Large-scale reuse of traffic gantries
Text Roel van Gils Beeld Birkhoff Staalwerken

As part of the widening of the A27, existing traffic gantries are recovered, refurbished, modified and recoated so they can be put back into service on the upgraded route. Of the 38 traffic gantries being installed along the route, only twelve are entirely new. Some of the refurbished gantries also come from Birkhoff Staalwerken’s own stock.
“On behalf of ALSÉÉN, we are responsible for the entire gantry package along a 40-kilometre stretch, including the construction of new foundations with piles and pile caps,” says Henk van den Ochtend, director of Birkhoff Staalwerken. Most of the foundation work is carried out during the summer road closure. “A closure like that is a great opportunity to make rapid progress. With no traffic around you, it is much safer for our people and you can work far more efficiently. Road users face temporary disruption, but in the end you save a great deal of time.”
Circularity as a guiding principle
One striking feature of the A27 project is the major role played by reuse. “Some of the gantries were recovered from sections 1 and 2 of the A27, which had been upgraded earlier,” says Henk. “After being carefully dismantled, they are modified, recoated and then installed on sections 6, 7 and 8. We are also using gantries from our own refurbishment stock. This not only reduces material use, but also shortens lead times.”

Long spans
In addition to the refurbished gantries, Birkhoff Staalwerken is also manufacturing several new ones. Their dimensions vary. The new gantries have spans of around twenty metres, while the refurbished ones range from twenty to fifty metres. The largest gantry in the project measures 61.5 metres. “That sounds impressive, but we have also built structures measuring 84 metres,” Henk says with a laugh. “So 61.5 metres is actually quite manageable.”
Prefabrication
Now that the foundations for a number of gantries are complete, attention is shifting to installing the superstructures. “We began installing the first gantries in early September. In the weeks beforehand, they were fully prepared in our workshop and fitted with backboards, camera brackets, cable provisions and fixing points. This means the traffic signalling can be connected as soon as they are installed,” Henk explains.

Efficient delivery
Efficiency is also a constant focus during construction. “Where possible, an existing gantry is removed as soon as a new or refurbished one is installed. Combining the work limits the traffic management measures required and saves valuable time on site.” According to Henk, this is also the project’s biggest challenge. “The overall project will take about two years, but you have to get as much done as possible during the road closures. That calls for tight planning, sufficient capacity and perfect coordination between all disciplines.”
According to Henk, one of Birkhoff Staalwerken’s key selling points is that virtually all the work is carried out in-house. “From engineering and production to blasting, coating, refurbishment, assembly and cabling, the entire process takes place under one roof,” he says. “That makes us flexible and enables us to reuse existing gantries to a high standard.”
Een zakelijke vraag aan Birkhoff Staalwerken B.V.? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeLower emissions and more reuse
- SubjectRoad construction
- CompanyBirkhoff Staalwerken B.V.