Complexity of Julianakanaal calls for flexibility and quick decision-making
Text Suzanne van Gaale Image FL BV

They call themselves the pioneers of civil engineering and see soil as the foundation for creating something beautiful. The same applies to Julianakanaal. The FL BV team, part of Reyrink Groep, was asked by Van den Herik-Sliedrecht to contribute ideas and work as a partner on the delivery of work section Noord. It is a challenging job, and flexibility is essential, according to project manager Pieter Quekel.
‘Could you help us work out how we can organise the work together in section Noord of Julianakanaal?’ This was the question Van den Herik put to FL BV a year ago. “We know each other well,” says Pieter. “We have worked as a earthworks partner for Van den Herik for some time. We are jointly involved in a partnership called Dijkgenoten, delivering dike reinforcement projects, and we also worked on Maximakanaal near Den Bosch. As for section Noord of Julianakanaal, it is fair to say that this is a large and complex stretch of the canal. When we were approached in April last year, little was yet known about the ground conditions. The ground investigations were still in full swing, even though we already had to draw up a work plan. This type of project would normally have a year of preparation, but we had only around four months for this job.”

Refining and adjusting the plan
FL BV drew up a plan for section Noord together with Van den Herik. “That gave us our basic approach. The earthmoving contractors Ermers and BC van der Vis later joined us to support the extensive deployment of plant and the delivery of the work. As the work progressed, we received new information and gained new insights. We were constantly refining and adjusting the plan.” One example was the volume of silt that had to be removed. Ground investigations had established the quantity, but in practice it turned out to be more than expected. “Having to move such a huge volume of silt in a relatively short time certainly made things challenging. It meant we had to be very flexible with the schedule and scale up quickly when needed.”

Bentonite mats laid using a telehandler
Another good example of a new insight was the method used to roll out the bentonite mats. These mats, approximately 2 centimetres thick, create a watertight layer on the canal bed. “To make Julianakanaal watertight, we rolled out approximately 180.000 m2 of bentonite mat in section Noord. The plan was to use an excavator positioned on top of the dike to pull the rolls up. However, there was not enough room to manoeuvre on the dike, so we reversed the method. A telehandler on the bed of Julianakanaal unrolled the mats from the bottom upwards. We spent several weeks working on this.”
Pieter is very positive about the collaboration. “It is a large team made up of many parties, each with different insights. The collaboration is also very intensive, given the short delivery period. We work closely together with one important initial goal in mind: reopening Julianakanaal to shipping.”
Question about this story? Ask your question
Who worked on Julianakanaal
- Trimble dealer
SITECHMentioned in Efficient excavation on the Julianakanaal thanks to Trimble machine control - setting outPS SurveyMentioned in Efficient excavation on the Julianakanaal thanks to Trimble machine control
- main contractorVan den Herik-SliedrechtMentioned in PS Survey deploys a range of surveying techniques on the Julianakanaal
- groundworksJac RijkMentioned in Julianakanaal: A mega-project involving 180 machines, 200 workers and nearly 1.5 million tonnes of earth
- earthworks partnerFL BVIn this story
- earthmoving companiesErmersIn this story
- earthmoving companiesBC van der VisIn this story
- project control
Count & CooperMentioned in Project controls demonstrate their value on the Julianakanaal project - clientRijkswaterstaatMentioned in Project controls demonstrate their value on the Julianakanaal project
- natural stoneRoxx InternationalMentioned in 500,000 tonnes of natural stone used in the Julianakanaal
- water management
VanderkampMentioned in The challenge for Van der Kamp: how do you keep the Julianakanaal dry? - earthworksErmers GrondverzetMentioned in Working as one team in the northern section of the Julianakanaal
- earthworks
Van Schaik GrondverzetMentioned in Van Schaik deploys heavy equipment for earthworks on the Julianakanaal
Keep following this
Get an email when a new story is published. No account needed.
- ProjectJulianakanaal
- SubjectWater infrastructure
- CompanyFL BV
- CompanyErmers
- CompanyBC van der Vis
















