Road construction

‘A brilliant home fixture’

Drilling the piles in the Rotte.
Drilling the piles in the Rotte.

“Working on the A16 Rotterdam infrastructure project is a real pleasure for Kandt BV,” says Marco Kandt, owner and director of the company that bears his name. “The project is literally just around the corner from us, so this is a brilliant home fixture. It is particularly special for us personally because my family’s roots are on the Rottekade. My father’s childhood home is just 200 metres from the Rotte crossing.” Kandt BV was engaged as a subcontractor by foundation contractor Voorbij-Franki. Marco tells us about the work carried out.

“During the 2020 construction industry summer holiday, we worked non-stop for 6 days on the foundations for a pier at KW52a, partly working within height restrictions because of the viaduct above.”

Pressing and vibrating sheet piles

Kandt BV was involved in several disciplines on the project. Marco says: “Our work began with pressing and vibrating sheet piles at the roundabout in sub-area 1, near the airport. Next came structure 52 in sub-area 3, the Terbregseplein. During the 2020 construction industry summer holiday, we worked non-stop for 6 days on the foundations for a pier at KW52a, partly working within height restrictions because of the viaduct above. At times, space was so tight it felt like ‘working on a postage stamp’.”

From late 2020, Kandt BV installed LeKa grout-injection piles at the deepest point of the tunnel.

The deepest point of the Rottemerentunnel

From late 2020, Kandt BV installed LeKa grout-injection piles at the deepest point of the tunnel. Marco explains: “Extra-strong piles were needed at the deepest point of the tunnel. We drilled on both banks and in the water itself. The LeKa pile is a cast-in-situ, displacement concrete pile with a permanent steel casing, installed to depth by screwing it in, in this case with grout injection. The pile consists of a steel casing fitted with a conical screw point and surrounded by grout. Once the pile has been installed, a reinforcement cage is lowered into the casing, which is then filled with concrete. It is highly specialised work, not least because all the piles were installed below ground level or the water surface, and the pile heads were formed with ribs. These ribs are incorporated into the underwater concrete, securing the underwater concrete floor directly to the piles.”

Kandt BV was involved in several disciplines on the project.

Disused cast-iron pipe partly drilled through

Another job carried out by Kandt was to drill through part of an old cast-iron pipe beneath the Rotte, which was no longer in use. “The pipe was in the way of the sheet piling. Removing it was not an option, but drilling through it was. This meant the sheet pile could be installed there too.” In addition to the work described above, Kandt also carried out a fair amount of lifting. “We carried out various lifting operations while the reinforcement and formwork were being installed at structure 52,” says Marco.

Kandt will remain on site for a while yet

Marco is already looking forward to the next job Kandt BV will undertake for De Groene Boog: installing all the tubular foundations for the noise barriers. “Steel tubes into which another contractor installs reinforcement cages, followed by the casting of pile caps. The noise barriers are then mounted on those pile caps. So we can continue to enjoy working on one of the finest infrastructure projects in the Netherlands, right on our doorstep.”     

A business enquiry for Kandt Aannemings- en Funderingsbedrijf BV? Get in touch

Who worked on A16 Rotterdam

  1. civil engineering componentsMobilisMentioned in A special launching method on the new A16 Rotterdam
  2. all installationsCroonwolter&drosMentioned in A special launching method on the new A16 Rotterdam
  3. clientRijkswaterstaatMentioned in An innovative launching method for the new A16 Rotterdam
  4. consortiumDe Groene BoogMentioned in Project A16 Rotterdam to become the first energy-neutral motorway, including a 2.2 km-long tunnel
  5. lifting and transport frameSarensMentioned in Reinforced underwater concrete floor for Rottemerentunnel
  6. supplier of reinforcing steelBCSMentioned in Reinforced underwater concrete floor for Rottemerentunnel
  7. diving teamsDISAMentioned in Working underwater is 100% teamwork
  8. construction consortiumBesixMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  9. construction consortiumVan OordMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  10. construction consortiumDura VermeerMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  11. construction consortiumTBIMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  12. construction consortiumRebelMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  13. construction consortiumJohn LaingMentioned in De Groene Boog aims for maximum reduction in CO2 emissions
  14. temporary bridgesRetro BridgeMentioned in ‘Safely to the other side’ on the A16 Rotterdam project
  15. reinforced earth structuresVoets Gewapende GrondconstructiesMentioned in Sure footing with geogrids
  16. geogridsHUESKER SyntheticMentioned in Sure footing with geogrids
  17. construction consortiumDe Groene Boog construction consortiumMentioned in GPS-guided precision excavation in the wet cofferdam
  18. excavation workAannemingsbedrijf Verboon Maasland BVMentioned in GPS-guided precision excavation in the wet cofferdam
  19. foundation contractor consortiumVoorbij FunderingstechniekMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  20. foundation contractor consortiumFranki GrondtechniekenMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  21. UO calculationsM.U.C.Mentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  22. UO calculationsHektecMentioned in The foundation joint venture is De Groene Boog’s ‘invisible friend’
  23. subcontractorKandtIn this story
  24. subcontractorFreyssinetMentioned in Building a viaduct over a live motorway?
  25. reinforcementDiepstraten WapeningstaalMentioned in Specialist reinforcement solutions for 33 structures
  26. culvertsDISA InternationalMentioned in Structured diving operations on the A16 Rotterdam project
  27. ready-mixed concreteDyckerhoff BasalMentioned in Specially formulated mixes significantly reduce carbon footprint
  28. waterproofingBrabotechMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
  29. construction consortiumDe Groene Boog construction consortiumMentioned in Watertight construction with flexible joint seals and a liquid-tight layer
  30. concrete pumpRvR Betonpomp VerhuurMentioned in Piles for traffic gantries drilled ‘remotely’
  31. prefabricatedCiviele technieken deBoerMentioned in A leading name in heavy lifting and specialist transport
  32. formwork specialistDokaMentioned in One-stop shop for shoring and formwork systems
  33. sheet pile profilesArcelorMittalMentioned in Circular sheet piles on the A16 Rotterdam
  34. printing pressDiesekoMentioned in Circular sheet piles on the A16 Rotterdam
  35. Bonneveld Gewapende GrondconstructiesBonneveldMentioned in One of the largest EPS structures ever built
  36. demolition hammersSaes InternationalMentioned in Demolition with military precision

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectA16 Rotterdam
  • SubjectRoad construction
  • CompanyKandt Aannemings- en Funderingsbedrijf BV
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.