Smart thinking in prestressing design

All structures on the Blankenburg Connection are being built using DYWIDAG prestressing systems. According to Robert Jansen of DYWIDAG-Systems International, the design incorporates a number of clever features to accommodate BAAK’s construction sequencing. These range from connecting prestressing systems through to fully submerging prestressing systems that are not yet complete.
“The decks of two viaducts at the Rozenburg interchange are being built one after the other on temporary supports,” Jansen explains. “Once complete, they are slid into their final position and another deck section is cast against them, while the prestressing still has to be continuous. That makes it a challenging operation, but it also gives us scope to tailor the prestressing to requirements. After all, each individual span has different prestressing requirements. If a structure is cast in one go, the prestressing is the same across the entire deck. Here, we can vary the cable lengths and the number of strands per cable. Not every cable has to run from one end to the other, which means we need to incorporate fewer cables. It is not unique, but it does require extra attention.”

Extra attention was also needed for the prestressing in the props supporting the tunnel approaches, which are being built in several phases. Jansen explains: “The lower section of the props is being cast now, after which the construction pit will be flooded. In a year’s time, the props will be ‘dug up’ again and the second section will be cast. Here too, the prestressing has to be continuous. Water and steel do not go particularly well together, of course. Plastic was not an option, however. So we came up with a steel solution after all, ‘heavy and galvanised’, which is sealed with a watertight cap.” A total of 1,400 tonnes of steel is being used on the project in various DYWIDAG prestressing systems with 19 to 31 strands.
Question about this story? Ask your question
Who worked on Blankenburgverbinding
- construction consortiumBAAKMentioned in Unique and remarkable: 800-metre-long floating reed bed in the Krabbeplas near Vlaardingen
- crane matsKo-MatsMentioned in German engineering in dragline mats for the Blankenburg Connection project
- prestressing systemsDYWIDAG-Systems InternationalIn this story
- designTunnel Engineering Consultants (TEC)Mentioned in Environmental and community interests at the heart of a unique technical concept
- ondersteunings- en horizontale bekistingsconstructiesMADEMA Steigerwerken BVMentioned in Temporary support structures for in-situ decks
- supplier of the scaffolding systemMatemco Hulpconstructies BVMentioned in Temporary support structures for in-situ decks
- geïntegreerde video-, audio- en communicatiesystemenHacousto ProtecMentioned in The link to the traffic control centre
- Breaking down foundation pile headsBlijleven KoppensnellersMentioned in Dust-free pile cropping on the Blankenburg Connection
- waterproofingPolyproofMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- waterproofing injectionsSpecial Industrial Repair (SIR)Mentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- supplier of waterproof coatingsAdcosMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- edge elementsTakke BreukelenMentioned in Architectural edge elements in composite and stainless steel
Keep following this
Get an email when a new story is published. No account needed.
- ProjectBlankenburgverbinding
- SubjectBridge construction
- CompanyDYWIDAG-Systems International