Working as one team in the northern section of the Julianakanaal
Text Suzanne van Gaale Image Ermers Grondverzet

Work has been under way for months on the Julianakanaal to make it suitable for larger inland vessels. The 4-kilometre stretch has been divided into three work sections: North, Middle and South. The northern section is the most challenging. Ermers Grondverzet from Nuland is helping get the job done with eight machines.
“It’s a big job,” says Rick Ermers, the third generation of the Ermers Grondverzet family. “We’ve been working here continuously since September last year. We’re doing this as part of a team of several earthmoving companies, working for Van den Herik-Sliedrecht. We excavate the soil, grade it, install the bentonite mats and, finally, lay a gravel layer and a layer of riprap.”

Family business
Ermers Grondverzet is a family business founded in 1968. Its work is highly varied, ranging from preparing sites for construction and laying sewers and golf courses to dike improvements and the construction of a new underpass beneath the A2. The company has an extensive, modern fleet, including crawler excavators and wheel loaders, as well as vibratory rollers and bulldozers. It only hires out its machines with an experienced, qualified operator.
Eight machines
Rick is working on the Julianakanaal project as a site supervisor. Ermers Grondverzet is also using two wheel loaders, four long-reach excavators and one standard excavator. “We work on both small and large projects, but the Julianakanaal is one of the biggest we’ve worked on to date. What’s happening here is truly unique. We’re working with several contractors as one team, which makes the job rewarding.”
Question about this story? Ask your question
Who worked on Julianakanaal
- Trimble dealer
SITECHMentioned in Efficient excavation on the Julianakanaal thanks to Trimble machine control - setting outPS SurveyMentioned in Efficient excavation on the Julianakanaal thanks to Trimble machine control
- main contractorVan den Herik-SliedrechtMentioned in PS Survey deploys a range of surveying techniques on the Julianakanaal
- groundworksJac RijkMentioned in Julianakanaal: A mega-project involving 180 machines, 200 workers and nearly 1.5 million tonnes of earth
- earthworks partnerFL BVMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- earthmoving companiesErmersMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- earthmoving companiesBC van der VisMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- project control
Count & CooperMentioned in Project controls demonstrate their value on the Julianakanaal project - clientRijkswaterstaatMentioned in Project controls demonstrate their value on the Julianakanaal project
- natural stoneRoxx InternationalMentioned in 500,000 tonnes of natural stone used in the Julianakanaal
- water management
VanderkampMentioned in The challenge for Van der Kamp: how do you keep the Julianakanaal dry? - earthworksErmers GrondverzetIn this story
- earthworks
Van Schaik GrondverzetMentioned in Van Schaik deploys heavy equipment for earthworks on the Julianakanaal
Keep following this
Get an email when a new story is published. No account needed.
- ProjectJulianakanaal
- SubjectWater infrastructure
- CompanyErmers Grondverzet