Janson Bridging designs 48-metre-long, 11-metre-wide temporary transport bridge over Julianakanaal
Text Suzanne van Gaale Image Janson Bridging

An efficient and safe transport solution was essential for the widening and deepening of the Julianakanaal. The enormous volume of earthworks and delivery of heavy rock armour would have placed considerable strain on the surrounding road network. To minimise disruption and maintain accessibility, Van den Herik-Sliedrecht called on Janson Bridging’s expertise.
Working with Van den Herik, Janson Bridging designed a temporary bridge over the Obbichterweg, with a minimum clearance of 4.5 metres. Using standard bridge components, they created an efficient structure 48 metres long, made up of two seamlessly connected sections, each 24 metres long. Janson Bridging handled everything, from design to installation and dismantling. “We have our own engineering department, which means we can respond very quickly to our clients,” explains Marcel van Fessem, General Manager at Janson Bridging Nederland. Janson Bridging specialises in modular temporary bridges, pontoons, ro-ro vessels and ferries for both civil and military applications. “Our bridges are modular and circular,” adds colleague and project manager Abdel al Harchaoui. “That means we can, in principle, build to any required dimensions, from a small footbridge to a large transport bridge. We offer various types, including plate girder bridges, beam bridges, movable bridges and truss bridges.”

A safe, functional bridge for heavy construction traffic
Safety and functionality are paramount when building a new bridge. The design was therefore adapted to provide sufficient clearance between the carriageways and the spill guards. This not only creates a safe working environment, but also prevents materials from the bridge from falling onto the road network below. To ensure safety, the temporary bridge was made wider than originally planned. Strategically positioned barriers create a safe zone on either side, which can also serve as a footpath for staff. The design also specifically accounted for heavy transport loads. The bridge is designed to allow four Volvo A30 dump trucks to cross at the same time, ensuring smooth and efficient construction traffic flow.

A 7% gradient
The bridge is supported by a foundation of steel tubular piles and beams, firmly anchored in the ground. Both the foundation and the bridge itself are temporary. “One important challenge was the gradient: Rijkswaterstaat specified a maximum of 7%, allowing for longer, less steep approach ramps. This affected the substructure, which we developed in close collaboration with De Vries uit Werkendam and Van den Herik. Thanks to the precise dimensions, the bridge was installed without difficulty.”

Installed in a single day
A Janson plate girder bridge, type JSB-1, has been installed for the Julianakanaal. Measuring 48 metres long and 11 metres wide, it was specially designed for heavy construction traffic. Abdel explains: “We build every bridge ourselves and, wherever possible, prefabricate the components at our own site. This shortens construction time on site and reduces disruption. The bridge for the Julianakanaal consisted of six sections weighing 34 tonnes each, which we installed in their final position in a single day using a 250-tonne crane.”
Minimal disruption, maximum convenience
The transport bridge over the Julianakanaal may not be the most eye-catching bridge, but it is unique in its own right. Marcel says: “Every temporary bridge from Janson Bridging is bespoke, tailored to specific needs, requirements and conditions. This bridge allows local people to continue travelling and cycling along the Obbichterweg without detours or disruption. This keeps disruption for local residents to a minimum during the works.”
Een zakelijke vraag aan JANSON BRIDGING NEDERLAND B.V.? Get in touch
Who worked on Julianakanaal
- Trimble dealer
SITECHMentioned in Efficient excavation on the Julianakanaal thanks to Trimble machine control - setting outPS SurveyMentioned in Efficient excavation on the Julianakanaal thanks to Trimble machine control
- main contractorVan den Herik-SliedrechtMentioned in PS Survey deploys a range of surveying techniques on the Julianakanaal
- groundworksJac RijkMentioned in Julianakanaal: A mega-project involving 180 machines, 200 workers and nearly 1.5 million tonnes of earth
- earthworks partnerFL BVMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- earthmoving companiesErmersMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- earthmoving companiesBC van der VisMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- project control
Count & CooperMentioned in Project controls demonstrate their value on the Julianakanaal project - clientRijkswaterstaatMentioned in Project controls demonstrate their value on the Julianakanaal project
- natural stoneRoxx InternationalMentioned in 500,000 tonnes of natural stone used in the Julianakanaal
- water management
VanderkampMentioned in The challenge for Van der Kamp: how do you keep the Julianakanaal dry? - earthworksErmers GrondverzetMentioned in Working as one team in the northern section of the Julianakanaal
- earthworks
Van Schaik GrondverzetMentioned in Van Schaik deploys heavy equipment for earthworks on the Julianakanaal