Proud partner brings its (in-house) strengths together

With a nominal value of €1 billion, the Blankenburgverbinding is one of the largest public-private partnership (PPP) projects in the Netherlands. As a partner in both the SPC (shareholders) and EPC (BAAK construction consortium), Ballast Nedam considers it a special assignment. “We bring together the expertise and capacity of different disciplines in a close-knit, integrated team. This enables us to deliver an efficient, high-quality project for Rijkswaterstaat, on time in 2024,” says Peter Kanninga, Commercial Director of Ballast Nedam Infra Projects.
The DBFM consortium brings together Ballast Nedam, DIMCO BV and Dredging International in an integrated partnership. The latter two are subsidiaries of DEME Group. “Together with our EPC partners, we are delivering the entire project scope, with Ballast Nedam focusing in particular on structures, complex foundations and tunnel technical installations. We also have a significant share in the design and project management for the project as a whole,” explains Kanninga. “The latter is a discipline in its own right on a project this complex and challenging, with so many stakeholders. Perfect coordination and managing everyone’s expectations are crucial. This naturally also applies to our contact with local residents, water authorities, the Port of Rotterdam, the Municipality of Vlaardingen and others.”
Virtual reality
The Blankenburgverbinding is also a technical tour de force. Kanninga says: “Building the immersed tunnel beneath Het Scheur and constructing the approach roads in deep excavations up to 30 metres below ground level place great demands on our organisation’s knowledge and expertise, including our in-house engineering capabilities. We have also brought in a number of Dutch specialists, such as TEC, to work together on the design of the immersed tunnel and deep excavations. One of our strengths is ensuring that the design remains technically buildable. Designing complex technical structures is one thing, but ensuring they can be built during the design phase is another. The experience and expertise of our various business units have enabled us to make a real difference here. The use of state-of-the-art BIM models and virtual reality (VR) technology further supports this process. In this respect, too, we are an innovative organisation, constantly looking for ways to develop further. We have to be, because the deep excavations are technically complex, cut through the primary flood defence and are located in one of the busiest shipping areas in the Netherlands.”

Stronger together
As one of the oldest construction companies in the Netherlands, with more than 140 years in business, Ballast Nedam has a rich history of major, innovative and complex projects. Several business units are naturally involved in a project of this scale, including Ballast Nedam Road Specialties and Ballast Nedam PMC Specialties. “One of our strengths is that, as subsidiaries, we can always work together easily. We can rely on one another and continually strengthen each other,” says Joep Hartjes, Director of Ballast Nedam Road Specialties. Since the contract was awarded to BAAK, the consortium has been responsible for the management and maintenance of the entire A20 and A15. “As a road construction company with broad expertise, we can play a significant role in every phase of the Blankenburgverbinding. We have all the expertise and resources in-house to build a road from start to finish, including road markings, safety barriers and even landscape maintenance.”
An optimised lifecycle model
BAAK is committed to pursuing the optimum lifecycle model, as required by the DBFM contract. “In other words, designing the project to deliver the required quality over its entire lifecycle at the lowest cost,” Kanninga acknowledges. “That is why we place such importance on collaboration between our business units. We draw on one another’s experience and best practice, and are not afraid to innovate our products to make a difference. This often involves developing unique solutions.” Hartjes adds: “For the A9 Gaasperdammerweg, for example, we developed a new type of asphalt that reflects light better, reducing the amount of lighting needed in the tunnel. We try to make a difference on every project in this way. The Blankenburgverbinding also presents plenty of challenges. We are currently contributing our expertise to the development of a special type of asphalt with a longer service life.” Ballast Nedam Road Specialties constructed the temporary access roads on the project and realigned part of the A15 to make room for the structures. The major work will begin in 2022, when the asphalt is laid for the tunnels and the interchanges with the A15 and A20.

Limiting risks
Speaking of ground conditions, one of the biggest challenges in infrastructure is managing risks relating to the geotechnical conditions below ground. “We start working together during the tender stage to identify risks early,” says Thom Hienekamp, Director of Ballast Nedam PMC Specialties and an expert in areas including foundations and anchors. “Excavating a construction pit to 30 metres below ground level is no small undertaking. We use all our knowledge and experience to minimise potential risks. We are not afraid to do things differently. Entrepreneurship is encouraged throughout our organisation. This means we often come up with fresh ideas and methods that may be technically complex, but do create added value for our clients, such as constructing the decks of the flyovers above the A15 without any traffic closures, or reducing the number of immersion operations for the Maasdeltatunnel by immersing two elements instead of six.” Ballast Nedam PMC Specialties is active along almost the entire route and is currently busy excavating the construction pits.
The gentlemen are extremely proud to be contributing to this major project, which brings together a series of technical feats. “That goes for our entire organisation, of course,” Kanninga adds. “We are truly doing this together, with great craftsmanship and, above all, a great deal of passion.”
Een zakelijke vraag aan Ballast Nedam Road Specialties? Get in touch
Who worked on Blankenburgverbinding
- construction consortiumBAAKMentioned in Unique and remarkable: 800-metre-long floating reed bed in the Krabbeplas near Vlaardingen
- crane matsKo-MatsMentioned in German engineering in dragline mats for the Blankenburg Connection project
- designTunnel Engineering Consultants (TEC)Mentioned in Environmental and community interests at the heart of a unique technical concept
- ondersteunings- en horizontale bekistingsconstructiesMADEMA Steigerwerken BVMentioned in Temporary support structures for in-situ decks
- supplier of the scaffolding systemMatemco Hulpconstructies BVMentioned in Temporary support structures for in-situ decks
- geïntegreerde video-, audio- en communicatiesystemenHacousto ProtecMentioned in The link to the traffic control centre
- Breaking down foundation pile headsBlijleven KoppensnellersMentioned in Dust-free pile cropping on the Blankenburg Connection
- waterproofingPolyproofMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- waterproofing injectionsSpecial Industrial Repair (SIR)Mentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- supplier of waterproof coatingsAdcosMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- edge elementsTakke BreukelenMentioned in Architectural edge elements in composite and stainless steel
Keep following this
Get an email when a new story is published. No account needed.
- ProjectBlankenburgverbinding
- SubjectBridge construction
- CompanyBallast Nedam Road Specialties
- CompanyEPC Groep