The challenge for Van der Kamp: how do you keep the Julianakanaal dry?
Text Suzanne van Gaale Image Vanderkamp

Draining it, keeping it dry and filling it again. In a nutshell, that is the water management challenge at the Julianakanaal. At Vanderkamp, The Dutch Water Engineers, they have a solution for every water-related challenge. The Julianakanaal is no exception. In practice, however, it has proved quite a challenge.
“Van den Herik-Sliedrecht asked us whether we could pump out the final 2 metres when draining the Julianakanaal,” says Robert van den Dool, project manager at Vanderkamp. “They handled the first 5 metres themselves by bracing the lock, but that was not possible for the final metres. These last metres also called for additional expertise because of the silt. We drew up a plan to pump the water out from both the lock side and the dam side. At the lock, three temporary pumps, set at different heights, pump water from the canal into the middle lock chamber. The lower the water level, the more turbid the water. To prevent silt from being pumped along with it, we pumped the remaining water through a bypass to the western chamber, where it could then settle.” And it was not just these three pumps. On the dam side, there is also a temporary pumping installation consisting of two interconnected pumps and a flexible hose. The assembly was suspended from a telescopic crane, which lowered it as the water level fell.

Pumps, buffer tanks and containers
Once the Julianakanaal was empty, the challenge was to keep it that way, given the risk of rainwater. To do this, Vanderkamp put together a mobile installation with diesel pumps, buffer tanks and a container, all connected by a 700-metre pipeline. “The difficulty was to set up an installation each time without it getting in the way, given the large number of machines and people working here. After consulting closely with the site managers, we identified the best location.”
2 million m3 of water
The most nerve-racking moment is yet to come: refilling the Julianakanaal. “Over the course of a week in April, we will pump 2 million m3 into the canal using three siphon systems. But it is not so much about the number of m3 as about controlling the water. First, the water had to be pumped out in a controlled manner because of the contaminated silt. In April, we will be able to refill the canal in a controlled manner, preventing damage to the banks and bridges beyond the lock.”
Een zakelijke vraag aan Vanderkamp – The Dutch Water Engineers? Get in touch
Who worked on Julianakanaal
- Trimble dealer
SITECHMentioned in Efficient excavation on the Julianakanaal thanks to Trimble machine control - setting outPS SurveyMentioned in Efficient excavation on the Julianakanaal thanks to Trimble machine control
- main contractorVan den Herik-SliedrechtMentioned in PS Survey deploys a range of surveying techniques on the Julianakanaal
- groundworksJac RijkMentioned in Julianakanaal: A mega-project involving 180 machines, 200 workers and nearly 1.5 million tonnes of earth
- earthworks partnerFL BVMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- earthmoving companiesErmersMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- earthmoving companiesBC van der VisMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- project control
Count & CooperMentioned in Project controls demonstrate their value on the Julianakanaal project - clientRijkswaterstaatMentioned in Project controls demonstrate their value on the Julianakanaal project
- natural stoneRoxx InternationalMentioned in 500,000 tonnes of natural stone used in the Julianakanaal
- earthworksErmers GrondverzetMentioned in Working as one team in the northern section of the Julianakanaal
- earthworks
Van Schaik GrondverzetMentioned in Van Schaik deploys heavy equipment for earthworks on the Julianakanaal
Keep following this
Get an email when a new story is published. No account needed.
- ProjectJulianakanaal
- SubjectWater infrastructure
- CompanyVanderkamp – The Dutch Water Engineers

















