A masterclass in hydraulic engineering
Text Roel van Gils Beeld Hessel Voortman Engineering Consultancy

The renovation of the Krammersluizen is one of the most complex hydraulic engineering projects in the Netherlands, with an extensive body of work on hydraulic loads. As lead hydraulic engineer on the ZEEKR consortium team, Hessel Voortman Engineering Consultancy oversees coordination across all hydraulic engineering disciplines and translates complex hydraulic loads into concrete design requirements.
The challenge starts with the fundamentals of the contract between Rijkswaterstaat and the ZEEKR consortium, Hessel explains. “Water-level differences, wave heights and flow conditions are specified in the contract, but they do not provide direct input for structural engineers. The data first needs to be converted into the actual forces and loads acting on the lock gates, sluices, levelling openings and other parts of the complex.”
Hydraulic loads
Under Hessel’s direction, the extensive body of work on hydraulic loads was developed with input from various specialists and engineering firms. He also focused on the new fish passage and discharge facility. “This facility not only contributes to water management, it also improves fish migration,” he says. “The design required extensive numerical analyses and scale-model studies. I was also responsible for the technical direction, specification and supervision of these studies.”

A scientific perspective
Hessel is currently working on various specialist issues related to construction. “By choosing the right analyses, I try to make life a little easier for the construction team,” he says. “That is my business model, really. I have a background in science, and I have always held on to that scientific perspective, particularly to help support construction.” Using advanced analyses, for example, he was able to show that some of the existing bed protection could be retained. “That saves materials, energy, construction work and risk.”
What makes the project special, according to Hessel, is the sheer number of issues that come together at a single lock complex. “New facilities, renovations to existing structures and construction issues are constantly overlapping. As chair of the hydraulic engineering consultation with Rijkswaterstaat, I also help bring technical dilemmas to the table and work towards solutions everyone can support.” In this way, in-depth hydraulic engineering expertise provides the vital link between theory and practice, helping to drive forward one of the largest lock renovation projects in the Netherlands.
Question about this story? Ask your question
Wie aan Krammersluizencomplex werkte
- main contractor
BESIXMentioned in The power of systems integration in the renovation of the Krammer Locks complex - constructionZEEKRMentioned in The power of systems integration in the renovation of the Krammer Locks complex
- system integrationINNOCYMentioned in The power of systems integration in the renovation of the Krammer Locks complex
- system integrationCPM ConsultancyMentioned in The power of systems integration in the renovation of the Krammer Locks complex
- replacement, renovation and modificationIemantsMentioned in Modified 400-tonne lock gates improve the lockage process
- subcontractor
DISA InternationalMentioned in The foundations for a new pumping station are being laid underwater - independent baseline inspection
A-QuinMentioned in Independent baseline inspection prevents surprises - machinery safety consultant
KaderMentioned in CE marking for one of the Netherlands’ most complex lock projects - lead hydraulic engineering engineerHessel Voortman Engineering ConsultancyIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectKrammersluizencomplex
- SubjectWater infrastructure
- CompanyHessel Voortman Engineering Consultancy