Krammer Locks under scrutiny
Text Roel van Gils Image Nebest

Comprehensive inspections and investigations as the basis for renovation
Commissioned by consortium ZEEKR, Nebest MOA Metaal carried out specialist inspections and in-depth material investigations to assess parts of the Krammer Locks complex, both above and below water. This provided a clear picture of their maintenance condition and, with targeted recommendations, practical guidance for informed maintenance and renovation decisions.
Nebest’s involvement in the project began as early as 2018. “At that point, our diving specialists carried out extensive inspections below the waterline,” says Bart Vreugdenhil, project manager at Nebest MOA Metaal. “Concrete structures, steel components and other assets were carefully examined to establish which needed renovation. This information also provided an important basis for preparing the subsequent works.”
Structural safety
After the renovation contract was awarded to consortium ZEEKR, additional issues came to light that had not been covered by the baseline inspections and preliminary investigations. “So our concrete team was sent out into the field to investigate, among other things, the lock chambers at the yacht locks and push-tow locks,” Bart explains. “We assessed the quality of the concrete through visual inspections, cover measurements, material testing and laboratory analyses. We also carried out residual service life analyses and used trial drilling to investigate how future modifications, such as the construction of the new discharge structure and fish passage, would affect structural safety.”

Safe to use
Nebest MOA Metaal focused on the steel components at the yacht locks. “One of our first assignments was to assess the maintenance gates used to dewater sections of the lock chamber for inspection and maintenance,” Bart explains. “Although these gates have been at the complex for many years, it was not known exactly when they had last been inspected. Structural inspections, material thickness measurements and corrosion mapping enabled us to confirm that the gates were safe to use at the yacht lock.”
Blueprint
Nebest has now assessed all the gates at the yacht locks, including the vertical gates at the fresh-/saltwater barrier. “For some gates, which show substantial material loss, the structural engineer for consortium ZEEKR is carrying out a recalculation based on our measurements,” says Hein van den Hout, product group manager at Nebest MOA Metaal. “The gates are safe to use now, but modifications could potentially extend their service life considerably.” At the request of consortium ZEEKR, Nebest’s successful approach at the yacht locks was then replicated at the push-tow locks. Hein says: “We effectively created a blueprint for inspecting the maintenance gates at the yacht locks, then applied it to the push-tow locks and the basin system.”
Proactive approach
At the initiative of consortium ZEEKR, Nebest MOA Metaal also assessed the operation of various mechanical components at the yacht locks, after damage to the gears of the Panama wheel drive was identified during a mechanical inspection. “We used non-destructive testing techniques to rule out cracking,” says Hein. “However, we did identify an alignment issue with the drive. This information was then shared with Rijkswaterstaat, who said they greatly valued this proactive approach. After all, it was outside the scope of the work. By flagging the issue in good time, we were able to propose targeted follow-up measures, and Demako is now including the alignment work in the renovation of the drive.”
According to both men, Nebest stands out for its integrated approach. “Dive inspections, concrete testing, metal inspections, mechanical engineering analyses, coating advice and records management are all handled by one organisation. There is no room for confusion. With one point of contact, we deliver an efficient approach, a complete picture and clear, actionable guidance. Our collaboration with the client here at Krammer Locks is so good that whenever an issue comes up requiring further investigation, consortium ZEEKR knows where to find us.”
A business enquiry for Nebest BV? Get in touch
Wie aan Krammersluizencomplex werkte
- main contractor
BESIXMentioned in The power of systems integration in the renovation of the Krammer Locks complex - constructionZEEKRMentioned in The power of systems integration in the renovation of the Krammer Locks complex
- system integrationINNOCYMentioned in The power of systems integration in the renovation of the Krammer Locks complex
- system integrationCPM ConsultancyMentioned in The power of systems integration in the renovation of the Krammer Locks complex
- renovationZEEKR combinationIn this story
- replacement, renovation and modificationIemantsMentioned in Modified 400-tonne lock gates improve the lockage process
- subcontractor
DISA InternationalMentioned in The foundations for a new pumping station are being laid underwater - independent baseline inspection
A-QuinMentioned in Independent baseline inspection prevents surprises - machinery safety consultant
KaderMentioned in CE marking for one of the Netherlands’ most complex lock projects - lead hydraulic engineering engineerHessel Voortman Engineering ConsultancyMentioned in A masterclass in hydraulic engineering
Keep following this
Get an email when a new story is published. No account needed.
- ProjectKrammersluizencomplex
- ThemeExtending the life of roads and civil engineering structures
- SubjectWater infrastructure
- CompanyZEEKR combination
- CompanyNebest BV
- CompanyDEMAKO NV