Road construction

Successful design and installation of a complex four-part temporary bridge

Text Roel van Gils Image De Groene Boog

Tijdens het Hemelvaartweekend zijn de hulpbruggen succesvol geïnstalleerd. (Beeld: Sjaak Boot Photography)
Tijdens het Hemelvaartweekend zijn de hulpbruggen succesvol geïnstalleerd. (Beeld: Sjaak Boot Photography)

The structure of the existing viaduct (KW58) on the A16 no longer meets requirements. As a result, construction consortium De Groene Boog has received another significant commission from Rijkswaterstaat, in addition to building the A16 Rotterdam. Civiele technieken deBoer was previously mobilised to install a support structure beneath the viaduct, and during this year’s Ascension weekend closure, the civil engineering and jacking specialist moved the eastern temporary bridge (TK59) into place. It is a particularly complex structure, made up of two pairs of sections assembled entirely in-house by sister company Rijnstaal.

Just over two years ago, De Groene Boog called to ask whether we could provide an emergency support structure for viaduct KW58 at very short notice, says Joost Beumer, project manager at Civiele technieken deBoer. “A visual inspection had found that the structure no longer met requirements and would need to be completely replaced rather than renovated. Working with our colleague company Heijmans, we managed to mobilise more than 400 tonnes of materials within a week and build a support structure beneath the existing viaduct, allowing it to continue serving its purpose safely. This gave construction consortium De Groene Boog the opportunity to prepare a sound solution.” 

TK59 was designed and manufactured in-house by Civiele technieken deBoer, with support from sister company Rijnstaal. (Image: Topview luchtfotografie)

Connecting ramp 

To make this complete replacement possible, through traffic is temporarily being diverted over two temporary bridges, one on the east side of the existing structure, for which Civiele technieken deBoer was engaged, and one on the west side, delivered by Retro Bridge. “The temporary bridge we built effectively consists of two parts: one for traffic on the A16/A20 connecting ramp towards Hoek van Holland, and the other for the A16/A20 connecting ramp towards Gouda,” Joost explains. “Each of the two temporary bridges consists of two identical 33-metre sections, giving each bridge a total span of 66 metres.” One small detail: the temporary bridge had to be installed over the long Ascension weekend. “We had just four days. We considered various construction methods, but given the tight schedule, the limited space and the many other works that had to be carried out that weekend, there was only one solution: assemble the bridge sections on site, then move them into place and install them fully assembled.”

Quality requirements

TK59 was designed and manufactured in-house by Civiele technieken deBoer, with support from sister company Rijnstaal, which is based at the same site in Nieuwegein. “We used mainly new components because the bridge had to be manufactured in accordance with NEN-EN1090 EXC.3 and ROK. Using existing equipment proved difficult because of the need to trace the components. The bridge is fully modular, in line with our existing systems. We also incorporated smart solutions from previous projects, enabling us to accommodate non-standard dimensions and making the bridge suitable for future projects too. The components were then transported to a site beside the A16 near exit 27, Prins Alexander, where they were assembled over the 4 weeks before the Ascension weekend.” The temporary bridge was assembled there in two pairs of sections on a sliding structure supplied by Civiele technieken deBoer. “Before the weekend, the first two sections were transferred onto Self-Propelled Modular Trailers (SPMTs), allowing us to slide the final two sections within reach of the SPMTs as well.”

The temporary bridges were successfully installed over the Ascension weekend. The two TK59 bridges rest on an abutment, an intermediate support and an end support, and will remain in place for a maximum of one year. They will then be dismantled and can be reused elsewhere.     

Een zakelijke vraag aan Retro Bridge Nederland? Get in touch

Who worked on A16 Rotterdam

  1. civil engineering componentsMobilisMentioned in A special launching method on the new A16 Rotterdam
  2. all installationsCroonwolter&drosMentioned in A special launching method on the new A16 Rotterdam
  3. clientRijkswaterstaatMentioned in An innovative launching method for the new A16 Rotterdam
  4. consortiumDe Groene BoogMentioned in Project A16 Rotterdam to become the first energy-neutral motorway, including a 2.2 km-long tunnel
  5. lifting and transport frameSarensMentioned in Reinforced underwater concrete floor for Rottemerentunnel
  6. supplier of reinforcing steelBCSMentioned in Reinforced underwater concrete floor for Rottemerentunnel
  7. diving teamsDISAMentioned in Working underwater is 100% teamwork
  8. construction consortiumBesixMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  9. construction consortiumVan OordMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  10. construction consortiumDura VermeerMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  11. construction consortiumTBIMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  12. construction consortiumRebelMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  13. construction consortiumJohn LaingMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  14. temporary bridgesRetro BridgeMentioned in ‘Safely to the other side’ on the A16 Rotterdam project
  15. reinforced earth structuresVoets Gewapende GrondconstructiesMentioned in Sure footing with geogrids
  16. geogridsHUESKER SyntheticMentioned in Sure footing with geogrids
  17. construction consortiumDe Groene Boog construction consortiumMentioned in GPS-guided precision excavation in the wet cofferdam
  18. excavation workAannemingsbedrijf Verboon Maasland BVMentioned in GPS-guided precision excavation in the wet cofferdam
  19. foundation contractor consortiumVoorbij FunderingstechniekMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  20. foundation contractor consortiumFranki GrondtechniekenMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  21. UO calculationsM.U.C.Mentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  22. UO calculationsHektecMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  23. subcontractorKandtMentioned in ‘A brilliant home fixture’
  24. subcontractorFreyssinetMentioned in Building a viaduct over a live motorway?
  25. reinforcementDiepstraten WapeningstaalMentioned in Specialist reinforcement solutions for 33 structures
  26. culvertsDISA InternationalMentioned in Structured diving operations on the A16 Rotterdam project
  27. ready-mixed concreteDyckerhoff BasalMentioned in Specially formulated mixes significantly reduce carbon footprint
  28. waterproofingBrabotechMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
  29. construction consortiumDe Groene Boog construction consortiumMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
  30. concrete pumpRvR Betonpomp VerhuurMentioned in Piles for traffic gantries drilled ‘remotely’
  31. prefabricatedCiviele technieken deBoerMentioned in A leading name in heavy lifting and specialist transport
  32. formwork specialistDokaMentioned in One-stop shop for shoring and formwork systems
  33. sheet pile profilesArcelorMittalMentioned in Circular sheet piles on the A16 Rotterdam
  34. printing pressDiesekoMentioned in Circular sheet piles on the A16 Rotterdam
  35. Bonneveld Gewapende GrondconstructiesBonneveldMentioned in One of the largest EPS structures ever built
  36. demolition hammersSaes InternationalMentioned in Demolition with military precision

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectA16 Rotterdam
  • ThemeExtending the life of roads and civil engineering structures
  • SubjectRoad construction
  • CompanyRetro Bridge Nederland
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.