Bridge construction

Six temporary bridges improve access to construction site

Retro Bridge hanteert diverse varianten van het modulaire brugconcept.
Retro Bridge hanteert diverse varianten van het modulaire brugconcept.

To improve access to the vast A24 Blankenburg Connection construction site, construction consortium BAAK is using six temporary bridges supplied by Retro Bridge. The temporary bridge specialist has more than 15,000 tonnes of bridge components in its fleet, enabling it to respond at relatively short notice. According to Han Kastermans, managing director of Retro Bridge, only a few months elapsed between the order and installation.

Retro Bridge offers several variants of its modular bridge concept.

The initial request was for four temporary bridges: one over Droespolderweg (RLB bridge), one over Maassluissedijk (RLB bridge) and two over Kistdam, one RLB and one RBB bridge. “As the bridges will be in use for more than about three years, BAAK opted to buy them, with the option for us to buy them back if they are used normally. That works out cheaper,” says Kastermans. “At a later stage, we also supplied two bridges for hire: an RBB bridge over a tunnel section and an RFB pedestrian bridge at the Hollandtunnel.”

Modular bridge concept

The main advantage of Retro Bridge’s temporary bridges is that they are easy to assemble on site. “We fully prepare the bridge spans in our workshop, up to a maximum length of 40.5 metres, then use a crane to lift them into position on site and connect them,” Kastermans explains. “We spent no more than three-quarters of a day assembling each bridge.” The longest bridge on the Blankenburg Connection is the 37.5-metre RLB bridge over Kistdam. That was not its original length, however. “We initially supplied the bridge in 24-metre spans. As construction progressed, the excavation grew, requiring a longer span. So we extended the bridge with 13.5-metre elements. That is no problem at all with our modular concept.”

BIM model

Retro Bridge offers several variants of its modular bridge concept. “Our standard range of RLB and RBB bridges can span 37.5 metres, in accordance with the maximum mobile load specified in the Eurocode,” says Kastermans. “The RFB pedestrian bridge can achieve a clear span of up to 57 metres. We usually draw on our extensive stock, but because we also had to supply the Groene Boog and Linkeroever in Antwerp at the same time as the Blankenburg Connection, we built four new bridge spans. Construction consortium BAAK had its plans well organised. The BIM model let us check the exact positions of our bridges in advance, along with the required specifications. That was truly impressive. As a result, we had a clear picture of what the temporary bridges needed to meet.”     

Een zakelijke vraag aan Retro Bridge Nederland? Get in touch

Who worked on Blankenburgverbinding

  1. construction consortiumBAAKMentioned in Unique and remarkable: 800-metre-long floating reed bed in the Krabbeplas near Vlaardingen
  2. crane matsKo-MatsMentioned in German engineering in dragline mats for the Blankenburg Connection project
  3. road construction companyBallastMentioned in Proud partner brings its (in-house) strengths together
  4. foundation specialistDe Vries TitanMentioned in Strong partnership delivers huge piling operation
  5. temporary support structureCiviele technieken deBoerMentioned in Jacking, sliding and pressing
  6. precast beamsHaitsma BetonMentioned in Precast concrete for the new A24
  7. prestressing systemsDYWIDAG-Systems InternationalMentioned in Smart thinking in prestressing design
  8. designTunnel Engineering Consultants (TEC)Mentioned in Environmental and community interests at the heart of a unique technical concept
  9. ondersteunings- en horizontale bekistingsconstructiesMADEMA Steigerwerken BVMentioned in Temporary support structures for in-situ decks
  10. temporary supportCT deBoerMentioned in Temporary support structures for in-situ decks
  11. supplier of the scaffolding systemMatemco Hulpconstructies BVMentioned in Temporary support structures for in-situ decks
  12. Steel-reinforced elastomeric bearingsKonstrukomMentioned in Reinforced elastomeric bearings
  13. dewatering worksHenk van Tongeren Water & TechniekMentioned in Dewatering operation
  14. civil underwater structuresDISA InternationalMentioned in A hive of activity underwater
  15. geïntegreerde video-, audio- en communicatiesystemenHacousto ProtecMentioned in The link to the traffic control centre
  16. supplierJdB groepMentioned in Reusing and upgrading soil products
  17. consultancy firmStrypesMentioned in Making a difference
  18. sealing specialistViltonMentioned in Sealing expert prevents ‘water ingress’
  19. industrial automation specialistICT GroupMentioned in Control software for tunnel systems
  20. Breaking down foundation pile headsBlijleven KoppensnellersMentioned in Dust-free pile cropping on the Blankenburg Connection
  21. excavationVerboon MaaslandMentioned in Preparing complex construction pits for construction
  22. waterproofingPolyproofMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
  23. waterproofing injectionsSpecial Industrial Repair (SIR)Mentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
  24. supplier of waterproof coatingsAdcosMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
  25. wall formworkPERIMentioned in Save time and money with an advanced formwork system
  26. temporary bridgesRetro BridgeIn this story
  27. edge elementsTakke BreukelenMentioned in Architectural edge elements in composite and stainless steel
  28. precast concrete structuresVan Dijk BetonMentioned in Versatile in precast concrete structures
  29. designRijkswaterstaatMentioned in Versatile in precast concrete structures
  30. pylon claddingGlasGroenMentioned in A touch of nostalgia on the Blankenburgverbinding

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectBlankenburgverbinding
  • ThemeExtending the life of roads and civil engineering structures
  • SubjectBridge construction
  • CompanyRetro Bridge Nederland
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.