An innovative launching method for the new A16 Rotterdam

Rijkswaterstaat is building a new motorway between the A13 near Rotterdam The Hague Airport and the A16/A20 at Terbregseplein. The 11 km-long A16 Rotterdam will help traffic on the A13, A20 and surrounding local roads keep moving smoothly. The new link will improve accessibility and quality of life in the region. The De Groene Boog construction consortium includes TBI companies Mobilis and Croonwolter&dros, with the former responsible for the civil engineering works and the latter for all the systems, including the tunnel systems. We speak to Martijn Jansen, design manager at Mobilis.
Viaduct will be a remarkable feat of engineering
“At Terbregseplein, the viaduct over the existing infrastructure will be a remarkable feat of engineering. We will launch in-situ-cast box girders over Terbregseplein without disrupting traffic. This is also known as the Incremental Launching Method,” Jansen begins. “In civil engineering, this method involves building a complete bridge deck from just one end of the bridge, pushing the bridge superstructure in sections towards the other end. Each girder/traffic direction is 400 metres long. We are currently working on the piers, over which the box girders will later be launched. This method is unique in the Netherlands.” The girders will be pushed at a speed of around 0.5 metres per hour. “It is completely safe, but may be quite a sight for traffic passing underneath. The launch will start from the north, where the construction facility is located.”
The crossing with the HSL is also a challenge: the work must not affect the existing infrastructure. The A16 Rotterdam, which crosses over the HSL, is 8 metres above ground level. Jansen explains: “The ground will be raised using EPS. Micropiles provide the necessary foundation and act as ground anchors under compression. We isolate the micropiles from the HSL box foundation layers by enclosing them in PVC sleeves. This means that all load transfer takes place below the foundation layer of the HSL box. The crossing with the Rotte is also a construction challenge: we are building a tunnel beneath the river on site. It will be safe and watertight.”
Traffic heading for The Hague will no longer use the ring road
“The 11 km-long A16 Rotterdam will help traffic on the A13, A20 and surrounding roads travel faster and more smoothly,” says Jansen. “As well as improving traffic flow, it will reduce disruption for residents living alongside the A20 and A13 at Overschie, cut noise pollution and reduce emissions.”
The A16 will cross over the existing Terbregseplein and then continue through Terbregseveld as a tunnel, passing beneath the Rotte. “After that, the A16 continues in a semi-sunken tunnel beneath Lage Bergse Bos. So you won’t hear, see or smell the new A16 here. This was a requirement set out by Rijkwaterstaat in the route decision. The semi-sunken tunnel emerges from the ground north of Rotterdam. New railway viaducts will be built to cross the HSL and Randstadrail, after which the A16 runs parallel to the N209 before connecting to the A13,” Jansen explains.
Energy-neutral design wins Sustainable Pearl award
The A16 Rotterdam has been carefully integrated into its surroundings, as in many places it cannot be seen, heard or smelled. It is also the world’s first energy-neutral motorway with a tunnel. Jansen explains: “Many parts of the project are powered by solar arrays, including the systems inside the tunnel. The A16 Rotterdam project received a ‘Sustainable Pearl’ award for this, a prize for projects that apply the Sustainable Public Infrastructure Approach in a unique way. Sustainable Pearls are awarded to client-contractor teams that have paid above-average attention to applying the Sustainable Public Infrastructure Approach, or elements of it, on a public infrastructure project.”
The De Groene Boog construction consortium consists of BESIX, Dura Vermeer, Van Oord and TBI companies Croonwolter&dros and Mobilis. Jansen says: “During the tender phase, ambitious commitments were made on materials use and energy consumption during the operational phase. The consortium also tendered at level 5 of the CO2 Performance Ladder, with a minimum CO2 reduction target of 10 per cent. CO2 emissions will be cut to a minimum. As well as using solar arrays and LED lighting, we are also using electric transport and hybrid plant.” The project slogan, ‘Groen en Groos’, is therefore no coincidence.
Three sections
The De Groene Boog construction consortium has divided the A16 Rotterdam project into three sections: the area north of Rotterdam, the tunnel and the area around Terbregseplein. After the contract was awarded, Jansen was responsible for all structures during the preliminary design phase, and is now responsible for designing the civil engineering structures in the area north of Rotterdam. “The tunnel can be seen as one complex, integrated project, involving extensive interaction with the surroundings, local residents, businesses and stakeholders such as Recreatieschap Rottemeren. The area north of Rotterdam presents a geotechnical challenge because of its soft ground and the large number of crossings. At Terbregseplein, we will be using the so-called Incremental Launching Method. This is a unique method in the Netherlands, which Mobilis is using to build the A16 Rotterdam.”
Have a business enquiry for Mobilis? Get in touch
Who worked on A16 Rotterdam
- clientRijkswaterstaatIn this story
- consortiumDe Groene BoogMentioned in Project A16 Rotterdam to become the first energy-neutral motorway, including a 2.2 km-long tunnel
- lifting and transport frame
SarensMentioned in Reinforced underwater concrete floor for Rottemerentunnel - supplier of reinforcing steelBCSMentioned in Reinforced underwater concrete floor for Rottemerentunnel
- construction consortium
Van OordMentioned in De Groene Boog aims for maximum reduction in CO2 emissions - construction consortiumDura VermeerMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumJohn LaingMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumDe Groene Boog construction consortiumMentioned in GPS-guided precision excavation in the wet cofferdam
- excavation workAannemingsbedrijf Verboon Maasland BVMentioned in GPS-guided precision excavation in the wet cofferdam
- foundation contractor consortium
Voorbij FunderingstechniekMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’ - foundation contractor consortiumFranki GrondtechniekenMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsM.U.C.Mentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsHektecMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- reinforcementDiepstraten WapeningstaalMentioned in Specialist reinforcement solutions for 33 structures
- ready-mixed concreteDyckerhoff BasalMentioned in Specially formulated mixes significantly reduce carbon footprint
- waterproofingBrabotechMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- construction consortiumDe Groene Boog construction consortiumMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- prefabricatedCiviele technieken deBoerMentioned in A leading name in heavy lifting and specialist transport
- Bonneveld Gewapende Grondconstructies
BonneveldMentioned in One of the largest EPS structures ever built
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA16 Rotterdam
- SubjectBouwMat
- CompanyRijkswaterstaat
- CompanyMobilis
- CompanyCroonwolter&dros
- CompanyBESIX Nederland BV
- CompanyVan Oord