Temporary bridges on and over the A9 safeguard mobility
Text Roel van GilsImage Janson Bridging

Rijkswaterstaat’s A9 widening project between Badhoevedorp and Holendrecht is an iconic project in its own right, particularly for Janson Bridging. With no fewer than eight temporary bridges, four of them on the motorway, it is the Dutch division’s largest hire project to date. The project also includes several firsts. For example, it is the first time the brand-new JSB4 bridge system has been used, and the largest temporary motorway bridge ever built is being constructed right next to Amstelveen’s city centre.
A request from construction consortium VeenIX for eight temporary bridges meant that Janson Bridging Nederland also had to move quickly, acknowledges Abdelhakim el Harchaoui, Project Manager at Janson Bridging Nederland. “The project involves four bridges on the motorway bypass that has been created, and another four spanning the motorway. The bridges over the motorway differ in type and design. Two are exclusively for pedestrians and cyclists, while two carry mixed traffic. All eight temporary bridges differ in shape, length and span. They are also made up of different bridge systems, ranging from beam bridge systems such as the JSK type to plate girder bridge systems JSB1, JSB2 and the brand-new JSB4.”

Monitoring traffic loads
Janson Bridging has its own engineering department, project managers and installation crews. “We have all the expertise in-house to tackle a complex project like this quickly and efficiently,” says Marcel van Fessem, General Manager at Janson Bridging Nederland. “Communication between Janson and VeenIX is therefore very direct. We also have a huge stock of materials, which was a definite advantage given the tight timeframe for delivering everything. In response in part to enquiries from other European countries, we accelerated development of our new JSB4 bridge system for this project. The JSB-4 is an evolution of the existing JSB systems, developed specifically for motorway applications. This makes the JSB-4 system considerably stronger and more resistant to fatigue caused by the heavy volume of traffic movements. The temporary bridge is continuously monitored for traffic movements, including heavy vehicles, to assess their impact on the bridge components. This information allows us to demonstrate through calculations that the bridge is strong enough for the remainder of the project or for use on future projects.” Van Fessem says that special attention was also paid to the noise produced by the bridge during the system’s design. “The result is that the updated JSB-4 design is significantly quieter than other systems.”
Amstelveen is home to Europe’s largest temporary motorway bridge built using the new JSB4 bridge system. “At 94.5 metres long and 32.5 metres wide, it is almost the size of a football pitch,” says El Harchaoui. “The bridge actually consists of three spans, each 31.5 metres long. The longest and heaviest elements have been used in a temporary bridge measuring 81 by 12.5 metres, which consists of just two clear spans of 40.5 metres.” Van Fessem adds: “Our modular concept allows us to deliver a bespoke solution using standard modules. And we have achieved that here. There are, of course, a great many variables and interfaces to manage, but we are doing so together with VeenIX.”
Een zakelijke vraag aan JANSON BRIDGING NEDERLAND B.V.? Get in touch
Who worked on A9 Badhoevedorp – Holendrecht
- precision drilling technologyInterboor MidslandMentioned in Widening the Schipholbrug: precision drilling between parabolic prestressing tendons
- foundation specialist
KandtMentioned in Kandt, foundation specialist, delivers quality work on the A9 - welding sheet piles
Marsé MontageMentioned in Specialist welding on the A9: welding 21 kilometres of sheet piling - foundation contractor consortiumDe Vries TitanMentioned in The Netherlands’ largest anchor pile project
- foundation contractor consortiumBAUER FunderingstechniekMentioned in The Netherlands’ largest anchor pile project
- construction cost consultancy
BKS SchagenMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach - UP scaffolding system
PeriMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen - scaffolding structuresVan der PanneMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
- Type C self-drilling anchor pilesHigh 5 SolutionsMentioned in A9: Smart solution for testing anchor piles next to a sheet-pile wall
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA9 Badhoevedorp – Holendrecht
- ThemeExtending the life of roads and civil engineering structures
- SubjectRoad construction
- CompanyJANSON BRIDGING NEDERLAND B.V.