Special bypass pumping system for renovation of Rotterdam sewage pumping station

Text Chris ElbersImage Fotovitalis en Vanderkamp - The Dutch Water Engineers

Michiel Sieders (projectleider) op de projectlocatie in Rotterdam.
Michiel Sieders (projectleider) op de projectlocatie in Rotterdam.

The Willem Schürmannstraat in Rotterdam’s Crooswijk district has been home to a distinctive sewage pumping station since 1954. The listed building, set between residential blocks and high-rise buildings, has been the scene of a major renovation over the past year and a half. Among other work, the pumps installed in 1985 were replaced with new ones. For the project, Vanderkamp, The Dutch Water Engineers from Zwolle supplied a temporary pumping installation (TPI). This system of five pumps ensured that sewage and rainwater continued to flow in and out without disruption during the works. 

The temporary pumping installation for the listed pumping station.

The renovation of the sewage pumping station in the heart of Rotterdam, commissioned by the Municipality of Rotterdam and carried out by the Van Boekel Bouw & Infra and GW Leidingtechniek joint venture, involved more than simply installing new pumps. During the recently completed project, the entire underground pipework outside the building was also replaced, and several wall penetrations were created. Inside, new floors, walls, stairs and landings were installed alongside the new pumps. The electrical installation was also completely renewed. Thanks to this upgrade, Rotterdam will once again have a well-functioning sewage pumping station for the next 30 years. 

Working safely in an urban environment.

Leading the way in bypass pumping

In parallel with the replacement of the underground pipework, Vanderkamp began setting up the required temporary pumping installation in mid-2023. After the ageing pumping station pumps were taken out of service early last year, the TPI, comprising three dry-installed pumps and two submersible pumps, was connected to the existing sewer network. The system was then brought into operation. “Using the installation, a kind of temporary bypass, sewage was pumped around the building throughout the project and discharged via sewer pipes further downstream,” says Vanderkamp project manager Michiel Sieders. “The pumping capacity of this particular installation was approximately 2,400 m3 per hour in dry weather. When rainwater also entered the system in wet weather, the TPI could ramp up to a maximum of 6,800 m3 per hour. This capacity was also guaranteed in the event that one of the pumps unexpectedly failed during the works.”

Campaign image of a temporary pumping installation in Rotterdam.

More than an exceptional project

Following a site acceptance test, dismantling of the TPI is due to begin in mid-March. This will bring Vanderkamp’s project in Rotterdam to a close. Michiel says the assignment was exceptional for several reasons. “First of all, there is limited space to manoeuvre and work in an urban area like this, especially when it comes to bringing equipment and installation components to and from the site. We also had to be even more mindful than usual of the surrounding area. The building right next to the sewage pumping station houses the Audiologisch Centrum Rotterdam, where audiometric tests are among the services provided. It was therefore essential to keep any noise from our work to an absolute minimum. Thanks in part to excellent communication with the municipality’s environmental manager, we succeeded. The most striking example was the delivery of a wind vessel required for our TPI, a kind of expansion vessel measuring 6 metres high and 5 metres in diameter. We brought this giant to the project site at night using specialist transport, without causing any significant disruption.”     

Een zakelijke vraag aan Vanderkamp – The Dutch Water Engineers? Get in touch

Who worked on it

Willem Schürmannstraat sewage pumping station in Rotterdam, renovation

  1. temporary pumping installationVanderkamp

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectWillem Schürmannstraat sewage pumping station
  • SubjectWater infrastructure
  • CompanyVanderkamp – The Dutch Water Engineers
  • CompanyGW Leidingtechniek BV
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.