Road construction

The project’s technical conscience

Text Roel van GilsImage VeenIX

Luchtfoto ter hoogte van Ouderkerk aan de Amstel.
Luchtfoto ter hoogte van Ouderkerk aan de Amstel.

At the pre-tender stage, Nobleo Bouw & Infra was asked to deliver the technical design for the A9 Badhoevedorp, Holendrecht, helping to produce a strong, integrated bid. Some of the ‘Nobleans’ have remained involved in the project since the tender and continue to hold a number of key roles. Nobleo is even regarded as the project’s technical conscience. We speak to Toon Hollanders, design coordinator at Nobleo Bouw & Infra.

During the tender phase, Nobleo was part of VeenIX. “A team of 25 Nobleans developed the technical design, including design management, design leadership and technical integration,” says Hollanders. “It was an intensive, dynamic process characterised by extensive collaboration with the client and the client behind the client, Rijkswaterstaat. This is where Nobleo stands out. We are not just a purely technical consultancy, we also focus strongly on integration, communication and client service. That was the added value we brought to the tender and continue to provide today.”

Some of the ‘Nobleans’ have remained involved in the project since the tender and continue to hold a number of key roles.

At the heart of the action

Nobleo continues to play a number of important roles during the detailed design (DO) and construction design (UO) phases, and now during construction. These include integration management for the eastern section, including at Ouderkerk aan de Amstel, with five viaducts, two major bridges, a depressed section at the Holendrecht interchange (reversible lane), retaining walls and noise barriers. Hollanders says: “We also manage integration for the Schipholbrug, a highly complex replacement project involving one of the Netherlands’ largest bascule bridges, with a complex construction sequence. We also provide lead planners for the roads team, who make it possible to phase the roadworks, including the bypass alongside the excavation for the depressed section in the heart of Amstelveen, without road users noticing a thing. We were also responsible for coordinating structural safety within our scope. We carried out all the technical reviews of the design calculations during the DO phase and now provide technical advice. Finally, we work closely with the engineering consultancies engaged by VeenIX and all the other disciplines on the project, which bring a wealth of expertise. That is what makes our role so rewarding: we are effectively at the heart of the action, working with all the parties and local authorities to achieve the best result together.”

Effective traffic management and integration with the surroundings

According to Hollanders, the design solution is characterised by a traffic management plan that enables the project to be delivered with minimal disruption to road users and the surrounding area. “The design also has a low risk profile for the local area. Rijkswaterstaat deliberately chose a solution that inspired confidence. Its sensitive integration into the surroundings also shows how much importance we attach to the quality of the area. The design is now almost complete and is being handed over to the site engineering and planning teams. They can also come to us with questions or seek our help in resolving technical challenges, as we are involved in those teams too. Naturally, we always work in collaboration with the other parties involved.”

Hollanders and his team of Nobleans are proud to contribute to such an iconic project in the Netherlands, one that almost everyone has driven over at some point. “We’re really enjoying it. It’s a complex, dynamic project involving many stakeholders and international parties. By comparing perspectives and exchanging ideas, we gain surprising insights together.”     

Een zakelijke vraag aan Nobleo Bouw & Infra? Get in touch

Wie aan A9 Badhoevedorp – Holendrecht werkte

  1. steel producerArcelorMittalMentioned in Steel with a low environmental impact
  2. construction consortiumVeenIXMentioned in Steel with a low environmental impact
  3. design teamKwast ConsultMentioned in EPS structures with a low environmental cost indicator
  4. temporary bridgesJanson BridgingMentioned in Temporary bridges on and over the A9 safeguard mobility
  5. clientRijkswaterstaatMentioned in Creative drilling, sawing and demolition
  6. technical designNobleo Bouw & InfraIn this story
  7. foundation engineering giantVoorbij FunderingstechniekMentioned in Foundation giants join forces
  8. radar technologyTerraCartaMentioned in Locating prestressing reinforcement using radar technology
  9. Noise forecastAlcedoMentioned in Managing construction and traffic noise
  10. subcontractorKandt Aannemings- en FunderingsbedrijfMentioned in Specialist contractor and foundation company deploys diverse disciplines on large-scale, complex A9/VeenIX project
  11. precision drilling technologyInterboor MidslandMentioned in Widening the Schipholbrug: precision drilling between parabolic prestressing tendons
  12. foundation specialistKandtMentioned in Kandt, foundation specialist, delivers quality work on the A9
  13. Asset managementINNOCYMentioned in Smart asset management for a safe, high-performing A9
  14. contractorBonneveldMentioned in From cofferdams to reinforced soil
  15. clientFCCMentioned in From cofferdams to reinforced soil
  16. welding sheet pilesMarsé MontageMentioned in Specialist welding on the A9: welding 21 kilometres of sheet piling
  17. foundation contractor consortiumDe Vries TitanMentioned in The Netherlands’ largest anchor pile project
  18. foundation contractor consortiumBAUER FunderingstechniekMentioned in The Netherlands’ largest anchor pile project
  19. construction cost consultancyBKS SchagenMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach
  20. design teamNobleoMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach
  21. UP scaffolding systemPeriMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
  22. scaffolding structuresVan der PanneMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
  23. Type C self-drilling anchor pilesHigh 5 SolutionsMentioned in A9: Smart solution for testing anchor piles next to a sheet-pile wall

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectA9 Badhoevedorp – Holendrecht
  • SubjectRoad construction
  • CompanyNobleo Bouw & Infra