PS Survey deploys a range of surveying techniques on the Julianakanaal
Text Suzanne van Gaale Images PS Survey

For the widening of the Julianakanaal, Rijkswaterstaat and main contractor Van den Herik-Sliedrecht are setting high standards for quality and speed. Every activity, from excavating the existing bed to placing the rock, is measured and checked in detail. A range of surveying techniques is used, including RTK-GPS, total station surveys, 3D laser scanning and drone surveys. Surveying company PS-Survey is primarily responsible for the measurements and has drawn up the project-specific setting-out plan.
“Our work essentially involves monitoring the earthworks and carrying out geometric checks on the bed protection,” explains Peter Strigencz, manager at PS-Survey. “We survey the Julianakanaal four times: after excavation, once the bentonite mats have been installed, once the gravel filter layer is in place, and finally after the rock armour has been placed.”

Skilled professionals
PS-Survey is responsible for all setting-out work on the project and is the point of contact for all surveyors and setting-out engineers. For the site work, it works with surveyors from IGL and Van den Herik. This draws on expertise built up over the past 27 years, including on numerous extraction projects. “We know the sand and gravel extraction sector well. On projects like this, we provide a complete surveying service because we have the expertise, a wide range of techniques and skilled professionals in-house. That combination sets us apart. For example, we handle all the setting-out and earthworks calculations for the Grensmaas project.”

The surveying process
The surveys on the Julianakanaal are used to guide, check and record the successive layers of bed protection. “It starts with checking the positioning of the machines and supplying the machine models in the correct format,” Peter explains. “Once everything is working correctly, the operator can get to work. We measure the thickness of the various layers as work progresses. Once a particular layer is complete, our surveyor carries out an initial check using RTK-GPS. If we find a deviation, we report it straight away to the site manager responsible and the machine operator so it can be corrected. We then carry out a second check, recording the various layers in a full-coverage survey using 3D laser scanning.” The data is processed into elevation and difference maps showing deviations from the design, enabling inspections to be carried out. PS-Survey also conducts drone surveys of the work zone and stockpiles. “This allows us, among other things, to calculate how much material is in each stockpile and whether there will be enough for the planned work.”

Precision
As the work covers a considerable area, 4 kilometres in length, and the required accuracy is very high, three GPS base stations have been installed across the site. All machines on the project that use GPS positioning rely on these stations. “This eliminates discrepancies between the different national networks. The system was set up in collaboration with our supplier Sitech Nederland and has proved to be a robust, but also essential, solution.”
3D and multibeam
For the Julianakanaal, the decision was made to carry out as many surveys as possible using a 3D laser scanner, for speed and safety. “We want to minimise the amount of surveying carried out among moving machinery. That’s why we use quad bikes fitted with a long-range 3D laser scanner,” Peter explains. In sections of the Julianakanaal where water remains, PS-Survey has carried out depth soundings using multibeam sonar. “We carried out underwater surveys to check the watertightness of the temporary dam. We will also use this survey method while the Julianakanaal is being filled and afterwards, so we can map any changes to the bed.”
Challenges
The extensive surveying generates a large volume of data. “That’s quite a challenge,” Peter explains. “The point clouds produced by the 3D scans in particular are huge files. Consistent naming, clear storage structures and several terabytes of storage are essential.” Updates to the machine models also require attention. They need to be uploaded as quickly as possible to machines equipped with positioning systems. For most machines, these updates are made through a web application. The remaining machines are updated by a surveyor visiting the site.
Collaboration
Peter has high praise for the collaboration with Van den Herik. “We have worked together before, including on projects abroad, and the relationship has always been excellent. Every week, we hold a surveying meeting to review the entire measurement process and the drawings to be prepared, and make adjustments where necessary. At first, the process involved a lot of intensive fine-tuning, but over time it has evolved into mainly reviewing the week’s work and confirming that everything is running smoothly.”
Question about this story? Ask your question
Who worked on Julianakanaal
- Trimble dealer
SITECHMentioned in Efficient excavation on the Julianakanaal thanks to Trimble machine control - setting outPS SurveyMentioned in Efficient excavation on the Julianakanaal thanks to Trimble machine control
- main contractorVan den Herik-SliedrechtIn this story
- surveyorsIGLIn this story
- groundworksJac RijkMentioned in Julianakanaal: A mega-project involving 180 machines, 200 workers and nearly 1.5 million tonnes of earth
- earthworks partnerFL BVMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- earthmoving companiesErmersMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- earthmoving companiesBC van der VisMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- project control
Count & CooperMentioned in Project controls demonstrate their value on the Julianakanaal project - clientRijkswaterstaatMentioned in Project controls demonstrate their value on the Julianakanaal project
- natural stoneRoxx InternationalMentioned in 500,000 tonnes of natural stone used in the Julianakanaal
- water management
VanderkampMentioned in The challenge for Van der Kamp: how do you keep the Julianakanaal dry? - earthworksErmers GrondverzetMentioned in Working as one team in the northern section of the Julianakanaal
- earthworks
Van Schaik GrondverzetMentioned in Van Schaik deploys heavy equipment for earthworks on the Julianakanaal
Keep following this
Get an email when a new story is published. No account needed.
- ProjectJulianakanaal
- ThemeDigitalisation from design to construction
- SubjectSurveying & geo-ICT
- CompanyVan den Herik-Sliedrecht
- CompanyIGL
- CompanySITECH Nederland BV