforcement is installed and the ‘section’ measuring 5 metres across the full width of the cofferdam is poured. It is an innovative solution that avoids the contractor having to drill and saw later to install additional reinforcement.”

Safety awareness

After the GEWI piles have been cleaned, a layer of gravel is placed in the cofferdam. DISA International’s divers then install the bearing beams, expansion beams and reinforcement meshes, which are secured to the GEWI piles with plates. “Each cofferdam has 26 rows of 100-metre ‘units’. That means 2.6 kilometres of bearing beams per cofferdam alone,” Penson calculates. A total of 130,000 m3 of underwater concrete will eventually be poured. “Even though we have more than a hundred divers working on the A16, there is no stress. Everyone knows what they have to do,” says De Graaff. “As well as our structured diving operations, the De Groene Boog consortium also commends our proactive approach to safe working. As an organisation, we are proud of that, quite apart from the impressive work our divers deliver every day.”   

Have a business enquiry for DISA International? Get in touch

Who worked on A16 Rotterdam

  1. civil engineering componentsMobilisMentioned in A special launching method on the new A16 Rotterdam
  2. all installationsCroonwolter&drosMentioned in A special launching method on the new A16 Rotterdam
  3. clientRijkswaterstaatMentioned in An innovative launching method for the new A16 Rotterdam
  4. consortiumDe Groene BoogMentioned in Project A16 Rotterdam to become the first energy-neutral motorway, including a 2.2 km-long tunnel
  5. lifting and transport frameSarensMentioned in Reinforced underwater concrete floor for Rottemerentunnel
  6. supplier of reinforcing steelBCSMentioned in Reinforced underwater concrete floor for Rottemerentunnel
  7. diving teamsDISAMentioned in Working underwater is 100% teamwork
  8. construction consortiumBesixMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  9. construction consortiumVan OordMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  10. construction consortiumDura VermeerMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  11. construction consortiumTBIMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  12. construction consortiumRebelMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  13. construction consortiumJohn LaingMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  14. temporary bridgesRetro BridgeMentioned in ‘Safely to the other side’ on the A16 Rotterdam project
  15. reinforced earth structuresVoets Gewapende GrondconstructiesMentioned in Sure footing with geogrids
  16. geogridsHUESKER SyntheticMentioned in Sure footing with geogrids
  17. construction consortiumDe Groene Boog construction consortiumMentioned in GPS-guided precision excavation in the wet cofferdam
  18. excavation workAannemingsbedrijf Verboon Maasland BVMentioned in GPS-guided precision excavation in the wet cofferdam
  19. foundation contractor consortiumVoorbij FunderingstechniekMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  20. foundation contractor consortiumFranki GrondtechniekenMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  21. UO calculationsM.U.C.Mentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  22. UO calculationsHektecMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  23. subcontractorKandtMentioned in ‘A brilliant home fixture’
  24. subcontractorFreyssinetMentioned in Building a viaduct over a live motorway?
  25. reinforcementDiepstraten WapeningstaalMentioned in Specialist reinforcement solutions for 33 structures
  26. culvertsDISA InternationalIn this story
  27. ready-mixed concreteDyckerhoff BasalMentioned in Specially formulated mixes significantly reduce carbon footprint
  28. waterproofingBrabotechMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
  29. construction consortiumDe Groene Boog construction consortiumMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
  30. concrete pumpRvR Betonpomp VerhuurMentioned in Piles for traffic gantries drilled ‘remotely’
  31. prefabricatedCiviele technieken deBoerMentioned in A leading name in heavy lifting and specialist transport
  32. formwork specialistDokaMentioned in One-stop shop for shoring and formwork systems
  33. sheet pile profilesArcelorMittalMentioned in Circular sheet piles on the A16 Rotterdam
  34. printing pressDiesekoMentioned in Circular sheet piles on the A16 Rotterdam
  35. Bonneveld Gewapende GrondconstructiesBonneveldMentioned in One of the largest EPS structures ever built
  36. demolition hammersSaes InternationalMentioned in Demolition with military precision

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectA16 Rotterdam
  • ThemeUnderground construction
  • SubjectConcrete
  • CompanyDISA International
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.