Smart asset management for a safe, high-performing A9
Text Suzanne van Gaale Image Rijkswaterstaat

INNOCY plays an important role in the A9 project between Badhoevedorp and Holendrecht. The consultancy and engineering firm is responsible for managing and maintaining the A9 during the construction phase. In practice, this means ensuring that everything on and around the ‘old’ A9 can continue to operate.
“The biggest challenge is maintaining a busy stretch of motorway while the new A9 is being built at the same time,” says Pim Bos, Maintenance Manager at INNOCY. VeenIX is widening and lowering the A9 on behalf of Rijkswaterstaat. “This motorway between Badhoevedorp and Holendrecht is an important traffic route. There is little room to work, and everything built has to be of high quality so that it lasts. At Amstelveen, the A9 will even run in a cutting, which is technically complex.” INNOCY has been involved in the project from the outset. VeenIX asked the consultancy and engineering firm to manage the entire asset management process, from strategy and planning through to delivery. “In practical terms, this means maintaining the road’s performance in line with Rijkswaterstaat’s requirements,” Pim explains. “Meanwhile, many parties are working on the new road. At a strategic level, we focus on finding the right balance between asset performance, risk and cost, so that the road is built and managed intelligently. We also take care of day-to-day management and maintenance, while looking to the longer term. Everything must still meet the agreed quality standards in 2040.”
Cost clarity and effective maintenance
INNOCY has extensive experience with similar projects, including the A9 Gaasperdammerweg and the A24 Blankenburgverbinding. This expertise, combined with close collaboration with all the parties involved, makes it possible to plan maintenance intelligently. This minimises disruption to traffic and keeps all components performing optimally.

Smart choices to reduce costs and risks
In asset management, it is important to strike the right balance between risks, performance and costs. That is why INNOCY makes smart choices wherever possible and necessary. Asset Manager Daan Jenken gives the movable Schipholbrug as an example. “Some bridge components need maintenance. This has to be taken into account at the design stage. Those components must be accessible without having to close the motorway. We pay attention to this and contribute our ideas.” Another example is the choice of lighting along the road. “Do you choose cheaper lights that have to be replaced six times by 2040? Or slightly more expensive ones that only need replacing once? Every choice, large or small, has an impact. When you cost everything out on a project as large as the A9, the total savings can be substantial.”
Maintenance starts after construction
Once construction of the A9 is complete, which is scheduled for 2027, the maintenance phase will begin. INNOCY will remain involved in maintenance for a further two years. In 2029, INNOCY will hand the work over to another party, SPC. Jenken says: “In 2027, we will have a completed project, but we will not actually hand it over until two years later. We will then demonstrate that everything meets the requirements and is of good quality.”
Question about this story? Ask your question
Who worked on A9 Badhoevedorp – Holendrecht
- temporary bridges
Janson BridgingMentioned in Temporary bridges on and over the A9 safeguard mobility - precision drilling technologyInterboor MidslandMentioned in Widening the Schipholbrug: precision drilling between parabolic prestressing tendons
- foundation specialist
KandtMentioned in Kandt, foundation specialist, delivers quality work on the A9 - Asset managementINNOCYIn this story
- welding sheet piles
Marsé MontageMentioned in Specialist welding on the A9: welding 21 kilometres of sheet piling - foundation contractor consortiumDe Vries TitanMentioned in The Netherlands’ largest anchor pile project
- foundation contractor consortiumBAUER FunderingstechniekMentioned in The Netherlands’ largest anchor pile project
- construction cost consultancy
BKS SchagenMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach - UP scaffolding system
PeriMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen - scaffolding structuresVan der PanneMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
- Type C self-drilling anchor pilesHigh 5 SolutionsMentioned in A9: Smart solution for testing anchor piles next to a sheet-pile wall
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA9 Badhoevedorp – Holendrecht
- SubjectRoad construction
- CompanyINNOCY





















