Bridge construction

A hive of activity underwater

DISA voert tijdens het project regelmatig inspecties uit in de verschillende bouwkuipen.
DISA voert tijdens het project regelmatig inspecties uit in de verschillende bouwkuipen.

Part of the Blankenburgverbinding will lie below ground level and will largely be built underwater. As a specialist in civil engineering structures constructed underwater, DISA International is making a major contribution to several subprojects, many of which are located at considerable depth below the water level, including the Hollandtunnel and the approaches to the Maasdeltatunnel. According to John Penson, Operational Manager at DISA International, some locations are very busy underwater.

During the tender phase, BAAK regularly consulted DISA International to find the most efficient way to approach certain aspects of the underwater structures. “Pouring the underwater concrete is effectively the final stage of our work. The key is to ensure that all the processes leading up to it run smoothly and are properly coordinated. This also means carrying out regular inspections in the various cofferdams during the project. We are working in no fewer than twenty cofferdams of varying sizes on the Blankenburgverbinding. We also started by installing bracing frames to provide vessel impact protection in Het Scheur.”

During the tender phase, BAAK regularly consulted DISA International to find the most efficient way to approach certain aspects of the underwater structures.

Spotless

The Hollandtunnel cofferdams are on average 150 metres long and 35 metres wide, while those for the Maasdeltatunnel are 100 metres long and 25 metres wide. Penson explains: “The Maasdeltatunnel cofferdams are where the approaches to the immersed tunnel are being built. They lie beneath a 4% slope and descend to a depth of no less than 28 metres, where the approaches meet the immersed tunnel. The sheet-pile walls, anchor piles and GEWI anchors were installed from ground level, after which the cofferdams were excavated underwater. Our task is to use diving teams to clean the sheet-pile walls thoroughly wherever the underwater concrete will eventually be poured against them. We are also responsible for extending the anchors where necessary and fitting bearing plates to the anchor piles and GEWI anchors.”

Multiple cofferdams 

A gravel layer is then laid in the cofferdams, on which DISA International places concrete spacers. “The concrete beams, with a cross-section of 20 by 20 centimetres, are positioned very carefully to within a centimetre and set to the correct level using depth sensors,” Penson explains. “The reinforcement cages are placed on top of these beams, after which the underwater concrete can be poured, the final stage of our operation in the cofferdams. In total, twenty cofferdams are being completed in this way. At the approaches to and from the Maasdeltatunnel, we are working in three cofferdams at the same time, with a total of three teams in each cofferdam. Each team has its own diving container equipped with tools. It is certainly extremely busy underwater. At the Hollandtunnel, we are working in two cofferdams at the same time. A total of 80,000 m3 of underwater concrete will be poured in the twenty cofferdams where we have been working.”

It seems that every tunnel project in the Netherlands is being built at the same time.

DISA International has more than a hundred divers and thirty diving containers working on various projects in the Netherlands alone. “It seems as though every tunnel project in the Netherlands is being built at the same time,” Penson observes. “It is precisely on these major projects that we can demonstrate our added value. That is why, as well as the Blankenburgverbinding, we are also involved in other projects at the same time. In short, we’ll be busy for years to come.”

Have a business enquiry for DISA International? Get in touch

Who worked on Blankenburgverbinding

  1. construction consortiumBAAKMentioned in Unique and remarkable: 800-metre-long floating reed bed in the Krabbeplas near Vlaardingen
  2. crane matsKo-MatsMentioned in German engineering in dragline mats for the Blankenburg Connection project
  3. road construction companyBallastMentioned in Proud partner brings its (in-house) strengths together
  4. foundation specialistDe Vries TitanMentioned in Strong partnership delivers huge piling operation
  5. temporary support structureCiviele technieken deBoerMentioned in Jacking, sliding and pressing
  6. precast beamsHaitsma BetonMentioned in Precast concrete for the new A24
  7. prestressing systemsDYWIDAG-Systems InternationalMentioned in Smart thinking in prestressing design
  8. designTunnel Engineering Consultants (TEC)Mentioned in Environmental and community interests at the heart of a unique technical concept
  9. ondersteunings- en horizontale bekistingsconstructiesMADEMA Steigerwerken BVMentioned in Temporary support structures for in-situ decks
  10. temporary supportCT deBoerMentioned in Temporary support structures for in-situ decks
  11. supplier of the scaffolding systemMatemco Hulpconstructies BVMentioned in Temporary support structures for in-situ decks
  12. Steel-reinforced elastomeric bearingsKonstrukomMentioned in Reinforced elastomeric bearings
  13. dewatering worksHenk van Tongeren Water & TechniekMentioned in Dewatering operation
  14. civil underwater structuresDISA InternationalIn this story
  15. geïntegreerde video-, audio- en communicatiesystemenHacousto ProtecMentioned in The link to the traffic control centre
  16. supplierJdB groepMentioned in Reusing and upgrading soil products
  17. consultancy firmStrypesMentioned in Making a difference
  18. sealing specialistViltonMentioned in Sealing expert prevents ‘water ingress’
  19. industrial automation specialistICT GroupMentioned in Control software for tunnel systems
  20. Breaking down foundation pile headsBlijleven KoppensnellersMentioned in Dust-free pile cropping on the Blankenburg Connection
  21. excavationVerboon MaaslandMentioned in Preparing complex construction pits for construction
  22. waterproofingPolyproofMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
  23. waterproofing injectionsSpecial Industrial Repair (SIR)Mentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
  24. supplier of waterproof coatingsAdcosMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
  25. wall formworkPERIMentioned in Save time and money with an advanced formwork system
  26. temporary bridgesRetro BridgeMentioned in Six temporary bridges improve access to construction site
  27. edge elementsTakke BreukelenMentioned in Architectural edge elements in composite and stainless steel
  28. precast concrete structuresVan Dijk BetonMentioned in Versatile in precast concrete structures
  29. designRijkswaterstaatMentioned in Versatile in precast concrete structures
  30. pylon claddingGlasGroenMentioned in A touch of nostalgia on the Blankenburgverbinding

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectBlankenburgverbinding
  • SubjectBridge construction
  • CompanyDISA International
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.