Specialist contractor and foundation company deploys diverse disciplines on large-scale, complex A9/VeenIX project

Text Susan PeekImage Kandt bv

Materieel en mensen van Kandt kunnen uitstekend werken op lastig bereikbare plekken, zoals bij de Schipholbrug/A9 waar LeKa-palen vanaf een ponton geboord worden.
Materieel en mensen van Kandt kunnen uitstekend werken op lastig bereikbare plekken, zoals bij de Schipholbrug/A9 waar LeKa-palen vanaf een ponton geboord worden.

The A9 Badhoevedorp–Holendrecht section is the final part of the SAA programme (Schiphol-Amsterdam-Almere). Consortium VeenIX is delivering the works together with several other parties. One of the companies it selected was Kandt Aannemings- en Funderingsbedrijf.

Working from the water: no challenge is too great for Kandt.

“A large and complex project like this requires several parties for specialist phases and scopes,” says Willem de Meijer, operations manager at Kandt. “VeenIX took advice on which parties were best placed to deliver specific scopes, and we’re pleased to have been awarded a substantial share of the ever-growing scope.”

Working close to the motorway, where foundation equipment without a leader is the preferred choice.

Specialist expertise

“One of the challenges on this project is that much of the work has to be carried out in an urban area with limited space,” says Willem. “The important A9 must also remain open to traffic throughout construction, which means some of the work has to be done at night and at weekends. Delivering everything properly in hard-to-reach locations and in accordance with specific guidelines requires specialist expertise and the right equipment. Fortunately, Kandt has an extensive fleet of equipment and the right skilled people, enabling us to provide a suitable solution for every specific project.”

Sheet-pile structures for piers 

“We are installing various sheet-pile structures, some in areas with height restrictions, for the concrete work on the piers of the Schipholbrug, one of the structures along this section. Because of the height restrictions, the sheet piles are installed in sections and welded together. We use a silent piler to press the sheet piles into the ground without vibration.”

LeKa piles drilled from a pontoon and HF/VM sheet piling installed at KW007/A9.

LeKa piles at the Schipholbrug structure 

For the widening of the Schipholbrug and the renovation of the two bascule basements in the structure, Kandt installed a large number of temporary and permanent LeKa grout-injection piles. “We drilled around 300 temporary piles (Ø508 mm with a wall thickness of 12.5 mm), on which the temporary working platforms were built. We will, of course, drill these out again afterwards,” says Willem, continuing: “For the widening of the structure itself, we installed no fewer than 410 permanent piles (Ø508 and Ø610 mm) for the piers. For the 610 mm piles, we used a drill bit with a diameter of 860.” Willem says this is fairly unusual, as the market is accustomed to drilling piles with a maximum diameter of 559 mm in areas with limited headroom. Kandt has developed a suitable machine for 610 mm piles.

Working from land: installing sheet piling for a bascule basement at Schipholburg/A9.

Combi-wall piles for bascule basements 

Kandt also installed two temporary drilled combi-wall cofferdams for the bascule basements of the Schipholbrug, using combi-wall tubes (Ø559 mm with a wall thickness of 30 mm) and drilled combi-wall piles (Ø762 mm with a wall thickness of 25 mm). Kandt also installed the bracing frames for these temporary cofferdams. Most of this work was carried out from pontoons on the water, designed for the purpose, using a range of equipment. “The work is carried out to execution classes 2 and 3, as required by Rijkswaterstaat, with materials traceability. As a subcontractor, we have to comply with the ROK (Guidelines for the Design of Structures, drawn up by Rijkswaterstaat). Guidelines for safe lifting in public areas also apply to this project.”

Specialist expertise is becoming increasingly important 

Work on the Schipholbrug is progressing well, and more and more work is being added to Kandt’s scope. Willem concludes: “This is another project where we can really show what Kandt is capable of. With specialist equipment and well-trained skilled workers who are experienced in hard-to-reach environments, we can take on projects with requirements for vibration-free or low-noise working, or with limited headroom, and deliver them to the client’s satisfaction.”   

A business enquiry for Kandt Aannemings- en Funderingsbedrijf BV? Get in touch

Who worked on A9 Badhoevedorp – Holendrecht

  1. steel producerArcelorMittalMentioned in Steel with a low environmental impact
  2. construction consortiumVeenIXMentioned in Steel with a low environmental impact
  3. design teamKwast ConsultMentioned in EPS structures with a low environmental cost indicator
  4. temporary bridgesJanson BridgingMentioned in Temporary bridges on and over the A9 safeguard mobility
  5. clientRijkswaterstaatMentioned in Creative drilling, sawing and demolition
  6. technical designNobleo Bouw & InfraMentioned in The project’s technical conscience
  7. foundation engineering giantVoorbij FunderingstechniekMentioned in Foundation giants join forces
  8. radar technologyTerraCartaMentioned in Locating prestressing reinforcement using radar technology
  9. Noise forecastAlcedoMentioned in Managing construction and traffic noise
  10. subcontractorKandt Aannemings- en FunderingsbedrijfIn this story
  11. precision drilling technologyInterboor MidslandMentioned in Widening the Schipholbrug: precision drilling between parabolic prestressing tendons
  12. foundation specialistKandtMentioned in Kandt, foundation specialist, delivers quality work on the A9
  13. Asset managementINNOCYMentioned in Smart asset management for a safe, high-performing A9
  14. contractorBonneveldMentioned in From cofferdams to reinforced soil
  15. clientFCCMentioned in From cofferdams to reinforced soil
  16. welding sheet pilesMarsé MontageMentioned in Specialist welding on the A9: welding 21 kilometres of sheet piling
  17. foundation contractor consortiumDe Vries TitanMentioned in The Netherlands’ largest anchor pile project
  18. foundation contractor consortiumBAUER FunderingstechniekMentioned in The Netherlands’ largest anchor pile project
  19. construction cost consultancyBKS SchagenMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach
  20. design teamNobleoMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach
  21. UP scaffolding systemPeriMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
  22. scaffolding structuresVan der PanneMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
  23. Type C self-drilling anchor pilesHigh 5 SolutionsMentioned in A9: Smart solution for testing anchor piles next to a sheet-pile wall

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectA9 Badhoevedorp – Holendrecht
  • ThemeUnderground construction
  • SubjectFoundations / Site investigation
  • CompanyKandt Aannemings- en Funderingsbedrijf BV
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.