From pencil drawings to a digital blueprint
Text Roel van Gils Image MBM Engineers

Yellowed pencil drawings from the 1980s provided the starting point for the renovation of the Krammersluizen. Although the original design drawings were still available, after forty years it became clear that many of the repairs, modifications and improvements made had neither been recorded nor documented. To model all the existing installations accurately, MBM Engineers combined archival research, 3D scans and advanced modelling techniques. This created a digital blueprint that is essential to the renovation of the lock complex.
MBM Engineers is a collaboration between three engineering consultancies: MH Poly, BT Engineering and Maters & De Koning. Together, they have more than 120 specialists in structural engineering, geotechnical engineering, mechanical engineering, building engineering and inspections. The companies already knew one another through their work in the sector. This is how MBM Engineers came to the attention of the ZEEKR consortium. “The project required specialist knowledge and experience to model all the existing installations accurately,” says Paul Quist, chair of the engineering collective.
Documenting the installations
The task was assigned to Michiel Zwart, a modeller at MH Poly. His brief was to document digitally all the installations in and around the locks, from rolling gates, stairs and overhead cranes to steel structures and mechanical installations. “So this wasn’t about the overall shape of the structure, but specifically about all the components inside it,” says Zwart. “That information provides the basis for other parties to carry out their design and modification work.” This proved to be a major challenge. “Most of the original drawings date from the 1980s and were often still drawn using pencil and ruler. In addition, not everything that had been modified over the past forty years had actually been documented.”

Shared model environment
Zwart combined archival research with extensive site surveys, photographs and 3D scans supplied by the ZEEKR consortium. “I modelled all the existing installations in 3D using Inventor,” he says. “The consortium then brought all these 3D models together in Revisto, in a shared model environment for the entire complex, including its overall form. This made it immediately clear whether designs and modifications fitted together, and where the clashes were.”
Existing conditions take precedence
According to Paul, the project reflects a broader trend in the infrastructure sector. “Engineering consultancies traditionally focused mainly on new construction, but attention is increasingly shifting towards the renovation and replacement of existing assets. With new construction, everything starts with the overall form. For renovation, the existing conditions take precedence. Existing installations and structures then suddenly become the starting point for the design. This calls for a different way of thinking and working. That is precisely where MBM Engineers’ strength lies.”
With their integrated approach, the three consultancies help clients make complex renovation projects manageable and deliverable, from the initial survey through to design and construction supervision.
A business enquiry for BT Engineering? Get in touch
Who worked on Krammersluizencomplex
- main contractor
BESIXMentioned in The power of systems integration in the renovation of the Krammer Locks complex - constructionZEEKRMentioned in The power of systems integration in the renovation of the Krammer Locks complex
- system integrationINNOCYMentioned in The power of systems integration in the renovation of the Krammer Locks complex
- system integrationCPM ConsultancyMentioned in The power of systems integration in the renovation of the Krammer Locks complex
- replacement, renovation and modificationIemantsMentioned in Modified 400-tonne lock gates improve the lockage process
- subcontractor
DISA InternationalMentioned in The foundations for a new pumping station are being laid underwater - independent baseline inspection
A-QuinMentioned in Independent baseline inspection prevents surprises - machinery safety consultant
KaderMentioned in CE marking for one of the Netherlands’ most complex lock projects - lead hydraulic engineering engineerHessel Voortman Engineering ConsultancyMentioned in A masterclass in hydraulic engineering
- engineering consultancyMBM EngineersIn this story
- engineering consultancyMaters & De KoningIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectKrammersluizencomplex
- SubjectWater infrastructure
- CompanyBT Engineering
- CompanyMBM Engineers
- CompanyMaters & De Koning