Dust-free pile cropping on the Blankenburg Connection

On the Blankenburg Connection, Blijleven Koppensnellers once again demonstrates that pile cropping really is a specialist skill.
With a brand-new crane and a pile cropper equipped with dust suppression, the family business cropped 580 foundation piles in phases on one of the largest infrastructure projects in the Netherlands. The work was fully integrated into the schedule set by client BAAK, with the crane balancing on trestles and mats 150 centimetres above the working floor. Just before this issue of GWW went to press, Blijleven Koppensnellers secured a follow-on contract to crop an additional 3,600 piles.


Pile cropping has traditionally been heavy, labour-intensive work, but Blijleven Koppensnellers has turned it into a real art. “The sawing is now done mechanically, the piles are cropped hydraulically with dust suppression, and the rubble is scooped up with a small crane,” explains John Blijleven. “So pile cropping no longer causes dust nuisance. We are the first company in the Netherlands to have developed our own dust suppression system, fitted to all 40 of our pile croppers. Unfortunately, not every contractor makes dust prevention a priority, even though it is mandatory. Fortunately, BAAK appreciates its importance.”


Blijleven Koppensnellers was mainly involved in pile cropping on the Blankenburg Connection for the approach to the Hollandtunnel. “We cropped the square vk450 precast piles, with eight or twelve reinforcing bars of around 25 millimetres, to a depth of 1 to 2 metres, working from a flexible position on trestles and mats. We followed the contractor’s schedule. In this case, BAAK could not excavate everything at once, as that would have caused the ground to burst open. The excavation was therefore carried out in phases, as was the pile cropping. The crane never left the pit. That is our strength: as a company, we are very flexible. All in all, it was a successful project. Working with infrastructure contractors is always a pleasure.” And the feeling is mutual, as the innovative family business has also been awarded work to crop a further 3,045 piles of the same vk450 type on the other side of the Hollandtunnel, as well as another 625 piles of the same type at the approach to the Maasdeltatunnel.
Question about this story? Ask your question
Who worked on Blankenburgverbinding
- construction consortiumBAAKMentioned in Unique and remarkable: 800-metre-long floating reed bed in the Krabbeplas near Vlaardingen
- crane matsKo-MatsMentioned in German engineering in dragline mats for the Blankenburg Connection project
- designTunnel Engineering Consultants (TEC)Mentioned in Environmental and community interests at the heart of a unique technical concept
- ondersteunings- en horizontale bekistingsconstructiesMADEMA Steigerwerken BVMentioned in Temporary support structures for in-situ decks
- supplier of the scaffolding systemMatemco Hulpconstructies BVMentioned in Temporary support structures for in-situ decks
- geïntegreerde video-, audio- en communicatiesystemenHacousto ProtecMentioned in The link to the traffic control centre
- Breaking down foundation pile headsBlijleven KoppensnellersIn this story
- waterproofingPolyproofMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- waterproofing injectionsSpecial Industrial Repair (SIR)Mentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- supplier of waterproof coatingsAdcosMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- edge elementsTakke BreukelenMentioned in Architectural edge elements in composite and stainless steel
Keep following this
Get an email when a new story is published. No account needed.
- ProjectBlankenburgverbinding
- SubjectSpecials
- CompanyBlijleven Koppensnellers