Road construction

A technically challenging project with numerous stakeholders

Text Roel van Gils Image VeenIX

Each sub-area has its own specific challenges, but overall the soft subsoil is the most challenging.
Each sub-area has its own specific challenges, but overall the soft subsoil is the most challenging.

The widening and sunken construction of the A9 between the Badhoevedorp and Holendrecht interchanges is an impressive project being carried out by the VeenIX construction consortium on behalf of Rijkswaterstaat. Limited space, soft ground conditions, the demolition, construction and widening of numerous structures, and the construction of a sunken section right through Amstelveen make the project quite challenging. And all this in the immediate vicinity of Amsterdam and Schiphol Airport, and just a stone’s throw from several other major infrastructure projects. 

The A9 is certainly challenging, not only in technical terms, but also because the road must remain open to traffic at all times.

VeenIX is a construction consortium specialising in the delivery of large-scale infrastructure projects. “We are always interested in projects that present a technical challenge. They give us the opportunity to put our expertise to good use,” says Jaime Carrasco Reyes, Technical Manager for the A9 at VeenIX, who has previously worked on projects in countries including Australia and the Middle East. “And the A9 is certainly challenging, not only in technical terms, but also because the road must remain open to traffic at all times. A huge volume of traffic passes through every day. We face numerous logistical challenges and have to deal with many more stakeholders, each with their own interests.”

The A9 is scheduled for official completion at the end of 2027.

A densely populated area

The A9 runs through the Randstad, a densely populated area. “This isn’t a motorway somewhere in the middle of the country, with no stakeholders or neighbours,” says Carrasco Reyes. “There are buildings close to the route in many places, and the motorway even runs right through Amstelveen, where we are building a 1.6-kilometre sunken section. Limited space, noise and vibration are therefore key considerations during the works. A range of measures are being taken to manage noise and vibration disturbance. For example, our schedule allows for drilling piles rather than driving them. It takes longer, but makes considerably less noise. The A9 is also one of the main gateways to Amsterdam, a European hotspot, and Schiphol Airport. All that traffic still needs to get through, despite the major works we are carrying out. The A9 is not the only major infrastructure project around Amsterdam either. Work is also under way on the A4, A10 and A12. Diversions for major works therefore have to be coordinated with all those parties to avoid cutting off the entire region. That takes considerable coordination, not just for our project, but across the whole area.”

Limited space, noise and vibration are therefore key considerations during the works.

Specialist subcontractors

The A9 project is divided into three sections. “Each section has its own specific challenges, but overall the soft ground is by far the biggest challenge,” says Carrasco Reyes. “That’s typical of the Netherlands. We work closely with specialist subcontractors who have plenty of experience in this kind of work.” The Technical Manager is highly satisfied with the professionalism of the local subcontractors and their flexibility. “It’s quite different in some other countries. Everyone here is well trained and able to respond flexibly to challenges or changes to the schedule. The only thing we can’t control here is the weather,” says Carrasco Reyes with a laugh. “But the subcontractors know how to deal with that too. They’re used to it.”

The A9 is scheduled for official completion at the end of 2027. “The western and eastern sections are expected to be completed in spring 2026. The central section, where the motorway is being built in a sunken cutting through Amstelveen, will be the last to be finished. In terms of the project’s total volume, I’d say we’re about halfway through,” says Carrasco Reyes, assessing progress.     

Question about this story? Ask your question

Who worked on A9 Badhoevedorp – Holendrecht

  1. steel producerArcelorMittalMentioned in Steel with a low environmental impact
  2. construction consortiumVeenIXMentioned in Steel with a low environmental impact
  3. design teamKwast ConsultMentioned in EPS structures with a low environmental cost indicator
  4. temporary bridgesJanson BridgingMentioned in Temporary bridges on and over the A9 safeguard mobility
  5. clientRijkswaterstaatMentioned in Creative drilling, sawing and demolition
  6. technical designNobleo Bouw & InfraMentioned in The project’s technical conscience
  7. foundation engineering giantVoorbij FunderingstechniekMentioned in Foundation giants join forces
  8. radar technologyTerraCartaMentioned in Locating prestressing reinforcement using radar technology
  9. Noise forecastAlcedoMentioned in Managing construction and traffic noise
  10. subcontractorKandt Aannemings- en FunderingsbedrijfMentioned in Specialist contractor and foundation company deploys diverse disciplines on large-scale, complex A9/VeenIX project
  11. precision drilling technologyInterboor MidslandMentioned in Widening the Schipholbrug: precision drilling between parabolic prestressing tendons
  12. foundation specialistKandtMentioned in Kandt, foundation specialist, delivers quality work on the A9
  13. Asset managementINNOCYMentioned in Smart asset management for a safe, high-performing A9
  14. contractorBonneveldMentioned in From cofferdams to reinforced soil
  15. clientFCCMentioned in From cofferdams to reinforced soil
  16. welding sheet pilesMarsé MontageMentioned in Specialist welding on the A9: welding 21 kilometres of sheet piling
  17. foundation contractor consortiumDe Vries TitanMentioned in The Netherlands’ largest anchor pile project
  18. foundation contractor consortiumBAUER FunderingstechniekMentioned in The Netherlands’ largest anchor pile project
  19. construction cost consultancyBKS SchagenMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach
  20. design teamNobleoMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach
  21. UP scaffolding systemPeriMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
  22. scaffolding structuresVan der PanneMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
  23. Type C self-drilling anchor pilesHigh 5 SolutionsMentioned in A9: Smart solution for testing anchor piles next to a sheet-pile wall

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectA9 Badhoevedorp – Holendrecht
  • SubjectRoad construction
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.