Foundations

Heavy-duty foundation for temporary transport bridge over the Julianakanaal

Tekst Suzanne van Gaale Beeld De Vries Werkendam

De fundatie bestaat uit twee maal vier buispalen met daar bovenop een staalconstructie.
De fundatie bestaat uit twee maal vier buispalen met daar bovenop een staalconstructie.

A huge quantity of soil and rock is being excavated as part of the widening and deepening of the Julianakanaal, around 1,400,000 tonnes in total. All this material has to be removed. To minimise disruption to the surrounding area, a temporary transport bridge has been built. Thanks to the bridge, the Obbichterweg will remain open to traffic during the works. The bridge foundation was built and installed by De Vries Werkendam.

“The ground conditions in Limburg and around the Julianakanaal are very different from those elsewhere in the Netherlands,” explains Jorrit Smeets, director of De Vries Werkendam. “That calls for considerable expertise and craftsmanship. That is why Van den Herik-Sliedrecht brought us in. With time pressing, they were looking for a reliable partner they knew would deliver quality and respond quickly.” De Vries Werkendam specialises in concrete and hydraulic engineering. The company is experienced in building quay walls, bank protection structures, locks, bridges and (special) concrete structures. It also has two complementary disciplines: ground anchors, under the name De Vries Titan, and post-tensioning technology, under the name De Vries VSP. 

Unpredictable ground conditions

To return to the ground conditions around the Julianakanaal: the ground is hard and somewhat unpredictable. “That was one of the challenges for us. So we opted for a heavier foundation design to avoid any risk of movement or settlement,” explains project manager Gerard van der Stelt. “Van den Herik designed the temporary transport bridge. The foundation consists of two sets of four tubular piles, topped by a steel structure. The piles are 76 and 92 centimetres in diameter. They were driven into the ground in a short time using a machine fitted with a heavier, oversized vibratory hammer. We also used this heavier hammer because the ground was hard and somewhat unpredictable.” 

The piles are 76 and 92 centimetres in diameter.

Expert welding

After the piles had been installed, Van den Herik filled them with concrete. De Vries Werkendam then welded the steel beams on top. “The welding had to be carried out with the utmost precision, to execution class 3, because of the bridge that would sit on top and the design requirements. This calls for skilled workmanship. We prepared the structure in our own workshop, in accordance with the applicable welding standard, NEN 1090.” A ground investigation was carried out before the bridge was installed. This was also needed to design the bridge. “The design produces certain specifications for the dimensions of the tubular piles and the supporting structure. We also need that information to determine the forces required to install the foundation.”

Synergy through collaboration

The work on the Julianakanaal was a relatively small job for De Vries Werkendam. “But,” says Jorrit, “it was a job with a tight deadline and quality was paramount. Our collaboration with Van den Herik always works very well. Our specialisms complement each other perfectly, creating excellent synergy.”     

Een zakelijke vraag aan De Vries Werkendam? Neem contact op

Wie aan Julianakanaal werkte

  1. maatvoeringPS SurveyGenoemd in Efficient excavation on the Julianakanaal thanks to Trimble machine control
  2. hoofdaannemerVan den Herik-SliedrechtGenoemd in PS Survey deploys a range of surveying techniques on the Julianakanaal
  3. grondverzetpartnerFL BVGenoemd in Complexity of Julianakanaal calls for flexibility and quick decision-making
  4. grondverzetbedrijvenErmersGenoemd in Complexity of Julianakanaal calls for flexibility and quick decision-making
  5. grondverzetbedrijvenBC van der VisGenoemd in Complexity of Julianakanaal calls for flexibility and quick decision-making
  6. projectbeheersingCount & CooperGenoemd in Project controls demonstrate their value on the Julianakanaal project
  7. opdrachtgeverRijkswaterstaatGenoemd in Project controls demonstrate their value on the Julianakanaal project
  8. natuursteenRoxx InternationalGenoemd in 500,000 tonnes of natural stone used in the Julianakanaal
  9. watermanagementVanderkampGenoemd in The challenge for Van der Kamp: how do you keep the Julianakanaal dry?
  10. grondverzetErmers GrondverzetGenoemd in Working as one team in the northern section of the Julianakanaal
  11. grondverzetVan Schaik GrondverzetGenoemd in Van Schaik deploys heavy equipment for earthworks on the Julianakanaal

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectJulianakanaal
  • OnderwerpFoundations
  • BedrijfDe Vries Titan B.V.
  • BedrijfDe Vries Werkendam
Deel dit artikel

Volgen op Grond/Weg/Waterbouw Nederland

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.