A leading name in heavy lifting and specialist transport
Text Roel van GilsImage DGB, Sarens, Fotorondleiding, Jaap Pameyer

Sarens has a framework contract with construction consortium De Groene Boog for all routine crane and transport services on the A16 Rotterdam. Some structures require heavy lifting or specialist transport. The Belgian family business is well equipped to handle those too, as it proved once again over the recent long Ascension weekend. Sarens was responsible for moving the concrete trough girder for the viaduct forming part of the new slip road from Hoofdweg (KW52B), and then positioning the temporary bridge on the A16 northbound (TK59).
“Under our framework contract with De Groene Boog, we have been involved in the A16 Rotterdam project from the outset, and have also worked on the construction pit,” begins Willem Ditmer, project manager at Sarens. “We were specifically asked to help plan the transport of KW52B over the long Ascension weekend, and this also brought up the positioning of temporary bridge TK59. Since the A16 was going to be closed that weekend anyway, De Groene Boog took the opportunity to combine the work. As an international crane operator, we are always able to mobilise the equipment required.”

Curved trough girder
KW52B was built on temporary abutments at a site next to the A16. “It is a curved concrete trough girder weighing more than 1,500 tonnes,” says Willem. “Our task was first to manoeuvre it towards the A16, then transport the structure around 500 metres north and position it on the two permanent abutments.” To do so, Sarens prepared two sets of SPMTs (Self-Propelled Modular Trailers), fitted with hydraulic cylinders. “First, we positioned the SPMTs beneath the structure, then jacked the girder clear of the temporary abutments and slowly moved it towards the A16. Once on the motorway, we headed north.” To prevent the structure from sinking, the ground at the construction site and the verge were excavated in advance and made sufficiently load-bearing. Steel road plates were used on the motorway to protect the asphalt. “The asphalt is reasonably strong in itself, but it is not suitable for manoeuvring our SPMTs. They would cause rutting.”

SPMTs
Sarens deployed two identical sets of 52 axle lines for this operation. “Each axle line has four wheels, so that’s 208 wheels on each side,” Willem explains. SPMTs are modular trailers typically available with 4, 5 or 6 axle lines. They are designed to fit in a shipping container, so they can be sent anywhere in the world. And Sarens does just that. Demand is high. The company owns more than 3,000 axle lines, but had to call on a third party for modular trailers to move KW52B. “In theory, the modules can be coupled together without limit, depending on requirements. They are powered by a separate power pack, which generates the energy needed to drive, steer and lift. All the modules are connected mechanically, electrically and by data links. The data connection is needed to transmit the various steering programmes. These programmes can be configured so that we can carry out virtually any manoeuvre required. That is the great advantage of this type of trailer.”

Bracing
Back to the A16 Rotterdam. The concrete trough girder was carefully manoeuvred into its final position on the motorway at a speed of 3 km/h. “Once in position, we lowered the girder onto the abutments. The entire operation, from picking it up at the construction site to placing it in its final position, took 3 hours and 15 minutes,” says Willem. “The two sets of SPMTs were connected to each other with braces. That was a deliberate choice. One trailer combination was positioned directly beneath the structure, while the other was at an angle because of the curved girder. We can account for that difference in the SPMTs’ computer controls, but even a slight misalignment could have consequences. With the bracing system between them, we could be sure the trailers stayed aligned. And that proved to be the case. Our work was done at 13:30 on the Friday after Ascension Day. At least, as far as structure KW52B was concerned, because we had another one waiting for us.”

Risk management
The following day, it was TK59’s turn. “In consultation with De Groene Boog, we decided to use different sets of SPMTs for this operation,” Willem continues. “First, to manage the scheduling risk. If transport of KW52B was delayed for any reason, we did not want that to affect the positioning of temporary bridge TK59. The space available on Hoofdweg to move TK59 into position was also very limited. We did not want to have to carry out any extra transport manoeuvres.” Temporary bridge TK59 consists of four sections, each weighing up to 285 tonnes, and was preassembled by Civiele technieken deBoer on a site at the junction of the A16 and the Prins Alexander exit. Willem: “The ground conditions there were not ideal either. We therefore decided to slide the sections over our SPMTs, so De Groene Boog only had to improve the ground over a limited area.”

Jacking towers
In the week before the Ascension weekend, Sarens first used two mobile cranes, with capacities of 700 and 650 tonnes, to install the precast abutments for TK59, each weighing up to 100 tonnes. “We also completed all the preparations that week to ensure the move went as efficiently as possible. Two bridge sections were ready to go on the SPMTs, and two were on the sliding structure. We first had to jack the bridge decks up, then lower them into position, because the deck had to be moved over the new abutments. To do that, we fitted the SPMTs with jacking towers,” Willem explains. “This operation also went perfectly. Although we started slightly later because of problems with rising groundwater, we made up some time during the move. That is the quality we stand for: achieving the intended result together with the client, thanks to our extensive range of equipment and huge global crane fleet.”
The SPMTs used to position TK59 were transported to Frankfurt am Main for their next job immediately after the project. “We move a bridge into position almost every weekend at the moment,” says Willem. Sarens will also be providing further crane services on the A16 Rotterdam under its framework contract in the coming period.
A business enquiry for Sarens? Get in touch
Who worked on A16 Rotterdam
- consortiumDe Groene BoogMentioned in Project A16 Rotterdam to become the first energy-neutral motorway, including a 2.2 km-long tunnel
- lifting and transport frame
SarensMentioned in Reinforced underwater concrete floor for Rottemerentunnel - supplier of reinforcing steelBCSMentioned in Reinforced underwater concrete floor for Rottemerentunnel
- construction consortium
Van OordMentioned in De Groene Boog aims for maximum reduction in CO2 emissions - construction consortiumDura VermeerMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumJohn LaingMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumDe Groene Boog construction consortiumMentioned in GPS-guided precision excavation in the wet cofferdam
- excavation workAannemingsbedrijf Verboon Maasland BVMentioned in GPS-guided precision excavation in the wet cofferdam
- foundation contractor consortium
Voorbij FunderingstechniekMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’ - foundation contractor consortiumFranki GrondtechniekenMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsM.U.C.Mentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsHektecMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- reinforcementDiepstraten WapeningstaalMentioned in Specialist reinforcement solutions for 33 structures
- ready-mixed concreteDyckerhoff BasalMentioned in Specially formulated mixes significantly reduce carbon footprint
- waterproofingBrabotechMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- construction consortiumDe Groene Boog construction consortiumMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- prefabricatedCiviele technieken deBoerIn this story
- Bonneveld Gewapende Grondconstructies
BonneveldMentioned in One of the largest EPS structures ever built
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA16 Rotterdam
- SubjectRoad construction
- CompanyCiviele technieken deBoer
- CompanySarens



























