News

A24 Blankenburgverbinding: Urgent job for waterproofing specialist

Polyurea is een hot spray coating, die vanuit een speciaal ingerichte mobiele unit, op een bijna kunstzinnige maar uiterst professionele wijze wordt aangebracht.
Polyurea is een hot spray coating, die vanuit een speciaal ingerichte mobiele unit, op een bijna kunstzinnige maar uiterst professionele wijze wordt aangebracht.

On the A24 Blankenburgverbinding, construction consortium BAAK is working at full speed on the Hollandtunnel and the approaches to the Maasdeltatunnel, 33 metres below ground. When the original applicator encountered supply problems, the consortium had to find an alternative at very short notice. The solution came from Special Industrial Repair (SIR), and in particular its sister company Polyproof.

The embankment takes shape. Beneath the earthworks lies the first 1,700 m2 of Polyurea.

“We initially approached three applicators to waterproof around 7,000 m2 of tunnel deck,” says Michael Dekker, project coordinator at BAAK. “The contract was awarded to a company that ultimately could not deliver, right at the last minute. Its supplier was unable to provide the materials. To avoid disrupting the programme, we had to find an alternative urgently. Adcos, a supplier of waterproof coatings, put us in touch with SIR and, ultimately, Polyproof. BAAK already knew SIR as a subcontractor for waterproof injection work. Polyproof then moved quickly and decisively. The end product is considerably more expensive, but also of higher quality.”

Thanks to its exceptional chemical properties, Polyurea is highly reactive, making it an extremely fast-curing spray with excellent adhesion to metal, concrete and foam.

Olympic medal-winning performance 

According to managing director Hans Bos, Polyproof recently delivered an Olympic-sized performance on the Blankenburgverbinding. “We were asked to waterproof the tunnel deck with Polyurea just two weeks before a huge sand embankment was due to be built over the approach to the immersed tunnel. It is a hot-spray coating, applied from a specially equipped mobile unit in an almost artistic yet highly professional manner. Getting the work underway quickly was important to the project’s progress. Given the considerable area of 1,700 m2 and the well-known supply delays caused by difficulties sourcing raw materials, it was quite a challenge. At times like these, you realise how important it is to have a network of genuine partners. Our supplier Adcos gave us tremendous support by rearranging its schedule and producing exclusively for us. That meant we were able to respond quickly.” 

Reactor metering pump

Polyproof received the order on Thursday, and a team of professionals was already on the tunnel deck exactly one week later. “A huge amount of work was done in the meantime too,” says Rens Olij, technical estimator, responsible for work preparation and quality assurance on the project. “We got the preparations underway quickly and efficiently, including drawing up a work plan, work instructions and a risk assessment (RI&E) in consultation with BAAK. Once on site, BAAK first cleaned the tunnel deck using high-pressure water, then dried it. The primer coats were applied later that same day. The Polyurea was then spray-applied in a single coat at a temperature of 70 degrees Celsius, using our multi-component reactor metering pump.” 

Polyproof’s professionals completed the waterproofing of the first 1,700 m2 of tunnel deck in just four days.

Ready to walk on after 13 seconds

Polyurea is formed from two components. Thanks to its exceptional chemical properties, it is highly reactive, making it an extremely fast-curing spray with excellent adhesion to metal, concrete and foam. The waterproof layer can be walked on after 13 seconds, and heavy machinery can drive over it after 24 hours. The result is a continuous, waterproof coating with no harmful effects on the environment. “Immediately after application, we check the layer for adhesion, uniformity and any irregularities. Critical points are marked and rectified straight away. We always aim for a score of 10. All our findings are recorded visually and compiled in daily reports, including details such as weather conditions. The finished result was also checked by our supplier Adcos.”

Polyproof’s professionals completed the waterproofing of the first 1,700 m2 of tunnel deck in just four days. “Unfortunately, you can no longer see any sign of it,” says Bos. “BAAK started adding the earthworks the very next day, building an embankment around 14 metres high on top of the tunnel deck.” He is particularly proud of the work delivered at such short notice. “Thanks also to the support from BAAK itself. You can only deliver an Olympic performance like that as a team.” Bos is convinced that Polyurea could be used much more widely in infrastructure, including to seal car park decks, bridge decks, tunnels, bridge piers, canal passages and bicycle parking facilities. The product is also root-resistant, making it suitable for green roofs. It is solvent-free and resistant to oils, fats and chemicals, making it an extremely durable solution too.”

Question about this story? Ask your question

Who worked on Blankenburgverbinding

  1. construction consortiumBAAKMentioned in Unique and remarkable: 800-metre-long floating reed bed in the Krabbeplas near Vlaardingen
  2. crane matsKo-MatsMentioned in German engineering in dragline mats for the Blankenburg Connection project
  3. road construction companyBallastMentioned in Proud partner brings its (in-house) strengths together
  4. foundation specialistDe Vries TitanMentioned in Strong partnership delivers huge piling operation
  5. temporary support structureCiviele technieken deBoerMentioned in Jacking, sliding and pressing
  6. precast beamsHaitsma BetonMentioned in Precast concrete for the new A24
  7. prestressing systemsDYWIDAG-Systems InternationalMentioned in Smart thinking in prestressing design
  8. designTunnel Engineering Consultants (TEC)Mentioned in Environmental and community interests at the heart of a unique technical concept
  9. ondersteunings- en horizontale bekistingsconstructiesMADEMA Steigerwerken BVMentioned in Temporary support structures for in-situ decks
  10. temporary supportCT deBoerMentioned in Temporary support structures for in-situ decks
  11. supplier of the scaffolding systemMatemco Hulpconstructies BVMentioned in Temporary support structures for in-situ decks
  12. Steel-reinforced elastomeric bearingsKonstrukomMentioned in Reinforced elastomeric bearings
  13. dewatering worksHenk van Tongeren Water & TechniekMentioned in Dewatering operation
  14. civil underwater structuresDISA InternationalMentioned in A hive of activity underwater
  15. geïntegreerde video-, audio- en communicatiesystemenHacousto ProtecMentioned in The link to the traffic control centre
  16. supplierJdB groepMentioned in Reusing and upgrading soil products
  17. consultancy firmStrypesMentioned in Making a difference
  18. sealing specialistViltonMentioned in Sealing expert prevents ‘water ingress’
  19. industrial automation specialistICT GroupMentioned in Control software for tunnel systems
  20. Breaking down foundation pile headsBlijleven KoppensnellersMentioned in Dust-free pile cropping on the Blankenburg Connection
  21. excavationVerboon MaaslandMentioned in Preparing complex construction pits for construction
  22. waterproofingPolyproofIn this story
  23. waterproofing injectionsSpecial Industrial Repair (SIR)In this story
  24. supplier of waterproof coatingsAdcosIn this story
  25. wall formworkPERIMentioned in Save time and money with an advanced formwork system
  26. temporary bridgesRetro BridgeMentioned in Six temporary bridges improve access to construction site
  27. edge elementsTakke BreukelenMentioned in Architectural edge elements in composite and stainless steel
  28. precast concrete structuresVan Dijk BetonMentioned in Versatile in precast concrete structures
  29. designRijkswaterstaatMentioned in Versatile in precast concrete structures
  30. pylon claddingGlasGroenMentioned in A touch of nostalgia on the Blankenburgverbinding

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectBlankenburgverbinding
  • SubjectNews
  • CompanyPolyproof
  • CompanySpecial Industrial Repair (SIR)
  • CompanyAdcos
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.