Successful design and installation of a complex four-part temporary bridge
Text Roel van Gils Image De Groene Boog

The structure of the existing viaduct (KW58) on the A16 no longer meets requirements. As a result, construction consortium De Groene Boog has received another significant commission from Rijkswaterstaat, in addition to building the A16 Rotterdam. Civiele technieken deBoer was previously mobilised to install a support structure beneath the viaduct, and during this year’s Ascension weekend closure, the civil engineering and jacking specialist moved the eastern temporary bridge (TK59) into place. It is a particularly complex structure, made up of two pairs of sections assembled entirely in-house by sister company Rijnstaal.
Just over two years ago, De Groene Boog called to ask whether we could provide an emergency support structure for viaduct KW58 at very short notice, says Joost Beumer, project manager at Civiele technieken deBoer. “A visual inspection had found that the structure no longer met requirements and would need to be completely replaced rather than renovated. Working with our colleague company Heijmans, we managed to mobilise more than 400 tonnes of materials within a week and build a support structure beneath the existing viaduct, allowing it to continue serving its purpose safely. This gave construction consortium De Groene Boog the opportunity to prepare a sound solution.”

Connecting ramp
To make this complete replacement possible, through traffic is temporarily being diverted over two temporary bridges, one on the east side of the existing structure, for which Civiele technieken deBoer was engaged, and one on the west side, delivered by Retro Bridge. “The temporary bridge we built effectively consists of two parts: one for traffic on the A16/A20 connecting ramp towards Hoek van Holland, and the other for the A16/A20 connecting ramp towards Gouda,” Joost explains. “Each of the two temporary bridges consists of two identical 33-metre sections, giving each bridge a total span of 66 metres.” One small detail: the temporary bridge had to be installed over the long Ascension weekend. “We had just four days. We considered various construction methods, but given the tight schedule, the limited space and the many other works that had to be carried out that weekend, there was only one solution: assemble the bridge sections on site, then move them into place and install them fully assembled.”
Quality requirements
TK59 was designed and manufactured in-house by Civiele technieken deBoer, with support from sister company Rijnstaal, which is based at the same site in Nieuwegein. “We used mainly new components because the bridge had to be manufactured in accordance with NEN-EN1090 EXC.3 and ROK. Using existing equipment proved difficult because of the need to trace the components. The bridge is fully modular, in line with our existing systems. We also incorporated smart solutions from previous projects, enabling us to accommodate non-standard dimensions and making the bridge suitable for future projects too. The components were then transported to a site beside the A16 near exit 27, Prins Alexander, where they were assembled over the 4 weeks before the Ascension weekend.” The temporary bridge was assembled there in two pairs of sections on a sliding structure supplied by Civiele technieken deBoer. “Before the weekend, the first two sections were transferred onto Self-Propelled Modular Trailers (SPMTs), allowing us to slide the final two sections within reach of the SPMTs as well.”
The temporary bridges were successfully installed over the Ascension weekend. The two TK59 bridges rest on an abutment, an intermediate support and an end support, and will remain in place for a maximum of one year. They will then be dismantled and can be reused elsewhere.
Een zakelijke vraag aan Retro Bridge Nederland? Get in touch
Who worked on A16 Rotterdam
- consortiumDe Groene BoogMentioned in Project A16 Rotterdam to become the first energy-neutral motorway, including a 2.2 km-long tunnel
- lifting and transport frame
SarensMentioned in Reinforced underwater concrete floor for Rottemerentunnel - supplier of reinforcing steelBCSMentioned in Reinforced underwater concrete floor for Rottemerentunnel
- construction consortium
Van OordMentioned in De Groene Boog aims for maximum reduction in CO2 emissions - construction consortiumDura VermeerMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumJohn LaingMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumDe Groene Boog construction consortiumMentioned in GPS-guided precision excavation in the wet cofferdam
- excavation workAannemingsbedrijf Verboon Maasland BVMentioned in GPS-guided precision excavation in the wet cofferdam
- foundation contractor consortium
Voorbij FunderingstechniekMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’ - foundation contractor consortiumFranki GrondtechniekenMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsM.U.C.Mentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsHektecMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- reinforcementDiepstraten WapeningstaalMentioned in Specialist reinforcement solutions for 33 structures
- ready-mixed concreteDyckerhoff BasalMentioned in Specially formulated mixes significantly reduce carbon footprint
- waterproofingBrabotechMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- construction consortiumDe Groene Boog construction consortiumMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- prefabricatedCiviele technieken deBoerMentioned in A leading name in heavy lifting and specialist transport
- Bonneveld Gewapende Grondconstructies
BonneveldMentioned in One of the largest EPS structures ever built
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA16 Rotterdam
- ThemeExtending the life of roads and civil engineering structures
- SubjectRoad construction
- CompanyRetro Bridge Nederland