Water infrastructure

The foundations for a new pumping station are being laid underwater

Text Roel van Gils Images DISA International

De samenwerking tussen DISA International en combinatie ZEEKR op de Krammersluizen ontstond vanuit positieve ervaringen op eerdere projecten.
De samenwerking tussen DISA International en combinatie ZEEKR op de Krammersluizen ontstond vanuit positieve ervaringen op eerdere projecten.

As part of the major renovation of the Krammersluizencomplex, work is under way to prepare for a new pumping station between two existing lock chambers. Diving teams from DISA International have mapped the profiles of both chamber walls to centimetre accuracy, while keeping the locks operational throughout.

The collaboration between DISA International and the ZEEKR consortium on this project grew out of positive experiences on previous projects, says Marc Veldhuizen, project manager at DISA International. The parties came together as early as the design phase to consider smart working methods and potential risks. This early involvement has proved essential. “It means we can contribute at an early stage as a subcontractor, advising on buildability and safety. That helps avoid surprises during construction.”

Surveying the existing structure

The renovation of the Krammersluizencomplex is a substantial project. It includes the construction of a new pumping station between the two existing chambers of the push-tow locks. An important part of the preparations involved accurately surveying the existing underwater structure. Two diving teams mapped the chamber walls and floor, centimetre by centimetre. According to Michiel Collin, work planner at DISA International, this is necessary to ensure the new structures fit precisely against the existing ones. “Possible shifts or settlement over the years mean the original drawings no longer match reality everywhere,” he says.

Specialist measuring equipment

DISA developed specialist measuring equipment to survey the inclination of the chamber walls. “Our teams used a bespoke aluminium measuring staff with extendable probes that made contact with the chamber wall. Combined with a digital inclinometer and depth sensors, this enabled us to take and check X, Y and Z measurements very accurately,” Michiel explains. “Those results form the basis for designing the temporary cofferdam structures and the permanent construction pit.”

Steel plates

In mid-May 2026, DISA made the necessary preparations to anchor the temporary cofferdam structure to the existing structure on the central island. “Steel plates 14 metres long were installed underwater on both the north and south sides of the island,” Michiel explains. Around 70 holes had to be drilled into the existing concrete for each plate, without damaging the reinforcement.

A precision operation

Drilling was a precision operation, especially as the reinforcement could not be scanned underwater, says Cecil de Groot, site manager at DISA International. “Our drilling teams marked the positions where they encountered reinforcement so these areas can be filled in later. The steel plates installed have prefabricated interlocking joints, to which the sheet piles of the cofferdam will later connect. This will ultimately create a watertight connection to the existing structure.”

A solution-focused approach

As well as the technical challenges, logistics played a major role in DISA’s work. “The lock remained in use throughout our work,” says Cecil, adding that shipping always had priority. “Whenever a vessel approached the lock, work was suspended while it passed through. This required constant coordination with the lock keeper and careful scheduling of all activities.”

In the coming period, the focus will be on constructing the pumping station and progressing the construction pit, including pouring approximately 3,000 m2 of underwater concrete. “We will of course be closely involved in this work too, as well as in all the other phases over the coming years that require diving support.”

Have a business enquiry for DISA International? Get in touch

Who worked on Krammersluizencomplex

  1. main contractorBESIXMentioned in The power of systems integration in the renovation of the Krammer Locks complex
  2. constructionZEEKRMentioned in The power of systems integration in the renovation of the Krammer Locks complex
  3. system integrationINNOCYMentioned in The power of systems integration in the renovation of the Krammer Locks complex
  4. system integrationCPM ConsultancyMentioned in The power of systems integration in the renovation of the Krammer Locks complex
  5. renovationZEEKR combinationMentioned in Krammer Locks under scrutiny
  6. hydraulics partnerBosch RexrothMentioned in Smarter hydraulics give Krammersluizen extra capacity
  7. replacement, renovation and modificationIemantsMentioned in Modified 400-tonne lock gates improve the lockage process
  8. renovationSmuldersMentioned in Renovating the Netherlands’ largest concrete structure
  9. mechanical installationsDemakoMentioned in Champions League standard in mechanical engineering
  10. subcontractorDISA InternationalIn this story
  11. specialistBon & MeesMentioned in The art of replacing lock gates
  12. concrete repairBE InjectMentioned in Concrete repairs under high voltage
  13. independent baseline inspectionA-QuinMentioned in Independent baseline inspection prevents surprises
  14. directorAmstelland IngenieursMentioned in From design to maintenance: an integrated approach to the Krammer Locks
  15. machinery safety consultantKaderMentioned in CE marking for one of the Netherlands’ most complex lock projects
  16. lead hydraulic engineering engineerHessel Voortman Engineering ConsultancyMentioned in A masterclass in hydraulic engineering
  17. engineering consultancyBT EngineeringMentioned in From pencil drawings to a digital blueprint
  18. engineering consultancyMBM EngineersMentioned in From pencil drawings to a digital blueprint
  19. engineering consultancyMaters & De KoningMentioned in From pencil drawings to a digital blueprint

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectKrammersluizencomplex
  • SubjectWater infrastructure
  • CompanyDISA International
  • CompanyVeldhuizen b.v.
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.