Heavy-duty foundation for temporary transport bridge over the Julianakanaal
Tekst Suzanne van Gaale Beeld De Vries Werkendam

A huge quantity of soil and rock is being excavated as part of the widening and deepening of the Julianakanaal, around 1,400,000 tonnes in total. All this material has to be removed. To minimise disruption to the surrounding area, a temporary transport bridge has been built. Thanks to the bridge, the Obbichterweg will remain open to traffic during the works. The bridge foundation was built and installed by De Vries Werkendam.
“The ground conditions in Limburg and around the Julianakanaal are very different from those elsewhere in the Netherlands,” explains Jorrit Smeets, director of De Vries Werkendam. “That calls for considerable expertise and craftsmanship. That is why Van den Herik-Sliedrecht brought us in. With time pressing, they were looking for a reliable partner they knew would deliver quality and respond quickly.” De Vries Werkendam specialises in concrete and hydraulic engineering. The company is experienced in building quay walls, bank protection structures, locks, bridges and (special) concrete structures. It also has two complementary disciplines: ground anchors, under the name De Vries Titan, and post-tensioning technology, under the name De Vries VSP.
Unpredictable ground conditions
To return to the ground conditions around the Julianakanaal: the ground is hard and somewhat unpredictable. “That was one of the challenges for us. So we opted for a heavier foundation design to avoid any risk of movement or settlement,” explains project manager Gerard van der Stelt. “Van den Herik designed the temporary transport bridge. The foundation consists of two sets of four tubular piles, topped by a steel structure. The piles are 76 and 92 centimetres in diameter. They were driven into the ground in a short time using a machine fitted with a heavier, oversized vibratory hammer. We also used this heavier hammer because the ground was hard and somewhat unpredictable.”

Expert welding
After the piles had been installed, Van den Herik filled them with concrete. De Vries Werkendam then welded the steel beams on top. “The welding had to be carried out with the utmost precision, to execution class 3, because of the bridge that would sit on top and the design requirements. This calls for skilled workmanship. We prepared the structure in our own workshop, in accordance with the applicable welding standard, NEN 1090.” A ground investigation was carried out before the bridge was installed. This was also needed to design the bridge. “The design produces certain specifications for the dimensions of the tubular piles and the supporting structure. We also need that information to determine the forces required to install the foundation.”
Synergy through collaboration
The work on the Julianakanaal was a relatively small job for De Vries Werkendam. “But,” says Jorrit, “it was a job with a tight deadline and quality was paramount. Our collaboration with Van den Herik always works very well. Our specialisms complement each other perfectly, creating excellent synergy.”
Een zakelijke vraag aan De Vries Werkendam? Neem contact op
Wie aan Julianakanaal werkte
- Trimble-dealer
SITECHGenoemd in Efficient excavation on the Julianakanaal thanks to Trimble machine control - maatvoeringPS SurveyGenoemd in Efficient excavation on the Julianakanaal thanks to Trimble machine control
- hoofdaannemerVan den Herik-SliedrechtGenoemd in PS Survey deploys a range of surveying techniques on the Julianakanaal
- grondwerkJac RijkGenoemd in Julianakanaal: A mega-project involving 180 machines, 200 workers and nearly 1.5 million tonnes of earth
- grondverzetpartnerFL BVGenoemd in Complexity of Julianakanaal calls for flexibility and quick decision-making
- grondverzetbedrijvenErmersGenoemd in Complexity of Julianakanaal calls for flexibility and quick decision-making
- grondverzetbedrijvenBC van der VisGenoemd in Complexity of Julianakanaal calls for flexibility and quick decision-making
- projectbeheersing
Count & CooperGenoemd in Project controls demonstrate their value on the Julianakanaal project - opdrachtgeverRijkswaterstaatGenoemd in Project controls demonstrate their value on the Julianakanaal project
- watermanagement
VanderkampGenoemd in The challenge for Van der Kamp: how do you keep the Julianakanaal dry? - grondverzetErmers GrondverzetGenoemd in Working as one team in the northern section of the Julianakanaal
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectJulianakanaal
- OnderwerpFoundations
- BedrijfDe Vries Titan B.V.
- BedrijfDe Vries Werkendam