Architectural edge elements in composite and stainless steel

The concrete structures on the A24 Blankenburg Connection are being finished with architecturally striking edge elements, mainly in composite, with a few in stainless steel. The work has been commissioned by construction consortium BAAK to Takke Breukelen, an expert in this type of structure. Given the scale of the project, rising material prices and the many interfaces with structures and signal gantries provided by third parties, it is a substantial undertaking.
Takke Breukelen is responsible for the design, manufacture and installation of all the edge elements. “It is a fairly large project, with more than 2,600 linear metres of composite edge elements, including 2,100 metres configured as parapets with stainless steel safety screens, 700 metres of stainless steel edge elements with stainless steel safety screens, and a further 1,200 metres of noise barriers,” says Jorn van Herwijnen, design lead at Takke Breukelen. “Given the scale of the project and market uncertainty over lead times and material prices, BAAK worked closely with us on the design to achieve a consistent, as minimalist as possible finished product while meeting all the constraints.”

Full-scale mock-up
Takke Breukelen’s edge elements generally provide the finishing touches to the structures. “As well as on the structures, our elements can also be found along a section of sheet piling and partly on the concrete ground beams between the structures,” explains Van Herwijnen. “A major advantage for us on the Blankenburg Connection was that the concrete design had already been worked out in 3D down to the finest detail. That gave us a great basis for developing the edge-element design, which was also modelled entirely in 3D.” To give BAAK, the local aesthetics committee and the architect a clear picture of the finished result, Takke Breukelen built a full-scale mock-up of the edge elements. “It was part of the design process, so that once the design had been approved, we could develop it further for each structure and start production.”
One type of edge element
Takke Breukelen ultimately succeeded in incorporating all the requirements and constraints into a single type of edge element. “We did make the necessary adjustments for each structure to accommodate varying concrete heights and crossfalls,” says Van Herwijnen. “We also had to deal with numerous interfaces with third-party installations. For example, 14 signal gantries (matrix signs) are integrated into the elements, and we incorporated the connections for lighting columns into the edge elements at 42 locations.” Takke Breukelen is carrying out the work in phases. “We are currently finalising the last design details, while production and installation are already well under way. The most challenging part will be installing the edge elements above the A15 during a road closure in April. It will all have to be done within that time frame. On the other hand, we have plenty of scope to take measurements on this project. Normally, we have to work from drawings and can only take measurements a few weeks before installation. That is not the case here, as the concrete structure is already at an advanced stage each time.”
Question about this story? Ask your question
Who worked on Blankenburgverbinding
- construction consortiumBAAKMentioned in Unique and remarkable: 800-metre-long floating reed bed in the Krabbeplas near Vlaardingen
- crane matsKo-MatsMentioned in German engineering in dragline mats for the Blankenburg Connection project
- designTunnel Engineering Consultants (TEC)Mentioned in Environmental and community interests at the heart of a unique technical concept
- ondersteunings- en horizontale bekistingsconstructiesMADEMA Steigerwerken BVMentioned in Temporary support structures for in-situ decks
- supplier of the scaffolding systemMatemco Hulpconstructies BVMentioned in Temporary support structures for in-situ decks
- geïntegreerde video-, audio- en communicatiesystemenHacousto ProtecMentioned in The link to the traffic control centre
- Breaking down foundation pile headsBlijleven KoppensnellersMentioned in Dust-free pile cropping on the Blankenburg Connection
- waterproofingPolyproofMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- waterproofing injectionsSpecial Industrial Repair (SIR)Mentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- supplier of waterproof coatingsAdcosMentioned in A24 Blankenburgverbinding: Urgent job for waterproofing specialist
- edge elementsTakke BreukelenIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectBlankenburgverbinding
- ThemeMaterials and techniques for infrastructure
- SubjectBridge construction
- CompanyTakke Breukelen























