A wave of divers at the Blankenburg connection

From 2024, the new A24 Blankenburg connection will link the A20 near Vlaardingen with the A15 near Rozenburg. Part of the new motorway lies below ground level, and most of it was built underwater. For DISA International, this was a mammoth task, much of it at considerable depth below the waterline. At peak times, the specialist in pioneering underwater solutions supported the BAAK contractor consortium with no fewer than 180 (!) divers. Didier de Graaff, Managing Director of DISA International, and Marc Dröge, General Manager of DISA International, look back on a remarkable and intensive project.
To ensure the underwater structures could be tackled as efficiently as possible, BAAK was in close contact with DISA International during the preparatory phase. “The Blankenburg connection is a project of huge numbers,” says Dröge. Here are just a few. By early February 2022, we had clocked up no fewer than 261,822 man-hours on the project, including cleaning 10,111 m2 of sheet piling, cleaning and extending 11,452 anchors, a further 500 Leka and VC piles, installing 24,825 linear metres of bearing beams and placing 25,000 tonnes of reinforcement. Finally, we assisted with the pouring of more than 100,000 m3 of underwater concrete.”

Nitrox instead of compressed air
According to Dröge, aside from the sheer volumes involved, the main challenge was the depth, reaching as much as 32 metres below the waterline. “At that depth, dive times are limited. We came up with all kinds of clever solutions to work efficiently, such as using different gas mixtures for diving (nitrox instead of compressed air) and surface decompression, which enabled our divers to stay underwater for longer. We also developed a system ourselves to extend the GEWI anchors quickly. By using a lifting beam that could hold eight anchors at a time, we avoided wasting valuable time underwater. We also designed a practical clamp for installing the bearing beams. In addition, during the preparatory phase we worked closely with BAAK on practical details, for example designing the piles to be extended and the reinforcement mats to be as diver-friendly as possible, so divers had to perform as few tasks as possible. That certainly paid off in practice.”

Millions invested
At peak times, DISA International was working around the clock, six days a week. To provide that capacity without letting down other clients and projects, we contacted our partners abroad. Millions were also invested in equipment. “We experienced some tense moments, right in the middle of the Covid-19 pandemic,” Dröge admits. “Borders were closing and the Netherlands was turning deep red on the Covid map. Just try getting the right people and equipment to the site on time. We scoured the world for equipment, and BAAK gave us enormous support with coordination, enabling the foreign divers to be deployed quickly and efficiently, without too many problems.” Dröge also praises BAAK’s approach during the pandemic. “As a result of the stricter hygiene measures, all equipment had to be disinfected after every dive, in addition to the usual procedures and in accordance with a new, special protocol. That was quite a challenge given the tight schedule. BAAK and we handled it very professionally, and the discipline of our people meant we kept things well under control right through to the end.”

DISA International looks back with pride on a project that went very well and achieved a very high safety score. “We do not compromise on safety,” Dröge says firmly. For DISA, however, the mammoth task is not quite finished. “At the end of this year, we will burn off the steelwork in the approaches to the Maasdeltatunnel at a depth of 32 metres, and next year we will provide the necessary assistance with sinking the tunnel sections.”
Have a business enquiry for DISA International? Get in touch
Who worked on Blankenburgverbinding
- construction consortiumBAAKMentioned in Unique and remarkable: 800-metre-long floating reed bed in the Krabbeplas near Vlaardingen
- crane matsKo-MatsMentioned in German engineering in dragline mats for the Blankenburg Connection project
- designTunnel Engineering Consultants (TEC)Mentioned in Environmental and community interests at the heart of a unique technical concept
- ondersteunings- en horizontale bekistingsconstructiesMADEMA Steigerwerken BVMentioned in Temporary support structures for in-situ decks
- supplier of the scaffolding systemMatemco Hulpconstructies BVMentioned in Temporary support structures for in-situ decks
- geïntegreerde video-, audio- en communicatiesystemenHacousto ProtecMentioned in The link to the traffic control centre
- Breaking down foundation pile headsBlijleven KoppensnellersMentioned in Dust-free pile cropping on the Blankenburg Connection
- waterproofingPolyproofMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- waterproofing injectionsSpecial Industrial Repair (SIR)Mentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- supplier of waterproof coatingsAdcosMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- edge elementsTakke BreukelenMentioned in Architectural edge elements in composite and stainless steel
Keep following this
Get an email when a new story is published. No account needed.
- ProjectBlankenburgverbinding
- SubjectNews
- CompanyDISA International























