A technically challenging project with numerous stakeholders
Text Roel van Gils Image VeenIX

The widening and sunken construction of the A9 between the Badhoevedorp and Holendrecht interchanges is an impressive project being carried out by the VeenIX construction consortium on behalf of Rijkswaterstaat. Limited space, soft ground conditions, the demolition, construction and widening of numerous structures, and the construction of a sunken section right through Amstelveen make the project quite challenging. And all this in the immediate vicinity of Amsterdam and Schiphol Airport, and just a stone’s throw from several other major infrastructure projects.

VeenIX is a construction consortium specialising in the delivery of large-scale infrastructure projects. “We are always interested in projects that present a technical challenge. They give us the opportunity to put our expertise to good use,” says Jaime Carrasco Reyes, Technical Manager for the A9 at VeenIX, who has previously worked on projects in countries including Australia and the Middle East. “And the A9 is certainly challenging, not only in technical terms, but also because the road must remain open to traffic at all times. A huge volume of traffic passes through every day. We face numerous logistical challenges and have to deal with many more stakeholders, each with their own interests.”

A densely populated area
The A9 runs through the Randstad, a densely populated area. “This isn’t a motorway somewhere in the middle of the country, with no stakeholders or neighbours,” says Carrasco Reyes. “There are buildings close to the route in many places, and the motorway even runs right through Amstelveen, where we are building a 1.6-kilometre sunken section. Limited space, noise and vibration are therefore key considerations during the works. A range of measures are being taken to manage noise and vibration disturbance. For example, our schedule allows for drilling piles rather than driving them. It takes longer, but makes considerably less noise. The A9 is also one of the main gateways to Amsterdam, a European hotspot, and Schiphol Airport. All that traffic still needs to get through, despite the major works we are carrying out. The A9 is not the only major infrastructure project around Amsterdam either. Work is also under way on the A4, A10 and A12. Diversions for major works therefore have to be coordinated with all those parties to avoid cutting off the entire region. That takes considerable coordination, not just for our project, but across the whole area.”

Specialist subcontractors
The A9 project is divided into three sections. “Each section has its own specific challenges, but overall the soft ground is by far the biggest challenge,” says Carrasco Reyes. “That’s typical of the Netherlands. We work closely with specialist subcontractors who have plenty of experience in this kind of work.” The Technical Manager is highly satisfied with the professionalism of the local subcontractors and their flexibility. “It’s quite different in some other countries. Everyone here is well trained and able to respond flexibly to challenges or changes to the schedule. The only thing we can’t control here is the weather,” says Carrasco Reyes with a laugh. “But the subcontractors know how to deal with that too. They’re used to it.”
The A9 is scheduled for official completion at the end of 2027. “The western and eastern sections are expected to be completed in spring 2026. The central section, where the motorway is being built in a sunken cutting through Amstelveen, will be the last to be finished. In terms of the project’s total volume, I’d say we’re about halfway through,” says Carrasco Reyes, assessing progress.
Question about this story? Ask your question
Who worked on A9 Badhoevedorp – Holendrecht
- temporary bridges
Janson BridgingMentioned in Temporary bridges on and over the A9 safeguard mobility - precision drilling technologyInterboor MidslandMentioned in Widening the Schipholbrug: precision drilling between parabolic prestressing tendons
- foundation specialist
KandtMentioned in Kandt, foundation specialist, delivers quality work on the A9 - welding sheet piles
Marsé MontageMentioned in Specialist welding on the A9: welding 21 kilometres of sheet piling - foundation contractor consortiumDe Vries TitanMentioned in The Netherlands’ largest anchor pile project
- foundation contractor consortiumBAUER FunderingstechniekMentioned in The Netherlands’ largest anchor pile project
- construction cost consultancy
BKS SchagenMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach - UP scaffolding system
PeriMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen - scaffolding structuresVan der PanneMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
- Type C self-drilling anchor pilesHigh 5 SolutionsMentioned in A9: Smart solution for testing anchor piles next to a sheet-pile wall
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA9 Badhoevedorp – Holendrecht
- SubjectRoad construction