Concrete repairs under high voltage
Text Roel van Gils Image BE Inject

The Krammersluizen complex is not only due for a technical upgrade, its concrete structure is also being carefully refurbished and repaired where necessary. BE Inject, part of Franki Grondtechnieken, was invited to submit a tender for this specialist repair work. Working within the limited construction windows, the company is addressing dozens of repair locations, ranging from minor damage to multiple cracks.
The various instances of concrete damage came to light during inspection work, explains Nico Heiligers, business manager at BE Inject. “Under the applicable BRL guidelines, this type of damage must first be carefully investigated and treated. This involves mapping the damaged concrete or removing it where necessary, and checking how deep the deterioration extends. Only then can the actual repair work begin.”

A tailored approach
BE Inject was assigned around fifty locations at the Krammersluizen. The extent of the damage varies considerably: from minor damage measuring just a few centimetres to multiple cracks that need to be injected. “Every instance of damage calls for its own approach,” says Nico. “It always starts by exposing the area fully, down to sound concrete. We then apply a protective coating to the reinforcement and repair the surface using specialist primers and repair mortars.”
According to Nico, the biggest challenge is not so much applying the mortar as preparing the area and ensuring the bond and curing are of the right quality. “Only when these steps are carried out perfectly will the repair last, allowing us to guarantee the same long service life as the original concrete.”

Concrete repairs in the lock chambers
BE Inject is carrying out concrete repairs on various parts of the complex, including in the lock chambers. “We can only start that work once the chamber has been completely pumped dry,” Nico notes. “Scaffolding is then erected and the walls are cleaned. So our available work period has to fit in with all the other activities being carried out by the ZEEKR consortium. It calls for maximum flexibility.” Nico says this is precisely where BE Inject stands out. “We began by rapidly fixing leaks in construction pits, where an immediate response is often essential. That ability to respond quickly is proving valuable on this project too. Depending on the schedule, we deploy one crew, or several teams at the same time if necessary.”

Qualified and certified
For BE Inject, the project marks an important step in the organisation’s further development. “Previously, we mainly carried out concrete repairs on a smaller scale,” says Nico. “The work at the Krammersluizen is one of our first major projects in which this discipline is a central focus. As a department, we have also been working hard to obtain BRL 3201 certification for the KOMO concrete repair certificate. All our employees hold the necessary qualifications as concrete repair and injection specialists, and are able to work across our specialist areas of concrete repair, injection technology and ground injection.”
The scale of the lock complex also impresses Nico. “The project is so large that you could almost get lost in it,” he says. “It’s an assignment we’re proud to be working on as a team, and one that shows we’re ready for the biggest challenges in concrete repair.”
Question about this story? Ask your question
Who worked on Krammersluizencomplex
- main contractor
BESIXMentioned in The power of systems integration in the renovation of the Krammer Locks complex - constructionZEEKRMentioned in The power of systems integration in the renovation of the Krammer Locks complex
- system integrationINNOCYMentioned in The power of systems integration in the renovation of the Krammer Locks complex
- system integrationCPM ConsultancyMentioned in The power of systems integration in the renovation of the Krammer Locks complex
- replacement, renovation and modificationIemantsMentioned in Modified 400-tonne lock gates improve the lockage process
- subcontractor
DISA InternationalMentioned in The foundations for a new pumping station are being laid underwater - concrete repairBE InjectIn this story
- independent baseline inspection
A-QuinMentioned in Independent baseline inspection prevents surprises - machinery safety consultant
KaderMentioned in CE marking for one of the Netherlands’ most complex lock projects - lead hydraulic engineering engineerHessel Voortman Engineering ConsultancyMentioned in A masterclass in hydraulic engineering
Keep following this
Get an email when a new story is published. No account needed.
- ProjectKrammersluizencomplex
- ThemeExtending the life of roads and civil engineering structures
- SubjectConcrete
- CompanyBE Inject