Bridge construction

Smart thinking in prestressing design

In total, 1,400 tonnes of steel are used in the project, in varying DYWIDAG post-tensioning systems of 19 to 31 strands.
In total, 1,400 tonnes of steel are used in the project, in varying DYWIDAG post-tensioning systems of 19 to 31 strands.

All structures on the Blankenburg Connection are being built using DYWIDAG prestressing systems. According to Robert Jansen of DYWIDAG-Systems International, the design incorporates a number of clever features to accommodate BAAK’s construction sequencing. These range from connecting prestressing systems through to fully submerging prestressing systems that are not yet complete.

“The decks of two viaducts at the Rozenburg interchange are being built one after the other on temporary supports,” Jansen explains. “Once complete, they are slid into their final position and another deck section is cast against them, while the prestressing still has to be continuous. That makes it a challenging operation, but it also gives us scope to tailor the prestressing to requirements. After all, each individual span has different prestressing requirements. If a structure is cast in one go, the prestressing is the same across the entire deck. Here, we can vary the cable lengths and the number of strands per cable. Not every cable has to run from one end to the other, which means we need to incorporate fewer cables. It is not unique, but it does require extra attention.”

DYWIDAG-Systems International has incorporated a number of clever features into the prestressing design to accommodate BAAK’s construction sequencing.

Extra attention was also needed for the prestressing in the props supporting the tunnel approaches, which are being built in several phases. Jansen explains: “The lower section of the props is being cast now, after which the construction pit will be flooded. In a year’s time, the props will be ‘dug up’ again and the second section will be cast. Here too, the prestressing has to be continuous. Water and steel do not go particularly well together, of course. Plastic was not an option, however. So we came up with a steel solution after all, ‘heavy and galvanised’, which is sealed with a watertight cap.” A total of 1,400 tonnes of steel is being used on the project in various DYWIDAG prestressing systems with 19 to 31 strands.

Question about this story? Ask your question

Who worked on Blankenburgverbinding

  1. construction consortiumBAAKMentioned in Unique and remarkable: 800-metre-long floating reed bed in the Krabbeplas near Vlaardingen
  2. crane matsKo-MatsMentioned in German engineering in dragline mats for the Blankenburg Connection project
  3. road construction companyBallastMentioned in Proud partner brings its (in-house) strengths together
  4. foundation specialistDe Vries TitanMentioned in Strong partnership delivers huge piling operation
  5. temporary support structureCiviele technieken deBoerMentioned in Jacking, sliding and pressing
  6. precast beamsHaitsma BetonMentioned in Precast concrete for the new A24
  7. prestressing systemsDYWIDAG-Systems InternationalIn this story
  8. designTunnel Engineering Consultants (TEC)Mentioned in Environmental and community interests at the heart of a unique technical concept
  9. ondersteunings- en horizontale bekistingsconstructiesMADEMA Steigerwerken BVMentioned in Temporary support structures for in-situ decks
  10. temporary supportCT deBoerMentioned in Temporary support structures for in-situ decks
  11. supplier of the scaffolding systemMatemco Hulpconstructies BVMentioned in Temporary support structures for in-situ decks
  12. Steel-reinforced elastomeric bearingsKonstrukomMentioned in Reinforced elastomeric bearings
  13. dewatering worksHenk van Tongeren Water & TechniekMentioned in Dewatering operation
  14. civil underwater structuresDISA InternationalMentioned in A hive of activity underwater
  15. geïntegreerde video-, audio- en communicatiesystemenHacousto ProtecMentioned in The link to the traffic control centre
  16. supplierJdB groepMentioned in Reusing and upgrading soil products
  17. consultancy firmStrypesMentioned in Making a difference
  18. sealing specialistViltonMentioned in Sealing expert prevents ‘water ingress’
  19. industrial automation specialistICT GroupMentioned in Control software for tunnel systems
  20. Breaking down foundation pile headsBlijleven KoppensnellersMentioned in Dust-free pile cropping on the Blankenburg Connection
  21. excavationVerboon MaaslandMentioned in Preparing complex construction pits for construction
  22. waterproofingPolyproofMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
  23. waterproofing injectionsSpecial Industrial Repair (SIR)Mentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
  24. supplier of waterproof coatingsAdcosMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
  25. wall formworkPERIMentioned in Save time and money with an advanced formwork system
  26. temporary bridgesRetro BridgeMentioned in Six temporary bridges improve access to construction site
  27. edge elementsTakke BreukelenMentioned in Architectural edge elements in composite and stainless steel
  28. precast concrete structuresVan Dijk BetonMentioned in Versatile in precast concrete structures
  29. designRijkswaterstaatMentioned in Versatile in precast concrete structures
  30. pylon claddingGlasGroenMentioned in A touch of nostalgia on the Blankenburgverbinding

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectBlankenburgverbinding
  • SubjectBridge construction
  • CompanyDYWIDAG-Systems International
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.