Carefully planned concrete deliveries keep environmental impact score low

BAAK engaged Mebin during the tender phase to help plan concrete deliveries for the Blankenburgverbinding. The use of two mobile batching plants at the project site, which has access to deep water, and three permanent back-up plants nearby helps keep the environmental impact score (MKI value) as low as possible.
The first discussions with BAAK took place as early as 2016, recalls Bas Pije, Commercial Manager at Mebin. “After the contract was awarded, we went into more detail and spent around a year and a half on all the preparations. We reached a final agreement at the end of November 2019. Before then, we had already supplied some ready-mixed concrete for the project, including for casting various working platforms. But that was only a fraction of the volume in our main contract: supplying 350,000 m3 of ready-mixed concrete over a five-year period, with the peak in 2021 and 2022.”
Short delivery routes
To minimise disruption to the surrounding area, it was decided to set up a mobile batching plant on the project site on both the north and south sides of the Scheur. Pije says: “On the northern side, we selected a suitable site on the project together with BAAK, right next to the construction pit. On the southern side, a mobile plant is being set up on our own site at ENCI. We will also use our permanent plants in Maassluis and Spaanse Polder, both on the northern side, and Europoort on the southern side. The main challenge is the short time frame in which we have to supply a large volume of ready-mixed concrete. The mobile plants keep transport distances short and will prevent disruption to the surrounding area.” Walter Speelman, Marketing and Product Manager at Mebin, adds: “Delivering raw materials will not involve any traffic on public roads either. The mobile plant sites are located on a deep-water quay, allowing us to use large vessels that can each unload 2,000 tonnes of raw materials in a single delivery.”
The permanent plants will only be brought in to help during peak periods, to ensure continuity or cover any downtime, Pije explains. “A continuous pour can sometimes last three days without a break. That takes a great deal of preparation and coordination beforehand.” Speelman adds: “We have therefore stationed a dedicated concrete planner on site to coordinate operations and ensure quality, even when outside temperatures fluctuate. We are dealing with a wide range of concrete grades and mix designs, from standard strength class 30/37 to high-strength concrete C75.”
Question about this story? Ask your question
Who worked on Blankenburgverbinding
- construction consortiumBAAKMentioned in Unique and remarkable: 800-metre-long floating reed bed in the Krabbeplas near Vlaardingen
- crane matsKo-MatsMentioned in German engineering in dragline mats for the Blankenburg Connection project
- designTunnel Engineering Consultants (TEC)Mentioned in Environmental and community interests at the heart of a unique technical concept
- ondersteunings- en horizontale bekistingsconstructiesMADEMA Steigerwerken BVMentioned in Temporary support structures for in-situ decks
- supplier of the scaffolding systemMatemco Hulpconstructies BVMentioned in Temporary support structures for in-situ decks
- geïntegreerde video-, audio- en communicatiesystemenHacousto ProtecMentioned in The link to the traffic control centre
- Breaking down foundation pile headsBlijleven KoppensnellersMentioned in Dust-free pile cropping on the Blankenburg Connection
- waterproofingPolyproofMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- waterproofing injectionsSpecial Industrial Repair (SIR)Mentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- supplier of waterproof coatingsAdcosMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- edge elementsTakke BreukelenMentioned in Architectural edge elements in composite and stainless steel
Keep following this
Get an email when a new story is published. No account needed.
- ProjectBlankenburgverbinding
- ThemeMaterials and techniques for infrastructure
- SubjectBridge construction