Van Schaik deploys heavy equipment for earthworks on the Julianakanaal
Text Suzanne van Gaale Beeld Van Schaik Grondverzet

Ships are due to sail through the Julianakanaal again in April 2025. To make this possible, earthworks specialists and machinery have been brought to Limburg from across the Netherlands. One of the companies involved is Van Schaik from Harmelen. It worked on the earthworks in section Zuid.
“We’re helping to write a piece of history,” says Peter van Schaik, director of Van Schaik, of the widening of the Julianakanaal. “We’re very likely to see a canal being drained just once in our lifetime. It’s a fantastic project, and we’re proud to be involved.” Peter is the second generation of the Van Schaik family to run the business. His father founded it 55 years ago. Today, the company specialises in earthworks in the broadest sense. It has a large fleet of machinery and employs skilled staff in-house, from work planners to GPS specialists.

30-tonne crawler crane
Van den Herik subcontracted work section Zuid to Boskalis. Boskalis, in turn, brought in Van Schaik to roll out the bentonite mats. Van Schaik deployed its largest machine for the job, a 30-tonne crawler crane with a 14-metre boom. “For ten weeks, we used this crane to roll out the bentonite mats on the canal bed. We laid around 13,000 m2 a week, rising to as much as 15,000 m2 at the peak of the work. These are huge quantities. We then placed the gravel and armourstone. One of our operators, a man with experience and knowledge of this kind of work, is at the controls. We use GPS machine control so you can see where you’re working. Bringing the gravel up to the required level is particularly challenging. It’s precision work and calls for great accuracy and care from the operator.”
Teamwork
“We’re working here with several parties as one team to get the job done together. When you see all the machines and people at work on the Julianakanaal bed, it’s one big, well-oiled machine.”
Een zakelijke vraag aan Van Schaik Grondverzet B.V.? Get in touch
Who worked on Julianakanaal
- Trimble dealer
SITECHMentioned in Efficient excavation on the Julianakanaal thanks to Trimble machine control - setting outPS SurveyMentioned in Efficient excavation on the Julianakanaal thanks to Trimble machine control
- main contractorVan den Herik-SliedrechtMentioned in PS Survey deploys a range of surveying techniques on the Julianakanaal
- groundworksJac RijkMentioned in Julianakanaal: A mega-project involving 180 machines, 200 workers and nearly 1.5 million tonnes of earth
- earthworks partnerFL BVMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- earthmoving companiesErmersMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- earthmoving companiesBC van der VisMentioned in Complexity of Julianakanaal calls for flexibility and quick decision-making
- project control
Count & CooperMentioned in Project controls demonstrate their value on the Julianakanaal project - clientRijkswaterstaatMentioned in Project controls demonstrate their value on the Julianakanaal project
- natural stoneRoxx InternationalMentioned in 500,000 tonnes of natural stone used in the Julianakanaal
- water management
VanderkampMentioned in The challenge for Van der Kamp: how do you keep the Julianakanaal dry? - earthworksErmers GrondverzetMentioned in Working as one team in the northern section of the Julianakanaal
Keep following this
Get an email when a new story is published. No account needed.
- ProjectJulianakanaal
- ThemeConstruction equipment and transport in motion
- SubjectWater infrastructure
- CompanyVan Schaik Grondverzet B.V.