Efficient excavation on the Julianakanaal thanks to Trimble machine control
Text Suzanne van Gaale Beeld Paul van Baardwijk/SITECH

Almost all the machines used to excavate and place the riprap in the Julianakanaal are equipped with Trimble Earthworks machine control. Thanks to the system’s high accuracy, operators can see exactly what they are doing, and what they need to do. Niels Timmermans, product specialist at SITECH, explains how Trimble machine control contributes to an efficient excavation process on the canal.
Most companies know SITECH as the Trimble dealer for machine control. The company supplies GPS systems, survey kits, software and associated cloud solutions. It has done the same for the widening of the Julianakanaal, equipping the machines, from excavators to bulldozers, with Trimble machine control. Niels says: “Trimble machine control systems help contractors complete work faster, with less rework, setting out and dimensional checks. For the widening of the Julianakanaal, we are doing this in collaboration with PS Survey, one of our clients, which is responsible for the project’s surveying. They produced the designs for the machine control. The question, though, was how to set all this up. We drew up a plan. This is also where our services and products really come into their own: by thinking ahead about machine control so the process can be organised as efficiently as possible.”

Three base stations
Around 60 GPS-equipped machines are working on the widening of the Julianakanaal. Of these, 55 are fitted with Trimble machine control. According to Niels, few projects currently have so many machines working at the same time. “When it comes to machine control, you set a number of priorities to ensure the project runs as efficiently as possible. Accuracy was particularly important when raising the level of the Julianakanaal. We therefore decided to use three base stations. Work on the Julianakanaal is also divided into three work areas, each with its own base station. The advantage is that data continuity is always guaranteed. If one base station were to fail, we could always fall back on another.”

Up-to-date work information at all times
A second key requirement was data transfer to and from the machines. Trimble uses the Worksmanager cloud environment, which allows main contractors to form so-called partnerships with the subcontractors supplying the machines. “This meant that all the machines were already connected to one another in the cloud via Worksmanager before they were deployed on the project. So on day one, operators could get straight to work with the latest 3D excavation model. Our helpdesk normally gets a lot of calls on the first day, as operators get used to the system, but this time it was very quiet. There was no downtime or delay, saving a lot of time and money. Another advantage of Trimble Worksmanager is that a design is updated immediately if changes are made. The operator is notified straight away. This also makes the risk of errors caused by working with an outdated design very low.”
“The Julianakanaal is a flagship project for us because we were able to contribute our ideas from the outset. Operators can get straight to work every morning, without any hassle or downtime, making the work more efficient, better and, above all, more enjoyable.”
Have a business enquiry for SITECH Nederland BV? Get in touch
Who worked on Julianakanaal
- setting outPS SurveyIn this story
- main contractorVan den Herik-SliedrechtMentioned in PS Survey deploys a range of surveying techniques on the Julianakanaal
- groundworksJac RijkMentioned in Julianakanaal: A mega-project involving 180 machines, 200 workers and nearly 1.5 million tonnes of earth
- earthworks partnerFL BVMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- earthmoving companiesErmersMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- earthmoving companiesBC van der VisMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- project control
Count & CooperMentioned in Project controls demonstrate their value on the Julianakanaal project - clientRijkswaterstaatMentioned in Project controls demonstrate their value on the Julianakanaal project
- natural stoneRoxx InternationalMentioned in 500,000 tonnes of natural stone used in the Julianakanaal
- water management
VanderkampMentioned in The challenge for Van der Kamp: how do you keep the Julianakanaal dry? - earthworksErmers GrondverzetMentioned in Working as one team in the northern section of the Julianakanaal
- earthworks
Van Schaik GrondverzetMentioned in Van Schaik deploys heavy equipment for earthworks on the Julianakanaal
Keep following this
Get an email when a new story is published. No account needed.
- ProjectJulianakanaal
- ThemeDigitalisation from design to construction
- SubjectMachines & equipment
- CompanySITECH Nederland BV
- CompanyPS Survey