The challenge for Van der Kamp: how do you keep the Julianakanaal dry?

Text Suzanne van Gaale Image Vanderkamp

Toen het Julianakanaal eenmaal leeg was, was het de kunst om deze ook leeg te houden in verband met regenwater.
Toen het Julianakanaal eenmaal leeg was, was het de kunst om deze ook leeg te houden in verband met regenwater.

Draining it, keeping it dry and filling it again. In a nutshell, that is the water management challenge at the Julianakanaal. At Vanderkamp, The Dutch Water Engineers, they have a solution for every water-related challenge. The Julianakanaal is no exception. In practice, however, it has proved quite a challenge.

“Van den Herik-Sliedrecht asked us whether we could pump out the final 2 metres when draining the Julianakanaal,” says Robert van den Dool, project manager at Vanderkamp. “They handled the first 5 metres themselves by bracing the lock, but that was not possible for the final metres. These last metres also called for additional expertise because of the silt. We drew up a plan to pump the water out from both the lock side and the dam side. At the lock, three temporary pumps, set at different heights, pump water from the canal into the middle lock chamber. The lower the water level, the more turbid the water. To prevent silt from being pumped along with it, we pumped the remaining water through a bypass to the western chamber, where it could then settle.” And it was not just these three pumps. On the dam side, there is also a temporary pumping installation consisting of two interconnected pumps and a flexible hose. The assembly was suspended from a telescopic crane, which lowered it as the water level fell.

Robert van den Dool, project manager at Vanderkamp.

Pumps, buffer tanks and containers

Once the Julianakanaal was empty, the challenge was to keep it that way, given the risk of rainwater. To do this, Vanderkamp put together a mobile installation with diesel pumps, buffer tanks and a container, all connected by a 700-metre pipeline. “The difficulty was to set up an installation each time without it getting in the way, given the large number of machines and people working here. After consulting closely with the site managers, we identified the best location.”

2 million m3 of water

The most nerve-racking moment is yet to come: refilling the Julianakanaal. “Over the course of a week in April, we will pump 2 million m3 into the canal using three siphon systems. But it is not so much about the number of m3 as about controlling the water. First, the water had to be pumped out in a controlled manner because of the contaminated silt. In April, we will be able to refill the canal in a controlled manner, preventing damage to the banks and bridges beyond the lock.”     

Een zakelijke vraag aan Vanderkamp – The Dutch Water Engineers? Get in touch

Who worked on Julianakanaal

  1. Trimble dealerSITECHMentioned in Efficient excavation on the Julianakanaal thanks to Trimble machine control
  2. setting outPS SurveyMentioned in Efficient excavation on the Julianakanaal thanks to Trimble machine control
  3. main contractorVan den Herik-SliedrechtMentioned in PS Survey deploys a range of surveying techniques on the Julianakanaal
  4. surveyorsIGLMentioned in PS Survey deploys a range of surveying techniques on the Julianakanaal
  5. earthworks partnerFL BVMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
  6. earthmoving companiesErmersMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
  7. earthmoving companiesBC van der VisMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
  8. project controlCount & CooperMentioned in Project controls demonstrate their value on the Julianakanaal project
  9. clientRijkswaterstaatMentioned in Project controls demonstrate their value on the Julianakanaal project
  10. natural stoneRoxx InternationalMentioned in 500,000 tonnes of natural stone used in the Julianakanaal
  11. water managementVanderkampIn this story
  12. earthworksErmers GrondverzetMentioned in Working as one team in the northern section of the Julianakanaal
  13. earthworksVan Schaik GrondverzetMentioned in Van Schaik deploys heavy equipment for earthworks on the Julianakanaal

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectJulianakanaal
  • SubjectWater infrastructure
  • CompanyVanderkamp – The Dutch Water Engineers
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.