Ecology as the guiding principle for the renovation of the Krammersluizen complex

Text Roel van Gils Images Ara Adviesburo

Zowel de kokmeeuw als de mantelmeeuw zijn veel voorkomende vogels op het sluizencomplex.
Zowel de kokmeeuw als de mantelmeeuw zijn veel voorkomende vogels op het sluizencomplex.

The renovation of the Krammersluizen complex is about much more than engineering. The lock complex forms a unique transition between salt water and fresh water. For many fish species, being able to move between the two areas is essential. The complex and its surroundings are also home to many other species of flora and fauna, including threatened species. Ecology therefore plays an important role in the renovation, with Ara Adviesburo ensuring that ecological considerations guide this extensive project.

Ecologists now advise on almost all work at the complex. Whether it involves excavation, laying cables and pipes, or building the new sluice and fish passage, the potential impact of the work on flora and fauna is assessed each time.

Ecological working protocol

The biggest challenge? “Carefully coordinating the schedule with nature,” says Daisy Linders, an ecologist at Ara Adviesburo. “For example, work must not conflict with the breeding season of the northern vole or the migration periods of fish. To minimise disturbance as far as possible, we drew up an ecological working protocol at the preparatory stage. This sometimes leads to different choices during construction, such as pressing sheet piles into the ground rather than vibrating them in.”

Common agrimony is a vascular plant species on the Red List.

Northern vole

Ecology remains an important consideration during construction. “The new sluice and fish passage is currently being built on the mid-pier between the push-tow locks. This causes vibration and noise. We monitor the impact on the northern vole population on the central island and check whether noise levels remain within the agreed limits,” says Daisy. “The results are recorded in logbooks and provide the basis for further decisions.”

Environment and Planning Act

The complex is also home to several species of gull, bats and protected plant species on the Red List. According to Daisy, this diversity makes the work not only challenging but also special. “Under the Environment and Planning Act, the effects of major works on nature must be carefully assessed and managed. This goes far beyond protecting a single plant or animal species. It is about finding a balance between the necessary renovation and the preservation of natural values.”

The Krammersluizen project is a wonderful one for Ara Adviesburo, and for Daisy in particular, to be involved in. “It is large, complex and ecologically fascinating. Thanks to the expertise and collaboration within our team, we can continually strike the right balance between construction and nature.”

Question about this story? Ask your question

Who worked on Krammersluizencomplex

  1. main contractorBESIXMentioned in The power of systems integration in the renovation of the Krammer Locks complex
  2. constructionZEEKRMentioned in The power of systems integration in the renovation of the Krammer Locks complex
  3. system integrationINNOCYMentioned in The power of systems integration in the renovation of the Krammer Locks complex
  4. system integrationCPM ConsultancyMentioned in The power of systems integration in the renovation of the Krammer Locks complex
  5. renovationZEEKR combinationMentioned in Krammer Locks under scrutiny
  6. hydraulics partnerBosch RexrothMentioned in Smarter hydraulics give Krammersluizen extra capacity
  7. replacement, renovation and modificationIemantsMentioned in Modified 400-tonne lock gates improve the lockage process
  8. renovationSmuldersMentioned in Renovating the Netherlands’ largest concrete structure
  9. mechanical installationsDemakoMentioned in Champions League standard in mechanical engineering
  10. subcontractorDISA InternationalMentioned in The foundations for a new pumping station are being laid underwater
  11. specialistBon & MeesMentioned in The art of replacing lock gates
  12. concrete repairBE InjectMentioned in Concrete repairs under high voltage
  13. independent baseline inspectionA-QuinMentioned in Independent baseline inspection prevents surprises
  14. directorAmstelland IngenieursMentioned in From design to maintenance: an integrated approach to the Krammer Locks
  15. machinery safety consultantKaderMentioned in CE marking for one of the Netherlands’ most complex lock projects
  16. lead hydraulic engineering engineerHessel Voortman Engineering ConsultancyMentioned in A masterclass in hydraulic engineering
  17. engineering consultancyBT EngineeringMentioned in From pencil drawings to a digital blueprint
  18. engineering consultancyMBM EngineersMentioned in From pencil drawings to a digital blueprint
  19. engineering consultancyMaters & De KoningMentioned in From pencil drawings to a digital blueprint

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectKrammersluizencomplex
  • ThemeExtending the life of roads and civil engineering structures
  • SubjectSpecials
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.