Surveyors are the eyes and ears on site
Text Suzanne van Gaale Image IGL

Is the excavation too deep? Is the rock armour at the right level? To check that the work is being carried out in accordance with the working model, IGL’s surveyors are responsible for setting out in the central and southern sections of the Julianakanaal. They are the eyes and ears of the work planner and machine operators. IGL’s Richard Roufs, Project Manager, explains how they work.
“The two of us are responsible for setting out every day,” Richard explains. “We work on site along the Julianakanaal, checking the work. Every machine is equipped with GPS machine control, so the operator knows exactly how deep and how far to excavate, and how much material to place. Our surveyor also has this 3D design model. He walks around with a GPS receiver, using it to determine the x, y and z coordinates and carry out a survey for checking purposes.” IGL is a surveying and hydrographic engineering consultancy with three offices: in Nieuwegein, Herten and Vlissingen. Its experts are ‘masters of measurement’, working across a range of disciplines, including geodesy, hydrography and technical surveying. For example, they provide setting-out services for housing, commercial construction and roadbuilding projects. They also carry out drone surveys. Their projects and clients are varied, from ProRail, Kadaster and Rijkswaterstaat to local authorities, contractors and construction companies.

In accordance with the working model
The widening of the Julianakanaal consists of four phases: excavation, installation of the bentonite mats, placement of gravel and installation of rock armour. In each phase, IGL’s surveyors check that the work is carried out in accordance with the working model. If the operator encounters something unexpected during the work, such as waste or rubble, IGL’s surveyor measures it immediately and reports it to the work planner, who can then take action.
Eyes and ears
IGL’s surveyors are also the eyes and ears on site. “Our surveyors are the link between the office and the site, and work as part of a team with the machine operators and the site manager. Communication is very important. It leads to excellent cooperation, which helps the work progress smoothly.”
Safety rules
Safety is a key issue. In addition to standard requirements such as a VCA certificate and personal protective equipment, our surveyors have also completed a mandatory e-learning safety course covering the site rules. Safety is also on the agenda every week. We discuss progress and any potential safety issues together.
Playing our part
The setting-out work itself is no different from that on many other projects. What makes the Julianakanaal different for Richard and his team, however, is the time pressure and scale. “It takes a great deal of logistical coordination to ensure all the work is properly aligned and there are no delays. That is quite an art. The Julianakanaal is just around the corner from our office in Herten. It’s great to be able to play our part in this wonderful project on our own Limburg soil.”
Question about this story? Ask your question
Who worked on Julianakanaal
- Trimble dealer
SITECHMentioned in Efficient excavation on the Julianakanaal thanks to Trimble machine control - setting outPS SurveyMentioned in Efficient excavation on the Julianakanaal thanks to Trimble machine control
- main contractorVan den Herik-SliedrechtMentioned in PS Survey deploys a range of surveying techniques on the Julianakanaal
- groundworksJac RijkMentioned in Julianakanaal: A mega-project involving 180 machines, 200 workers and nearly 1.5 million tonnes of earth
- earthworks partnerFL BVMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- earthmoving companiesErmersMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- earthmoving companiesBC van der VisMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- project control
Count & CooperMentioned in Project controls demonstrate their value on the Julianakanaal project - clientRijkswaterstaatMentioned in Project controls demonstrate their value on the Julianakanaal project
- natural stoneRoxx InternationalMentioned in 500,000 tonnes of natural stone used in the Julianakanaal
- water management
VanderkampMentioned in The challenge for Van der Kamp: how do you keep the Julianakanaal dry? - earthworksErmers GrondverzetMentioned in Working as one team in the northern section of the Julianakanaal
- earthworks
Van Schaik GrondverzetMentioned in Van Schaik deploys heavy equipment for earthworks on the Julianakanaal
Keep following this
Get an email when a new story is published. No account needed.
- ProjectJulianakanaal
- ThemeDigitalisation from design to construction
- SubjectSurveying & geo-ICT