Vanderkamp involved in redevelopment of AWZI Almere
Text and images Vanderkamp

The wastewater treatment plant (AWZI) in Almere, operated by Waterschap Zuiderzeeland, is undergoing a complete redevelopment and sustainability upgrade to keep pace with the city’s growth and treat wastewater more efficiently and sustainably. The work is taking place in 2025 and 2026. Thanks to Vanderkamp’s temporary pumping systems and pipework, the plant will remain operational throughout the redevelopment.
The plant’s current treatment capacity and ageing sludge line are no longer adequate. Waterschap Zuiderzeeland is therefore undertaking a major upgrade of AWZI Almere. Van Haarst, as main contractor, is responsible for the overall refurbishment of the plant. The temporary pumping system and associated pipework have been subcontracted to Vanderkamp.

Vanderkamp is supplying a complete temporary pumping system with a screenings washer, which collects and cleans the incoming wastewater before conveying it to the activated sludge tanks. This keeps the treatment process running continuously, including while the new primary settlement tank is being connected.
Rick van der Kamp explains: “The complexity of this project lies in distributing the flow, and also in the above-ground tanks around the screenings washer. We have to fill the screenings washer and then distribute the flow to various basins. So we are not just pumping here, we are conveying, screening, pumping and distributing.”
As with many complex water projects, Vanderkamp is delivering a fully bespoke solution, from design and hydraulic calculations to installation, pipework and 24/7 monitoring. Sustainability is a key priority, including through the use of electrically driven pumps.
In short, thanks to the expertise of Vanderkamp, The Dutch Water Engineers, AWZI Almere can be upgraded safely and efficiently, with the treatment process running continuously and in line with circular and sustainable ambitions.
Een zakelijke vraag aan Vanderkamp – The Dutch Water Engineers? Get in touch
Who worked on it
AWZI Almere in Almere
- main contractorVan Haarst
Keep following this