Water infrastructure

The art of replacing lock gates

Text Roel van Gils Images De Klerk

Voor De Klerk vormen de deurwissels de bekroning van jarenlange betrokkenheid bij het complex, waar het bedrijf sinds 2015 vrijwel onafgebroken actief is met onderhouds-, renovatie- en revisiewerkzaamheden.
Voor De Klerk vormen de deurwissels de bekroning van jarenlange betrokkenheid bij het complex, waar het bedrijf sinds 2015 vrijwel onafgebroken actief is met onderhouds-, renovatie- en revisiewerkzaamheden.

Replacing a lock gate may seem like a simple matter of taking it out and putting it back. The reality is considerably more complex, especially at the Krammersluizen, where gates range in weight from 65 tonnes to as much as 400 tonnes. For De Klerk, replacing the gates is the culmination of years of involvement in the complex, where the company has been almost continuously engaged in maintenance, renovation and overhaul work since 2015.

That experience played an important role when the ZEEKR consortium began looking for specialist partners to renovate various parts of the complex. “De Klerk was brought in during the tender phase to advise on gate replacement, bed protection works, construction methods, phasing and risks,” says Edwin Sebregts, mechanical engineering discipline lead at De Klerk.

The fixed bridge above the lock chamber leaves limited room for lifting operations on the side of the bascule bridge.

A complete package under one roof

De Klerk’s involvement is no coincidence. “Between 2020 and 2024, we overhauled all the steel fendering and mooring berths in the Krammersluizen approach harbours,” says Sebregts. “The steel structures were dismantled, refurbished, recoated and reinstalled.” De Klerk had also previously replaced several gates at the complex, in both the yacht locks and the inland shipping locks. “Water engineering is our largest discipline, but we also have a steel fabrication business and, since 2019, a mechanical engineering division.” This combination is particularly valuable when replacing gates and overhauling the gates of the yacht locks.

All of De Klerk’s disciplines come together on this project.

Static emergency barrier

After the summer, one of the most visible parts of the renovation gets under way: replacing the gates in the yacht lock. “Work on one lock chamber runs from mid-September to early May,” Sebregts explains. The timing is deliberate, to minimise disruption to recreational boating during the peak season. “Each time, one lock gate is removed and replaced with a temporary (static) emergency barrier. The gate is then taken to our yard in Moerdijk, where it is overhauled, strengthened where necessary and recoated. About nine weeks later, the gate returns to the chamber and the emergency barrier is moved to the second gate in the same chamber, after which we repeat the process.”

The yacht lock gates weigh around 65 tonnes, but Sebregts says that weight is not the biggest challenge. “The fixed bridge above the chamber means there is limited room for lifting operations on one side.” De Klerk devised a specific method for this: the gate is first lifted, then a pontoon carrying a specially designed steel frame is manoeuvred underneath it. This keeps the gate upright so it can be floated out of the chamber.

Floating sheerleg crane

At the same time, gates are also being replaced at the inland shipping locks. “This is on a completely different scale,” says Sebregts. “A rolling gate weighs almost 400 tonnes, including its components.” For this operation, De Klerk is working with Rotterdam-based specialist Bon & Mees. “The enormous gates are removed and replaced with a modified, overhauled rolling gate using the floating sheerleg crane Matador. On behalf of Smulders, De Klerk is handling logistics, mechanical engineering work and support during these complex operations, among other things. Smulders is overhauling the gates in Vlissingen. As soon as a gate is ready, we pick it up and move on to the next replacement.”

From dismantling drive systems and overhauling moving parts to steel repairs, coating and lifting operations from the water, all of De Klerk’s disciplines come together on this project.

Have a business enquiry for De Klerk Werkendam? Get in touch

Who worked on Krammersluizencomplex

  1. main contractorBESIXMentioned in The power of systems integration in the renovation of the Krammer Locks complex
  2. constructionZEEKRMentioned in The power of systems integration in the renovation of the Krammer Locks complex
  3. system integrationINNOCYMentioned in The power of systems integration in the renovation of the Krammer Locks complex
  4. system integrationCPM ConsultancyMentioned in The power of systems integration in the renovation of the Krammer Locks complex
  5. renovationZEEKR combinationMentioned in Krammer Locks under scrutiny
  6. hydraulics partnerBosch RexrothMentioned in Smarter hydraulics give Krammersluizen extra capacity
  7. replacement, renovation and modificationIemantsMentioned in Modified 400-tonne lock gates improve the lockage process
  8. renovationSmuldersMentioned in Renovating the Netherlands’ largest concrete structure
  9. mechanical installationsDemakoMentioned in Champions League standard in mechanical engineering
  10. subcontractorDISA InternationalMentioned in The foundations for a new pumping station are being laid underwater
  11. specialistBon & MeesIn this story
  12. concrete repairBE InjectMentioned in Concrete repairs under high voltage
  13. independent baseline inspectionA-QuinMentioned in Independent baseline inspection prevents surprises
  14. directorAmstelland IngenieursMentioned in From design to maintenance: an integrated approach to the Krammer Locks
  15. machinery safety consultantKaderMentioned in CE marking for one of the Netherlands’ most complex lock projects
  16. lead hydraulic engineering engineerHessel Voortman Engineering ConsultancyMentioned in A masterclass in hydraulic engineering
  17. engineering consultancyBT EngineeringMentioned in From pencil drawings to a digital blueprint
  18. engineering consultancyMBM EngineersMentioned in From pencil drawings to a digital blueprint
  19. engineering consultancyMaters & De KoningMentioned in From pencil drawings to a digital blueprint

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectKrammersluizencomplex
  • ThemeExtending the life of roads and civil engineering structures
  • SubjectWater infrastructure
  • CompanyBon & Mees
  • CompanyDe Klerk Werkendam
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.