Specially formulated mixes significantly reduce carbon footprint
Text Roel van GilsImage Dyckerhoff Basal

Building the new A16 Rotterdam motorway requires a huge quantity of ready-mixed concrete. Dyckerhoff Basal, whose four nearby ready-mix plants effectively ‘bracket’ the A16 Rotterdam, was commissioned by construction consortium De Groene Boog to supply a total of 400,000 m3 of ready-mixed concrete. By using specially selected blast-furnace cement in the various mixes, the CO2 footprint is up to around 55% lower than that of Portland cement.
The first deliveries of ready-mixed concrete began in 2019, says Ron Mulder, concrete technologist at Dyckerhoff Basal. “Initially, De Groene Boog planned to use a mobile concrete batching plant, but finding a suitable site in this busy area proved a major challenge. Since our plants in the western region are nearby, in Delft, Rotterdam, Dordrecht and The Hague, the decision was quickly made. At peak times, the plant in Nieuwegein was also brought into operation.” One of the biggest peaks involved supplying more than 29,000 m3 of ready-mixed concrete in a month. “That was a real challenge, particularly given the global problems with cement supplies. But in the end, everything worked out well.”
CO2 savings
Dyckerhoff Basal drew up the mix schedule in consultation with De Groene Boog’s concrete technologists. “The mixes cover various strength classes, ranging from C12/15 to C60/75, and a range of consistencies, including self-compacting concrete,” explains Ron. “The different types of cement come from Dyckerhoff plants in Germany. We mainly use blast-furnace cement (CEM III/B 42,5N) from Neuss and ECODUR (CEM III/B-L) from Neuwied. Together, these achieve a 52-55% reduction in CO2 emissions compared with the use of standard Portland cements.” Since 2019, Dyckerhoff Basal has supplied around 380,000 m3 of ready-mixed concrete to the project, most of it for the Rottemerentunnel.
Question about this story? Ask your question
Who worked on A16 Rotterdam
- consortiumDe Groene BoogMentioned in Project A16 Rotterdam to become the first energy-neutral motorway, including a 2.2 km-long tunnel
- lifting and transport frame
SarensMentioned in Reinforced underwater concrete floor for Rottemerentunnel - supplier of reinforcing steelBCSMentioned in Reinforced underwater concrete floor for Rottemerentunnel
- construction consortium
Van OordMentioned in De Groene Boog aims for maximum reduction in CO2 emissions - construction consortiumDura VermeerMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumJohn LaingMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
- construction consortiumDe Groene Boog construction consortiumMentioned in GPS-guided precision excavation in the wet cofferdam
- excavation workAannemingsbedrijf Verboon Maasland BVMentioned in GPS-guided precision excavation in the wet cofferdam
- foundation contractor consortium
Voorbij FunderingstechniekMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’ - foundation contractor consortiumFranki GrondtechniekenMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsM.U.C.Mentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- UO calculationsHektecMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
- reinforcementDiepstraten WapeningstaalMentioned in Specialist reinforcement solutions for 33 structures
- ready-mixed concreteDyckerhoff BasalIn this story
- waterproofingBrabotechMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- construction consortiumDe Groene Boog construction consortiumMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
- prefabricatedCiviele technieken deBoerMentioned in A leading name in heavy lifting and specialist transport
- Bonneveld Gewapende Grondconstructies
BonneveldMentioned in One of the largest EPS structures ever built
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA16 Rotterdam
- ThemeLower emissions and more reuse
- SubjectUnderground infrastructure
- CompanyDyckerhoff Basal