Save time and money with an advanced formwork system

The construction of the Blankenburg Connection comprises several sections, each requiring a bespoke approach. PERI contributed to four of the main sections by providing its expertise, skills and equipment. Almost every discipline within the company was involved. In total, PERI supplied more than 17,000 m2 of wall formwork (VARIO and MAXIMO), and 300 trailers of equipment were delivered to the project. Systems used during this ongoing project include PERI UP for shoring, stair towers and reinforcement scaffolds; VARIO, MAXIMO and TRIO for wall formwork; and VARIOKIT for special solutions.
PERI supplied the formwork for the walls of the central tunnel duct, both for the construction of the Hollandtunnel and for the immersed elements of the Maasdeltatunnel, including gantry carriages with hydraulic systems. This system allows the crane to be operated and moved independently. The walls were built using single-sided tie anchoring, a major advantage given the limited space available for movement. In addition, no crane is needed to strip and move the wall formwork. This saves time and money, among other benefits.
Meccano for grown-ups
PERI also supplied the wall formwork for the approaches to the central tunnel duct. A travelling formwork carriage was built from the VARIOKIT system to carry out this work. “The VARIOKIT system can be thought of as Meccano for grown-ups,” says Rene van Zutven of PERI BeNeLux. “The system is versatile, and its standard components are ideally suited to creating high-quality special structures for civil engineering concrete construction. Its versatility makes it suitable for a wide range of applications. It can be deployed quickly, and much of it can be prepared as prefabricated units.” Finally, at the Maasdeltatunnel, the walls on both the north and south sides were built using the PERI single-sided MAXIMO panel formwork system. This also resulted in a significant saving in time.
A business enquiry for PERI? Get in touch
Who worked on Blankenburgverbinding
- construction consortiumBAAKMentioned in Unique and remarkable: 800-metre-long floating reed bed in the Krabbeplas near Vlaardingen
- crane matsKo-MatsMentioned in German engineering in dragline mats for the Blankenburg Connection project
- designTunnel Engineering Consultants (TEC)Mentioned in Environmental and community interests at the heart of a unique technical concept
- ondersteunings- en horizontale bekistingsconstructiesMADEMA Steigerwerken BVMentioned in Temporary support structures for in-situ decks
- supplier of the scaffolding systemMatemco Hulpconstructies BVMentioned in Temporary support structures for in-situ decks
- geïntegreerde video-, audio- en communicatiesystemenHacousto ProtecMentioned in The link to the traffic control centre
- Breaking down foundation pile headsBlijleven KoppensnellersMentioned in Dust-free pile cropping on the Blankenburg Connection
- waterproofingPolyproofMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- waterproofing injectionsSpecial Industrial Repair (SIR)Mentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- supplier of waterproof coatingsAdcosMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- edge elementsTakke BreukelenMentioned in Architectural edge elements in composite and stainless steel
Keep following this
Get an email when a new story is published. No account needed.
- ProjectBlankenburgverbinding
- ThemeMaterials and techniques for infrastructure
- SubjectBridge construction
- CompanyPERI